Resolved
to approve the award of the contract for a new transfer station facility to handle the council’s dry mixed recycling (DMR) to the preferred bidder. The contract would run for a minimum of five years, starting in June 2026.
Cabinet approved this item on Friday 29 November 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
to approve the award of the contract for a new transfer station facility to handle the council’s dry mixed recycling (DMR) to the preferred bidder. The contract would run for a minimum of five years, starting in June 2026.
Cabinet Report
Report of Head of Housing and Environment Author: William Maxwell Telephone: [phone removed]
E-mail: [email protected]
Wards affected: All Vale Cabinet member responsible: Cllr. Coleman. Tel: [phone removed] E-mail: [email protected] To: Vale of White Horse Cabinet Meeting Dates: 29 November 2024
Waste Transfer Station Contract Award Recommendation(s) (a) That Cabinet approves the award of the contract for a new transfer station facility to handle the council’s dry mixed recycling (DMR) to the preferred bidder. The contract would run for a minimum of five years, starting in June 2026.
Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) Yes Yes Yes No
Signing off Emma Creed Nicholas Kim Hall Lorne Grove officer Bennett Purpose of report 1. The purpose of this report is to seek approval to award a contract for the provision of a waste transfer station to the preferred bidder, as shown in confidential Appendix 1.
Corporate objectives Vale:
• Tackling the Climate emergency
• Building Stable Finances.
Background 2. The councils as waste collection authorities (WCA) operate a shared household waste collection service. This is currently subject to a contractual arrangement with Biffa which runs until the end of June 2026, who provide a vehicle depot and transfer station (a facility for bulking) at Culham. This site is earmarked for redevelopment and access to a new vehicle depot and transfer facility will therefore be required from June 2026. The provision of the two facilities has been split for operational and commercial reasons.
3. The current waste transfer facilities are only used for Dry Mixed Recyclate (DMR) which is the co-mingled recyclable waste stream collected from households. The non- recyclable (residual), garden waste and food waste all have existing in-district transfer points which are managed by Oxfordshire County Council as the waste disposal authority (WDA) and aren’t therefore included in this contract or as part of this report.
4. The transfer facility makes up a key piece of infrastructure required for the effective operation of waste collection services to residents. The transfer facility will handle DMR as it is transferred from the Rear Compaction Vehicles (RCVs), bulked up and then loaded onto Heavy Goods Vehicles (HGVs) to be transported to a Material Recovery Facility (MRF) for reprocessing. Without it, each collection vehicle would be required to deliver the collected DMR directly to a MRF. However, because there are no operating MRFs within Oxfordshire, this would make the service undeliverable due to the distances involved and increase in cost, time and carbon to the service.
5. The cabinet paper, dated: 4 February 2022 (Vale), delegated authority to the Deputy Chief Executive – Place to explore options to secure a waste depot and other necessary associated infrastructure. An ICMD in May 2024 outlined the reasons why a procurement should be undertaken rather than the councils develop their own transfer station and secured approval to go out to procurement for the provision of access to a transfer element and associated contract. Vale
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Waste Transfer Station Contract AwardReport | 128 KB | DownloadRead as text |
Follow Cabinet at Vale of White Horse and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Jul 2026 | MinutesThe minutes of the Cabinet meeting on 5 June 2026 were agreed as a correct record and the chair would sign them as such. | Agreed | Open |
| 3 Jul 2026 | Business Rates – Local Discretionary Relief scheme for 2026/2027That Cabinet (a) Approves the introduction of a local discretionary relief scheme, providing further relief for eligi... | Approved | Open |
| 3 Jul 2026 | At the Heart of the Vale: Annual Delivery Plan End of Year Report 2025-26That cabinet approves the Annual Delivery Plan End of Year Report 2025-26. | Approved | Open |
| 3 Jul 2026 | Thames Valley Spatial Development Strategy (SDS) Development and GovernanceThat Cabinet: · Notes the establishment of a partnership with the councils covering Oxfordshire, Berkshire and Swindo... | Decided | Open |
| 3 Jul 2026 | Revised Land and Property Asset Disposal PolicyRESOLVED : That Cabinet (a) Approves the revised Joint Property Asset Disposal policy. (b) Approves the revised Joint... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.