Cabinet Report Report of Head of Finance Author: Richard Spraggett Telephone: 01235 422505 Textphone: 18001 01235 422505 E-mail: [email protected] Wards affected: All Cabinet member responsible: Andrew Crawford Tel: Tel: 01235 772134 E-mail: [email protected] To: CABINET Date: 4 October 2019
Budget monitoring April – May 2019 Recommendation Cabinet is recommended to note the contents of the report
Purpose of Report 1. To report the revenue and capital expenditure against budget for the period April to May 2019.
Corporate Objectives 2. The allocation of financial resources within the revenue and capital budgets needs to match the objectives agreed by the council. The budget monitoring report shows how these resources have been during the first two months of the financial year.
Background 3. Council agreed in setting the 2019/20 budget to increase the management accounting function of the council to support more frequent revenue and capital budget monitoring activity in year, including the re-introduction of formal reporting to Cabinet of performance against budget three times per year.
4. The formal reports will cover performance to the end of period two (May), period five (August) and period eight (November). These time periods have been chosen so that formal budget monitoring activity does not clash with peaks in the management accounting team’s workload on budget setting. Revenue budget monitoring
5. On 13 February 2019, Council agreed its revenue budget for 2019/20. For revenue service expenditure, Council agreed to a net cost of services of £15.360 million. In reviewing in-year financial performance, the focus is on two things:
Comparing expenditure and income for the year to date (in the case of this report for April and May 2019), against the “profiled” working1 budget for the year to date. The profiled working budget is the proportion of the budget that would have been expected to have been incurred at the end of May 2019
Reviewing the outturn forecast of expenditure and income at year end compared to the working budget for the whole year.
6. Appendix 1 is a summary, by service, of both of these. Where variances of over £50,000 are identified, in either net expenditure to date against profiled working budget, or in forecast net expenditure against whole year budget, then heads of service have provided commentary for the reasons. It should be noted that the budgets do not include any revenue carry forwards from the previous financial year which had not been agreed at the time the budget reports were run.
7. At this early stage in the financial year there is little to report, other than in Planning where income is forecast to be £200,000 below budget, due to adverse market conditions. This will be monitored as the financial year progresses.
Capital budget monitoring
8. On 13 February 2019, Council agreed a capital programme for 2019/20 of £9.096 million.
9. At the end of May 2019, the capital programme had increased to £10.042 million. This reflects the capital programme as approved by Council, plus slippage from the previous financial year, additions and deletions.
10. As shown in appendix 2, spend against the latest capital programme2 was £198,987. At this stage no forecast year end underspends against the capital programme have been identified.
Financial, legal and any other implications 11. The financial implications are as set out in the body of the report. There are no other implications of this report.
Conclusion 12. At this early stage of the financial year only a limited number of year end variances against budget have been identified. However, as budget monitoring activity will be more frequent during 2019/20, it is anticipated that such variances will be identified
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget monitoring April: May 2019Report | 128 KB | DownloadRead as text |
PDF |
ValeBudgetMonitoringReportMay2019ForFocusReport | 93 KB | Download |
PDF |
ValeCapitalreportMay2019v2Report | 77 KB | Download |
Follow Cabinet at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Jul 2026 | MinutesThe minutes of the Cabinet meeting on 5 June 2026 were agreed as a correct record and the chair would sign them as such. | Agreed | Open |
| 3 Jul 2026 | Business Rates – Local Discretionary Relief scheme for 2026/2027That Cabinet (a) Approves the introduction of a local discretionary relief scheme, providing further relief for eligi... | Approved | Open |
| 3 Jul 2026 | At the Heart of the Vale: Annual Delivery Plan End of Year Report 2025-26That cabinet approves the Annual Delivery Plan End of Year Report 2025-26. | Approved | Open |
| 3 Jul 2026 | Thames Valley Spatial Development Strategy (SDS) Development and GovernanceThat Cabinet: · Notes the establishment of a partnership with the councils covering Oxfordshire, Berkshire and Swindo... | Decided | Open |
| 3 Jul 2026 | Revised Land and Property Asset Disposal PolicyRESOLVED : That Cabinet (a) Approves the revised Joint Property Asset Disposal policy. (b) Approves the revised Joint... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.