Operational Net Zero Annual Progress Report

Decided Executive 1 paper

AI summaryVale Cabinet notes 12% cut in operational carbon emissions since 2019/20, but says the 2030 net zero target is unlikely to be met due to reorganisation and waste fleet challenges.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCabinet noted emissions progress; 2030 target unlikely
Money£7.45m waste vehicle capital budgetPer council, like-for-like replacements
What happens nextAnnual net zero progress reporting continuesPer Nature and Climate Action Plan
Who it affectsAll Vale of White Horse residentsCouncil operations and future unitary authority

What was decided

Cabinet noted a 12 per cent reduction in operational carbon emissions since the 2019/20 baseline and 45 per cent since 2009/10. Report P5, P14

Cabinet received five modelled scenarios showing that the 2030 operational net zero target will not be met on current progress, with the council still a net emitter in 2029/30. Report P57, P75, P76

Why

Local Government Reorganisation is delaying longer-term decarbonisation investment and the Didcot Gateway office move has been shelved. Report P8, P24, P25, P27

Electric Refuse Collection Vehicles over 15 tonnes are not yet proven for the council's rural routes, so most large waste trucks will be diesel and run for their full eight-year life. Report P20, P21, P31, P32

No further rounds of the Public Sector Decarbonisation Scheme are being funded by government, limiting options for buildings such as The Beacon and Abbey Meadows Pool. Report P27

What happens next

Continue committed decarbonisation of Faringdon, Wantage and White Horse Leisure and Tennis Centre, expected to deliver over 25 per cent operational emissions savings by 2026. Report P16, P37

Take delivery of new electric and ICE council fleet vehicles by end of December 2025 and an electric 3.5T tipper from November 2025. Report P32, P43

Open the new waste vehicles depot at Great Haseley in June 2026, with at least ten commercial EV charging points and ducting for a full electric fleet. Report P29, P43, P56, P57

The money

  • £7.45m per council Capital budget for waste vehicle procurement over 2024 to 2028, based on like-for-like replacements Report P47
  • £30m Indicative cost of replacing the whole waste fleet with EVs at today's prices, cost shared between South and Vale Report P41
  • £400,000 to £500,000 Cost per large electric Refuse Collection Vehicle Report P40
  • £60,000 to £312,000 Cost range to replace the rest of the waste fleet, from an electric van to an electric food waste truck Report P40

Options considered

  • Chosen: Scenario 1: Committed building decarbonisation of three leisure centres. Already in progress; estimated 43 per cent reduction from 2019/20 baseline by 2029/30 Report P37, P38
  • Chosen: Scenario 2: Transition to low carbon council fleet (excluding waste). Captured in NCAP action ONZ17; estimated 2.8 tonnes CO2e saving per year by 2027/28 Report P39, P46
  • Chosen: Scenario 3: Transition to low carbon waste fleet in current procurement period. Larger trucks will still be ICE; estimated 45 per cent reduction from 2019/20 baseline by 2029/30 Report P49, P51
  • Chosen: Scenario 4: New waste vehicles depot at Great Haseley. Adds around 28 per cent to annual waste fleet emissions; estimated 34 per cent reduction from 2019/20 baseline by 2029/30 Report P59, P63
  • Chosen: Scenario 5: Future transition of waste fleet to low carbon by 2034/35. Decision sits with a future unitary authority; estimated 65 per cent reduction from 2019/20 baseline by 2034/35 Report P64, P65
  • Rejected: Purchase carbon credits to offset residual emissions from 2030. Vale cannot commit to offsetting post 2028 ahead of Local Government Reorganisation Report P76, P80
  • Rejected: Continue with the Didcot Gateway office move. Project no longer being progressed due to upcoming changes to council structures under LGR, though planning permission remains in place Report P25

Implications

  • Climate: Council will still be a net emitter of carbon in 2029/30 on current modelled trajectory, so the 2030 operational net zero target will not be met without offsetting. Report P75, P76
  • Financial: No financial implications arise directly from the report itself; replacing ICE waste vehicles with EVs costs around twice as much as the current ICE replacement. Report P40, P77
  • Legal: No legal implications are anticipated as a result of this report. Report P78
  • Equalities: An Equality Impact Assessment has been completed and no implications were identified. Report P81
  • Risk: Six significant risks are identified, including LGR-driven delays to longer-term decarbonisation, failure to secure funding, future baseline rises from new assets, grid capacity delays, lack of suitable electric waste vehicles, and rising carbon credit costs. Report P82, P83, P84, P85, P86, P87, P88, P89
  • Staffing: The council's Climate Emergencies Advisory Committee has recommended good practice principles for future offsetting decisions. Report P92

Who and where

  • Vale of White Horse District Council as the current operating authority Report P4, P12
  • Future unitary authority or authorities created under Local Government Reorganisation Report P8, P50, P65
  • South Oxfordshire District Council, which shares the waste fleet and depot plans Report P29, P36
  • Waste contractor operating from the new Great Haseley depot Report P19
  • Residents and businesses served by the council's waste collection service, including 1300 additional properties Report P10

Timeline

  • 2019: Vale of White Horse declared a Climate Emergency Report P12
  • 2009/10: Baseline year for Greenhouse Gas emissions reporting, at 5588 tCO2e Report P8, P14
  • 2019/20: Baseline year for the Climate Action Plan, at 3502 tCO2e Report P12, P14
  • March 2025: Overall council emissions measured at 3073 tCO2e, a 6 per cent increase on the previous year Report P8, P10
  • November 2025: New electric 3.5T tipper scheduled to be operational Report P22, P76
  • End of December 2025: Five new facilities vehicles to be delivered, four of them EVs Report P31
  • 2025/26 to 2027/28: Remaining waste vehicle procurement rounds, with up to eight more EVs potentially bought Report P37, P78
  • June 2026: New waste vehicles depot at Great Haseley due to become operational with EV charging infrastructure Report P19, P44
  • 2026: Committed leisure centre decarbonisation expected to deliver over 25 per cent operational emissions savings Report P10
  • 2028: Anticipated point at which a new unitary council could be in place under LGR Report P7, P57
  • 2029/30: Council's operational net zero target date; on current trajectory the council will still be a net emitter Report P26, P30, P63
  • 2034/35: Projected timing of the next waste vehicle procurement cycle when current replacements reach end of life Report P9, P64, P65

Plain English for the jargon

  • Operational net zero: The point at which the council's own operations produce no net carbon emissions, separate from emissions across the wider district.
  • tCO2e: Tonnes of carbon dioxide equivalent, a standard unit for comparing greenhouse gas emissions.
  • LGR: Local Government Reorganisation, the restructuring of councils in England including in Oxfordshire.
  • NCAP: Joint Nature and Climate Action Plan 2025-29 covering South Oxfordshire and Vale of White Horse.
  • eRCV: Electric Refuse Collection Vehicle.
  • PSDS: Public Sector Decarbonisation Scheme, government grant funding for public sector heat decarbonisation.
  • HVO: Hydrotreated Vegetable Oil, a biofuel that can replace diesel as a transition fuel.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item180

Resolved

RESOLVED (a) That Cabinet notes the progress made in reducing the council’s operational carbon emissions. These have reduced by 12 per cent since the council’s Climate Action Plan baseline year of 2019/20 and by 45 per cent since Greenhouse Gas reporting commenced in 2009/10.
Word for word from the decision Vale of White Horse published for this meeting. Source: democratic.whitehorsedc.gov.uk

Follow this further

Built from Vale of White Horse's papers

What the report saysPro

Report to Cabinet

Cabinet Report

Report of Head of Policy and Programmes Author: Dominic Lamb E-mail: [email protected] Wards affected: All

Vale Cabinet member responsible: Hayleigh Gascoigne Tel: Cllr Hayleigh Gascoigne E-mail: [email protected]

To: CABINET Date: 10 October 2025

Operational Net Zero Annual Progress Report Recommendation(s) (a) That Cabinet notes the progress made in reducing the council’s operational carbon emissions. These have reduced by 12 per cent since the council’s Climate Action Plan baseline year of 2019/20 and by 45 per cent since Greenhouse Gas reporting commenced in 2009/10.

Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) No No Yes No

Signing off Nicole Vivien Heather Lorne Grove officer Tyreman Williams Saunders Purpose of report 1. This report reviews the council’s progress towards the 2030 target for achieving net zero carbon in its own operations.

2. This paper addresses the shifting context of the local government reorganisation (LGR) announced in HM Government’s white paper in 2024, and the implications for achieving the council’s targets. In line with the anticipated reorganisation timelines, it is important to maintain a positive outlook on the work that can be achieved to continue to reduce the council’s emissions over the next two years.

3. This paper includes five scenarios designed to present a review of the council’s trajectory to net zero, showing where we are currently in terms of emissions, and giving a realistic assessment of where we will be in 2030. The first four scenarios represent the position of the council at the current time, as is reflected in current capital and revenue budgets. Only the fifth scenario has been projected beyond 2028 to 2034/35, as this demonstrates the likely impact of a full transition to an electric vehicle (EV) waste fleet to coincide with the projected timing of the next cycle of vehicle procurement. Any future council will be looking at replacing the end-of-life fleet, and assumptions have been made regarding securing the necessary finance and sufficient advances in vehicle technology.

Strategic priorities 4. Vale of White Horse’ Council Plan 2025-29 outlines five key priorities for the future. One of these key priorities is supporting Climate and Nature Recovery.

5. This report meets our commitment in the joint Nature and Climate Action Plan (NCAP) 2025-29 to produce annual reports outlining progress towards the council’s operational net zero target and the predicted emissions pathway to 2030 (NCAP action ONZ1).

Background 6. Vale of White Horse declared a Climate Emergency in 2019 and therefore the baseline year used in this report is 2019/20.

7. This is the second operational net zero annual report. The first net zero report was designed to test the earliest possible date that the council could reach net zero in its own operations. This report however presents a more realistic appraisal of the council’s current position, with the emphasis on committed projects and consideration given to emerging factors such as local government reorganisation, government funding for decarbonisation and other factors influencing the decarbonisation of our waste fleet.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Operational Net Zero Annual Progress ReportReport 482 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
HG
Councillor Hayleigh GascoigneCommittee Member, present
ES
Councillor Emily SmithCommittee Member, present
NB
Nick BennettCouncil Staff, present, as expected, virtual
PB
Phil BarkerCouncil Staff, expected
BT
Councillor Bethia ThomasChair, present
MC
Councillor Mark ColemanVice-Chair, present
AC
Councillor Andy CrawfordCommittee Member, present
NF
Councillor Neil FawcettCommittee Member, present
AF
Councillor Andy FoulshamCommittee Member, apologies
HP
Councillor Helen PighillsCommittee Member, present
SH
Simon HewingsOfficer, present, as expected, virtual
CB
Candida BasilioOfficer, present

On this subject at Vale of White Horse

Search all
  1. Operational Net Zero Annual Progress ReportThis decision
  2. Operational Net Zero TargetDecided

More from Vale of White Horse Cabinet

All decisions
MeetingDecisionOutcome
3 Jul 2026 MinutesThe minutes of the Cabinet meeting on 5 June 2026 were agreed as a correct record and the chair would sign them as such. Agreed Open
3 Jul 2026 Business Rates – Local Discretionary Relief scheme for 2026/2027That Cabinet (a) Approves the introduction of a local discretionary relief scheme, providing further relief for eligi... Approved Open
3 Jul 2026 At the Heart of the Vale: Annual Delivery Plan End of Year Report 2025-26That cabinet approves the Annual Delivery Plan End of Year Report 2025-26. Approved Open
3 Jul 2026 Thames Valley Spatial Development Strategy (SDS) Development and GovernanceThat Cabinet: · Notes the establishment of a partnership with the councils covering Oxfordshire, Berkshire and Swindo... Decided Open
3 Jul 2026 Revised Land and Property Asset Disposal PolicyRESOLVED : That Cabinet (a) Approves the revised Joint Property Asset Disposal policy. (b) Approves the revised Joint... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies