Resolved
RESOLVED : to support the assessment of Biffa’s overall performance of the household waste collection, street cleansing and ancillary services contract in 2018 as “Fair”.
Joint Scrutiny Committee decided this item on Tuesday 10 September 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : to support the assessment of Biffa’s overall performance of the household waste collection, street cleansing and ancillary services contract in 2018 as “Fair”.
Joint Scrutiny Committee Report
Report of Head of Housing and Environment Author: Ian Matten Tel: 01235 422113 E-mail: [email protected] Vale Cabinet Member responsible: Jenny Hannaby South Cabinet Member responsible: David Rouane Tel: [phone removed] Tel: [phone removed] E-mail: [email protected] E-mail: [email protected] To: JOINT SCRUTINY COMMITTEE DATE: 10 September 2019
Performance review of Biffa Municipal Plc - 2018 RECOMMENDATION That scrutiny committee considers Biffa Municipal Plc (Biffa) performance in delivering the household waste collection, street cleansing and ancillary services contract for the period 1 January 2018 to 31 December 2018 and makes any comments before a final assessment on performance is made.
PURPOSE OF REPORT 1. To ask scrutiny committee for its views on the performance of Biffa in providing the household waste collection, street cleansing and ancillary services in South Oxfordshire and Vale of White Horse for the period 1 January 2018 to 31 December 2018.
STRATEGIC OBJECTIVES 2. The service contributes to Vale’s strategic objective of running an efficient council and continue to improve our environment and South’s objective of delivering services that reflect residents needs and build thriving communities by making communities clean and safe.
BACKGROUND 3. Managing contractor performance is essential for delivering the councils’ objectives and targets. Since a high proportion of the councils’ services are outsourced, the councils cannot deliver high quality services to its residents unless its contractors are performing well. Using an agreed framework and working jointly with contractors to review performance regularly is therefore essential.
4. The councils’ process for managing contractor performance focuses on continuous improvement and action planning. The council realises that the success of the framework depends on contractors and the council working together to set and review realistic, jointly agreed and measurable targets.
5. The overall framework is designed to be
a way for the council to consistently measure contractor performance, to help highlight and resolve operational issues
flexible enough to suit each contract, including smaller contracts which may not require all elements of the framework
a step towards managing risk more effectively and improving performance through action planning.
OVERVIEW OF THE REVIEW FRAMEWORK 6. Evaluating contractor performance has four elements:
1. performance measured against key performance targets (KPT) 2. customer satisfaction with the total service experience 3. council satisfaction as client 4. a summary of strengths and areas for improvement, feedback from the contractor on the overall assessment plus the contractor’s suggestions of ways in which the council might improve performance.
7. The first three dimensions are assessed, and the head of service makes a judgement of classification. The fourth element is a summary of strengths and areas for improvement and includes contractor feedback. Where some dimensions are not relevant, or difficult to apply fairly to certain types of contract, the framework may be adjusted or simplified at the discretion of the head of service.
8. A summary of officer’s assessment in 2018 for each dimension, the overall assessment and a comparison against 2017 can be seen in the following table:
2017 2018
Key Performance Target Fair Fair
Customer satisfaction Good Good
Council satisfaction Fair Fair
Overall officer Fair Fair assessment 9. Biffa were awarded the joint waste contract in December 2008 with a commencement date in South Oxfordshire of June 2009. The Vale of White Horse element of the contract commenced in October 2010. The council in 2013 decided, in accordance with the conditions of contract to extend the contract for a seven-year period. The contract is due to end in June 2024.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Performance review of Biffa Municipal Plc: 2018Report | 315 KB | DownloadRead as text |
Follow Joint Scrutiny Committee at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Minutes of the last meetingThe minutes of the meeting on 23 June 2026 were agreed as a correct record, and the chair would sign them as such. | Agreed | Open |
| 23 Jun 2026 | Minutes of the last meetingThe minutes of the last meeting of Joint Scrutiny Committee (JSC) on 23 February 2026 were agreed as a correct record... | Agreed | Open |
| 23 Feb 2026 | Minutes of the last meetingThe minutes of the meetings held on 10 November 2025 and 1 December 2025 were agreed as correct records, and the chai... | Agreed | Open |
| 10 Nov 2025 | Minutes of the last meetingThe minutes of the meeting held on 7 July 2025 were agreed as a correct record, and the chair would sign them as such. | Agreed | Open |
| 7 Jul 2025 | Minutes of the last meetingThe minutes of the meeting held on 24 February 2025 were agreed as a correct record and the Chair will sign them as s... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.