RESOLVED to: 1. Pass its concerns to the Executive over the delay in implementing the recommendations relating to Information Security Governance, emphasising the importance of this area of work, and endorsing any additional resource requests that may be required in order to move this forward; and 2. Agree that the implementation ... view the full minutes text for item 13.
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
Internal audit work helps management in achieving good value for money and, individual recommendations may have value for money implications.
Legal implications
There are no direct legal implications, although good governance is strengthened by attention to the matters raised in audit recommendations.
Introduction
1. This report provides the Audit Committee with the latest position regarding the implementation of Internal Audit recommendations.
Annexe 1 provides the current position on recommendations due for completion at the end of the month of the Audit Committee date.
Annexe 2 details the request for change of implementation due date.
2. Recommendations relate to the control environment and hence the overall governance and risk management of the Council and it is important that agreed actions are completed within timeframes agreed with the relevant Head of Service. Recommendation
It is recommended that the Committee:
1. considers the information contained in Annexe 1 and, following discussion at the Audit Committee meeting, identifies any action it wishes to be taken, particularly in relation to the Information Security Governance recommendations which are linked to the recent Data Protection review completed in preparation for the General Data Protection Regulations (GDPR) that comes into force in May 2018.
2. agrees an appropriate implementation date for the recommendations listed in Annexe 2, where a request has been made by the Head of Service for a change in the previous implementation date.
Background papers
There are no background papers (as defined by Section 100D (5) of the Local Government Act 1972) relating to this report.
Audit Recommendations overdue or due within next month Generated on: 06 July 2017
Action Status
Cancelled
Overdue; Neglected
Unassigned; Check Progress
Not Started; In Progress; Assigned
Completed
Head of Service Taylor, Robin
The Council’s Information Management Exit Meeting 02-Jun-2016 Policy, Record Disposal and Retention Date Schedule and the Acceptable Use of IT policy were last updated over a year ago. Action Code The policies do not cover off the process to & IA16/22.001 Policies be followed in regard to the retention, Description sharing and disposal of manual or Due Date 03-Jul-2017 electronic data. The policies also do not cover the procedure to be followed if manual or electronic data is lost or subject to misappropriation. Audit Report Code and Description IA16/22 Information Security Governance The Council will update the Record Disposal and Retention Schedule to ensure it includes the preferred disposal method for all types of data.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.