Social Housing Improvement Task and Finish Group (Paper No.26-8)

Approved Scrutiny 2 papers

AI summaryThe Housing Overview and Scrutiny Committee voted 5 for, 0 against and with 3 abstentions to send seven social housing improvement recommendations to Cabinet and approve two oversight measures [D]. The measures cover repairs, resident engagement, stock condition analysis and governance of managed housing [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSeven for Cabinet consideration, two for Committee oversight [D]
MoneyNot stated
What happens nextCabinet consideration and oversight [D]Seven recommendations submitted for Cabinet consideration [D]
Who it affectsCouncil tenants and leaseholders [D]Repairs, engagement, stock data and scrutiny [D]

What was decided

The decision passed by 5 votes for, 0 against and 3 abstentions [D].

The Committee agreed to submit seven recommendations to Cabinet: consider additional resource for stock condition data analysis; improve the resident repair journey, including shorter appointment windows, online tracking, rescheduling and immediate feedback; jointly design repairs and maintenance specifications with residents and explain how their views shaped service design; use resident feedback and data to monitor contracts; revise the Borough Residents’ Forum constitution and meeting dates; include tenant and leaseholder representation in governance; and commission external consultants to review formal and informal engagement by June 2026 [D].

The Committee approved annual presentation of Tenant Satisfaction Measures and continued scrutiny after the election, including the matter in its work programme [D].

Why

A clear analysis of stock condition data would help senior leaders and members prioritise investment by resident safety and impact, and identify blocks with particular investment needs [P3][P51][P53]. Report P3, P51, P53

Residents reported repair delays, repeated visits and poor contractor performance. Repair satisfaction was 58% in 2024/25, and the online portal lacked reporting and tracking options [P69][P70]. The new journey seeks shorter waits, online tracking and a non digital option [P5][P70][P72]. Report P5, P69, P70, P72

The Borough Residents’ Forum needed to reflect changed governance, and the regulator had identified limited tenant led engagement, weak tenant influence and poor communication of that influence. Resident input would shape specifications, contract monitoring and oversight [P73][P77][P80][P83][P86]. Report P73, P77, P80, P83, P86

What happens next

Recommendations 1 to 7 are to be submitted to Cabinet for consideration. The Housing Improvement Plan was due to be considered by Cabinet on 26th January 2026, with the aim of reflecting the Group’s recommendations [D][P45]. Report P45

Specialist external consultants will review formal and informal engagement arrangements, with the review to conclude by June 2026 [D][P15]. Report P15

The Committee will receive Tenant Satisfaction Measures annually, continue scrutiny and include the matter in its work programme after the election [D][P18][P20]. Report P18, P20

Options considered

  • Chosen: Consider additional resource for stock condition data analysis. A large volume of survey data was hard to analyse, and clear analysis would help identify blocks needing investment [P51][P53]. Report P51, P53
  • Chosen: Reduce appointment windows and expand online repair tracking. Residents wanted better tracking and transparency, and the online portal lacked sufficient reporting options [P70][P72]. Report P70, P72
  • Chosen: Jointly design repairs and maintenance specifications with residents. Contract re-procurement creates a route for tenant voice to shape service design [P73][P75]. Report P73, P75
  • Chosen: Use resident feedback and data in contract monitoring. This would support a customer focused approach and the quality of the tenant experience [P73][P77]. Report P73, P77
  • Chosen: Revise the Borough Residents’ Forum constitution and meeting dates. The Forum must fit the Council’s new decision making model after Cabinet papers stopped needing prior Housing Overview and Scrutiny Committee consideration [P80][P82]. Report P80, P82
  • Chosen: Include tenant and leaseholder representation in housing governance. Resident involvement can benefit scrutiny and monitoring of improvement delivery [P83][P85]. Report P83, P85
  • Chosen: Commission specialist external consultants for engagement review. Further communication and specialist review of engagement changes were needed [P90][P92]. Report P90, P92
  • Chosen: Report Tenant Satisfaction Measures annually and continue scrutiny. Public discussion would highlight tenants’ perceptions, and the improvement journey still had some way to go [P96][P109]. Report P96, P109

Implications

  • Financial: Cabinet consideration of additional resource could help the department analyse survey data swiftly and identify blocks with particular investment needs [P51][P53]. Report P51, P53
  • Risk: Clear analysis would help prioritise investment by resident safety and impact, while faster surveys may identify Category 1 hazards [P53][P54]. Report P53, P54
  • Other: The revised repair journey would let residents track orders, see appointment slots, check lateness, reschedule online and give feedback immediately [P5][P72]. Report P5, P72
  • Equalities: Expanded online services would retain a non digital reporting option [P70][P72]. Report P70, P72
  • Other: Joint design and feedback based contract monitoring would let resident experience shape service design and contract performance [P73][P77]. Report P73, P77
  • Other: Updating the Forum, adding representation and commissioning specialists would reshape formal and informal engagement and oversight of housing improvements [P82][P85][P92]. Report P82, P85, P92
  • Other: Area Repair Contracts end in September 2026, and re-procurement offers a route to embed resident designed specifications and monitoring [P67][P73]. Report P67, P73
  • Risk: The Housing Ombudsman and Building Safety Regulator had not issued findings, while any Social Housing Regulator reassessment or re-inspection timing remained at its discretion [P25][P104][P106]. Report P25, P104, P106

Who and where

  • Council tenants and leaseholders Report P70, P85
  • Residents using the repairs service Report P66, P72
  • Residents needing safety checks or stock condition surveys Report P54, P57
  • Residents without Resident Associations Report P86
  • Resident Associations, Area Housing Panels and the Borough Residents’ Forum Report P80
  • Housing Department and Resident Services Report P44, P51
  • External repairs and safety check contractors Report P59, P67
  • Social Housing Regulator, Housing Ombudsman and Building Safety Regulator Report P25, P104, P105

Timeline

  • 18th June 2025: The Committee requested the Task and Finish Group following the C3 inspection grade [P22]. Report P22
  • 1st October 2025: The Resident Services department was established, and officers needed more time to develop the wider Housing Improvement Plan [P44]. Report P44
  • 26th January 2026: Cabinet was due to consider the Housing Improvement Plan. The Group aimed for its recommendations to be reflected in it [P45]. Report P45
  • April 2026: Target for completing new high rise Fire Risk Assessments [P63]. Report P63
  • June 2026: External engagement review due to conclude [P15]. Report P15
  • by end of 2026: Revised target to achieve 100% of stock condition surveys [P50]. Report P50
  • September 2026: Area Repair Contracts due to end [P67]. Report P67
  • after the election: The Committee is to continue scrutiny and include the matter in its work programme [P20][P111]. Report P20, P111

Plain English for the jargon

  • Social Housing Regulator: The regulator that inspected the Council and gave its social housing services a C3 grade [P22].
  • C2 grade: The higher rating the Task and Finish Group sought as a minimum future outcome [P25].
  • Stock condition surveys: Surveys of homes and blocks used to assess condition and help plan investment [P49][P50].
  • Area Repair Contracts (ARCs): External repair contracts that started in 2021 and end in September 2026 [P67].
  • Fire Risk Assessments (FRAs): Assessments of fire risks, with overdue actions under review [P62][P64].
  • Borough Residents’ Forum (BRF): A formal Council resident engagement structure whose constitution is to be revised [P80][P82].
  • Tenant Satisfaction Measures: Survey measures showing tenants’ perceptions of the housing service [P93][P95].
  • Category 1 hazards: Survey issues including mould growth and missing carbon monoxide and smoke alarms [P54].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

RESOLVED - by 5 votes for, to 0 against and with 3 abstentions that a) the following recommendations be submitted to Cabinet for its consideration: 1) There be consideration of additional resource being established to assist with analysing data gathered during stock condition surveys. It is considered that having a clear picture and analysis of the stock condition data will enable senior leaders and members to prioritise investment based on resident safety and impact. 2) Improve the resident repair journey by reducing appointment windows and including a digital / online tracking element so that residents can track the raising of their repair order, view their appointment slot, track lateness and reschedule their appointment online if necessary as well as provide feedback on the service immediately after. 3) Co-design the repairs and maintenance contract specifications with residents and communicate with tenants how tenants’ voice has influenced service design. 4) Use resident provided feedback and data in robust monitoring of repairs and maintenance contracts. 5) The Borough Residents’ Forum constitution and future meeting dates should therefore be revised and updated to reflect the change in the Council’s governance. 6) Tenant and leaseholder representation be included in the governance arrangements monitoring performance and delivery of improvements to the Council’s managed housing stock. 7) Commission specialist external consultants on the engagement strategy, to include both the formal engagement structures including Residents Associations, and informal engagement processes, with a view to concluding their review by June 2026. b) the following recommendations to the Committee be approved: 8) The Tenant Satisfaction Measures be presented to the Housing Overview and Scrutiny Committee on an annual basis. 9) The Committee continue to scrutinise and oversee progress and include the matter on their work programme post-election.
Word for word from the decision Wandsworth published for this meeting. Source: democracy.wandsworth.gov.uk

Follow this further

Built from Wandsworth's papers

What the report saysPro

Report to Housing Overview and Scrutiny Committee, 16 pages

Recommendations

1. The Task and Finish Group recommends the following to Cabinet:

Recommendation One

There be consideration of additional resource being established to assist with analysing data gathered during stock condition surveys. It is considered that having a clear picture and analysis of the stock condition data will enable senior leaders and members to prioritise investment based on resident safety and impact.

Recommendation Two

Improve the resident repair journey by reducing appointment windows and including a digital / online tracking element so that residents can track the raising of their repair order, view their appointment slot, track lateness and reschedule their appointment online if necessary as well as provide feedback on the service immediately after.

Recommendation Three

Co-design the repairs and maintenance contract specifications with residents and communicate with tenants how tenants’ voice has influenced service design.

Recommendation Four

Use resident provided feedback and data in robust monitoring of repairs and maintenance contracts.

Recommendation Five

The Borough Residents’ Forum constitution and future meeting dates should therefore be revised and updated to reflect the change in the Council’s governance.

Recommendation Six

Tenant and leaseholder representation be included in the governance arrangements monitoring performance and delivery of improvements to the Council’s managed housing stock.

Recommendation Seven

Commission specialist external consultants on the engagement strategy, to include both the formal engagement structures including Residents Associations, and informal engagement processes, with a view to concluding their review by June 2026.

3 2. The Task and Finish Group recommends the following to the Housing Overview and Scrutiny Committee:

Recommendation Eight

The Tenant Satisfaction Measures be presented to the Housing Overview and Scrutiny Committee on an annual basis.

Recommendation Nine

The Committee continue to scrutinise and oversee progress and include the matter on their work programme post-election.

INTRODUCTION

3. At the 18th June 2025 Housing Overview and Scrutiny Committee, Members requested that a task and finish group be established in response to the C3 grading by the Regulator of Social Housing following their inspection in late 2024 and the publication of their findings in February 2025. Members wanted to ensure that improvements were made, and measures were put in place so that all consumer standards were met and council tenants were provided with the highest quality service, with a view to ensuring a higher grade is achieved when the Council is re- inspected.

4. The Social Housing Improvement Task and Finish Group was subsequently established, with the membership comprising Councillors Stock (Chair), Ayres, Davies, Govindia and [name removed]. The Group also agreed to invite residents Tom Glockner, Vice-Chair of the Borough Residents’ Forum (BRF) and Joanna Playford, Tenant representative of the Association of Retained Council Housing (ARCH) to their November and December meetings.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
26-8 TF Group Final Report final versionReport 16 pages DownloadRead as text
PDF
Social Housing Improvement Task and Finish Group (Paper No.26-8)Report 2 pages Download

More from Wandsworth Housing Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Jan 2026 Minutes - 27th November 2025RESOLVED – That the minutes of the previous meeting of the Housing Overview and Scrutiny Committee held on 27th Novem... Decided Open
21 Jan 2026 Borough Residents' Forum - Report of meeting held on 19 January 2026 (Paper No.25-17)RESOLVED – that the report be received for information. Decided Open
21 Jan 2026 Housing Services Activity Report (Paper No.26-6)RESOLVED - That Cabinet be recommended to ‘explore ensuring that when nightly paid or licensed accommodation were use... Decided Open
27 Nov 2025 Minutes - 2nd October 2025RESOLVED – That the minutes of the previous meeting of the Housing Overview and Scrutiny Committee held on 2nd Octobe... Decided Open
27 Nov 2025 Housing OSC Work Programme (Paper No.25-411)RESOLVED – that the current work programme, with the additions of the paper on the HRA and an update on the Fox House... Noted Open