Resolved
RESOLVED – to approve the minutes of the previous meeting of the Passenger Transport Liaison Group (PTLG), held on the 25 th September 2025.
Passenger Transport Liaison Group approved this item on Wednesday 25 March 2026. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – to approve the minutes of the previous meeting of the Passenger Transport Liaison Group (PTLG), held on the 25 th September 2025.
Official
Minutes of a meeting of the Passenger Transport Liaison Group held online via Microsoft Teams on Thursday, 25th September, 2025 at 6.30 p.m.
PRESENT
Councillors Fraser (Chair), Hamilton, and Yates.
Transport Representatives: Joel Adams (Transport for London – TfL), Malcolm Claridge (First Bus London – FBL), Yvonne Leslie (Govia Thameslink Railway – GTR), James Pickard (Transport for London – TfL), and Jack Wharton (Network Rail – NR).
Wandsworth Borough Council: Gabrielle Aron (Vulnerabilities Manager – VM), Michael Flowers (Democratic Services Officer – DSO), Sidonie Forrest-Brown (Senior Transport Planner – STP), and David Tidley (Transport Strategy Team Manager – TSTM).
1. Minutes of the Previous Meeting and Matters Arising
RESOLVED – to approve the minutes of the previous meeting of the Passenger Transport Liaison Group (PTLG), held on the 13th May 2025.
2. Declarations of Interests
There were no declarations of interests.
3. Public Transport Passenger Safety
Safe Spaces: Clapham Junction Station
The Group were advised that owing to recent developments, an update could not be provided at the meeting, and it was agreed by attendees that the agenda item be deferred to the next meeting of the Group, and for a private update to be provided to councillors after the meeting once more information was available.
RESOLVED – to note the Public Transport Passenger Safety update.
4. Trains and Overground
‘Access for All’ and Second Entrance: Wandsworth Town Station
The NR representative advised the Group that the detailed design and pricing had been completed, and the delivery of the project was not dependent on security the relevant funding.
In response to a question of clarification, the NR representative confirmed that if funding was secured, then work at the train station would be able to commence in 2026. Official
Second Entrance: Queenstown Road Station
The NR representative commented that a problem had been identified with a window at the site, which was quite accessible, but which shouldn’t have been, which was currently being worked on. He advised that the expectation was that the second entrance would be open approximately next month.
East Putney Rail Bridge Enhancement
The STP explained that developer funding had been secured for improvements to two railway bridges, one of which was owned by Network Rail and the other by TfL. She added that the proposed work would include cleaning, painting, and pigeon proofing, and the addition of ‘East Putney’ writing to both sides on the bridges. The quote included an allowance for a two colour scheme and the refurbishment work would be completed by the ‘M Group’. To mitigate disruption, the STP confirmed that work would be undertaken overnights between 10pm to 5:30am over a defined timeframe and work which would be loud would be restricted to a 12am timeframe. The nearby roads would incorporate temporary traffic lights and would operate using a single lane closure. The STP then advised the Group that communication would be provided to local residents to inform them about the work that would take place.
RESOLVED – to note the Trains and Overground updates.
5. Underground
London Underground: Step Free Access Projects
The TfL representative working on the project introduced himself and explained that Tooting Broadway station was a problematic one for step free access owing to the design of it and the impact that improvement work would have on the nearby road and on the ability of the station to remain open at the same time as work was underway. TfL staff were therefore currently investigating how to undertake step free access work whilst minimising the impact from it, but it was a slow process.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the Previous Meeting and Matters ArisingMinutes | 3 pages | DownloadRead as text |
Follow Passenger Transport Liaison Group at Wandsworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2026 | Safe Spaces: Clapham Junction StationRESOLVED – to note the Public Transport Passenger Safety update. | Noted | Open |
| 25 Mar 2026 | G1 Bus Route: Performance MonitoringRESOLVED – to note the Buses updates. | Noted | Open |
| 25 Mar 2026 | Second Entrance: Queenstown Road StationRESOLVED – to note the Trains and Overground updates. | Noted | Open |
| 25 Mar 2026 | East Putney Rail Bridges: RefurbishmentRESOLVED – to note the London Underground updates. | Noted | Open |
| 25 Mar 2026 | Any Other BusinessRESOLVED – to note the other matters of business discussed. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.