Temporary Accommodation Conversions - Main Works Budgets

Noted Committee 2 papers

AI summaryCabinet approved a revised gross capital budget of up to £18,084,330 for four temporary accommodation conversion schemes. The net £17,597,879 funding requirement after grant is expected to be met from the General Fund.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeNotedRevised gross capital budget for four schemes
MoneyUp to £18,084,330Gross capital; £17,597,879 net from General Fund
What happens nextFunded from General FundNet Council funding requirement to be met
Who it affectsTemporary accommodation supplyFour conversion schemes in progress

What was decided

Cabinet noted the progress made in developing the four temporary accommodation conversion schemes.

Cabinet approved a revised gross capital budget of up to £18,084,330 for the four schemes.

The net Council funding requirement after secured grant is £17,597,879 and is expected to be met from the General Fund.

What happens next

The net £17,597,879 funding requirement is expected to be met from the General Fund.

The money

  • £18,084,330 Revised gross capital budget for the four temporary accommodation conversion schemes
  • £17,597,879 Net Council funding requirement after secured grant

Implications

  • Financial: A revised capital budget of up to £18,084,330 has been approved, with the net Council contribution of £17,597,879 expected to come from the General Fund.
  • Other: The decision relates to progress on four temporary accommodation conversion schemes.

Who and where

  • Households placed in or seeking temporary accommodation
  • London Borough of Waltham Forest General Fund

Plain English for the jargon

  • Gross capital budget: Total planned capital spending before deducting grants or other income.
  • Net Council funding requirement: The amount the Council must itself fund after grants and other income are taken into account.
  • General Fund: The Council's main account used for day to day revenue spending on services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Cabinet: (1) noted the progress made in developing the four temporary accommodation conversion schemes; (2) approved a revised gross capital budget of up to £18,084,330 for the four schemes, noting that the net Council funding requirement after secured grant is £17,597,879 and is expected to be met from General Fund ...
Word for word from the decision Waltham Forest published for this meeting. Source: democracy.walthamforest.gov.uk

Follow this further

Built from Waltham Forest's papers

What the report saysPro

Report to Health and Wellbeing Board
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Equalities ScreeningAppendix 1 198 KB Copy on its way
PDF
Temporary Accommodation Conversions: Main Works BudgetsReport 157 KB Copy on its way

At this meeting

Whole meeting

More from Waltham Forest Health and Wellbeing Board

All decisions
MeetingDecisionOutcome
18 Sep 2026 Grant of a premises licence: RnR Lounge, 221-223 Chingford Mount Road, Chingford, E4 8LPThe Sub-Committee considered the application and determined to grant the variation in part, including the conditions ... Agreed Open
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 Grocery Voucher Scheme Contract VariationNotice of Executive Decision Published in Accordance with The Local Authorities (Executive Arrangements) (Meetings an... Decided Open
11 Sep 2026 Grant of a premises licence: St Marys, Church End, Walthamstow, E17 9RJThe Sub-Committee considered the application and determined to grant the application in full, including the condition... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies