Resolved
RESOLVED to note the Budget Monitoring Report for April to September 2023.
Cabinet noted this item on Tuesday 19 December 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the Budget Monitoring Report for April to September 2023.
Cabinet Report Report of Head of Finance Author: Richard Spraggett Telephone: [phone removed] E-mail: [email protected] Wards affected: All Vale Cabinet member responsible: Andrew Crawford Tel: [phone removed] E-mail: [email protected] To: CABINET Date: 19 December 2023
Budget monitoring April 2023 – September 2023 Recommendation Cabinet is recommended to note the contents of the report
Purpose of report 1. To report the revenue and capital expenditure against budget for the period April 2023 to September 2023 and the latest year end outturns forecast by heads of service.
Corporate objectives 2. The allocation of financial resources within the revenue and capital budgets needs to match the objectives agreed by the council. The budget monitoring report shows how these resources have been allocated during the first six months of the financial year.
Background 3. This report reviews the council’s revenue and capital expenditure performance to the end of month six (September). Year-end outturn forecasts were worked on during October and are based on heads of service’s best knowledge at that time.
Revenue budget monitoring
4. On 15 February 2023, Council agreed a net revenue budget for 2023/24 of £17.385 million. This has subsequently increased to £18.851 million. This reflects the carry forward of unspent one-off project budgets from 2023/23 and additional grant funded budgets. 5. Table 1 below shows, summarised at service level, both the revenue position as at the end of September 2023 and the forecast position at year end.
Table 1: Revenue budget monitoring position as at September 2023
Service Working Spend to Variance Working Forecast Variance budget Date budget spend for year to full year year date £000 £000 £000 £000 £000 £000 Strategic management team 398 412 14 797 791 (6) Corporate services 1,620 1,739 119 3,223 3,203 (20) Development and corporate landlord 774 891 117 916 823 (93) Finance 592 1,959 1,367 890 936 46 Housing and environment 2,309 2,022 (287) 6,032 6,124 92 Legal and democratic 921 1,021 100 1,770 1,786 16 Partnerships 1,056 819 (237) 2,113 2,113 0 Planning 155 459 304 312 908 596 Policy and programmes 1,708 1,735 27 3,416 2,541 (875) Contingency (334) 0 334 (618) 0 618 Total 9,199 11,057 1,858 18,851 19,225 374
6. The forecast variance is further broken down in table 2 below.
Table 2: summary of forecast major variances against revenue budget
Working Working Forecast Variance Employee Other budget budget after spend for costs full year carry year Service forwards removed £000 £000 £000 £000 £000 £000 Strategic management 797 797 791 (6) (34) 28 Corporate services 3,223 3,223 3,203 (20) (102) 82 Development & corporate landlord 916 858 823 (35) (20) (15) Finance 890 890 936 46 48 (2) Housing & environment 6,032 6,032 6,124 92 (30) 122 Legal & democratic 1,770 1,770 1,786 16 (36) 52 Partnerships 2,113 2,113 2,113 0 0 0 Planning 312 312 908 596 (25) 621 Policy & programmes 3,416 2,653 2,541 (112) 54 (166) Contingency (618) (618) 0 618 718 (100) 18,851 18,030 19,225 1,195 573 622
7. Excluding carry forwards of £0.821 million the projected overspend is forecast to be £1.2 million. Treasury income however is anticipated to be ahead of budget by £2 million and net expenditure is therefore overall forecast to be under budget.
Budgets forecast to be carried forward to 2024/25
8. As detailed above there is forecast to be slippage of £0.821 million in one-off budgets. These will be requested as carry forwards at the end of the financial year. These carry forwards are shown in appendix 1. Employee costs
9. At this stage of the year, employee costs are forecast to be overspent by £573,000. Latest forecasts indicate that employee costs will be underspent by £145,000. However, the managed vacancy factor included in the budget, which assumed employee costs would be 95 per cent of budget, was £718,000, leading to the resulting £573,000 overspend. Key employee cost variances are as follows:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 187 KB | Download |
PDF |
Budget Monitoring: quarter 2 2023/24Report | 246 KB | DownloadRead as text |
Follow Cabinet at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Jul 2026 | MinutesThe minutes of the Cabinet meeting on 5 June 2026 were agreed as a correct record and the chair would sign them as such. | Agreed | Open |
| 3 Jul 2026 | Business Rates – Local Discretionary Relief scheme for 2026/2027That Cabinet (a) Approves the introduction of a local discretionary relief scheme, providing further relief for eligi... | Approved | Open |
| 3 Jul 2026 | At the Heart of the Vale: Annual Delivery Plan End of Year Report 2025-26That cabinet approves the Annual Delivery Plan End of Year Report 2025-26. | Approved | Open |
| 3 Jul 2026 | Thames Valley Spatial Development Strategy (SDS) Development and GovernanceThat Cabinet: · Notes the establishment of a partnership with the councils covering Oxfordshire, Berkshire and Swindo... | Decided | Open |
| 3 Jul 2026 | Revised Land and Property Asset Disposal PolicyRESOLVED : That Cabinet (a) Approves the revised Joint Property Asset Disposal policy. (b) Approves the revised Joint... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.