Decision RESOLVED that, subject to the consideration of any further representations and consultee responses received by 6 th July 2018 that raise further material planning matters that have not already been considered, permission be granted, subject to amended conditions 1, 5, 6, 7,10, 14 and 18 and informative 2 in the update sheet and conditions 2, 3, 4, 8, 9, 11, 12, 13, 15, 16, 17 and informative 1 in the agenda report and the additional condition 19 raised at the meeting and noted below: 19. Following completion of a surface water drainage scheme, as required by condition 14(t), a verification report shall be submitted to an approved in writing by the Local Planning Authority confirming that the surface water drainage scheme has ... view the full minutes text for item 21.
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
B1 WA/2018/0544 Provision of a dual-lane temporary construction Crest Nicholson Regeneration Ltd & access to the A31, comprising a bridge across the Sainsbury's Supermarkets River Wey, pedestrian underpass, temporary 27/03/2018 vehicular access from South Street and other associated temporary works to enable the bridge construction, other supporting infrastructure and re-instatement works, including the erection of a permanent pedestrian footbridge across the River Wey (as amended and amplified by plans and additional information received 01/06/2018) at Site B, East Street Regeneration, East Street, Farnham
Public Notice: Was Public Notice required and posted: N/A Grid Reference: E: 484358 N: 146775
Town: Farnham Ward: Farnham Castle Farnham Moor Park Case Officer: Ruth Dovey Expiry Date: 21/05/2018 Time Extended Date: 29/06/2018 Neighbour Notification Expiry Date: 04/05/2018 Neighbour Notification Amended/Additional Expiry Date: 25/06/2018
RECOMMENDATION That, subject to the consideration of any further representations and consultee responses received and subject to conditions, permission be GRANTED.
Introduction/Background
The application has been brought before the Joint Planning Committee at the request of the Head of Planning due to the application’s strategic importance in the Borough.
The bridge is required to enable the construction of the East Street (Brightwells) redevelopment scheme. Over the course of various planning applications for the East Street redevelopment, the need for a bridge from the A31 directly into the site to construct the development has been required by condition, on the basis that routing construction traffic through Farnham itself would result in unacceptable levels of traffic congestion and have a harmful impact on air quality resulting in a loss of amenity to local residents.
The need for a bridge was reinforced in June 2010 when an application (WA/2010/0372) to remove Condition 37 on the original redevelopment permission (WA/2008/0279), which required the applicants to submit details of the temporary access from the A31 Farnham By-Pass, was refused. This application was refused because an alternative means of access to the site for construction purposes, i.e. use of the existing accesses to the site, would cause material harm to amenity by way of loss of air quality, excessive traffic congestion and related inconvenience to highway users, visitors and businesses and material loss of amenity to local residents. The refusal of this application re-affirms the need for a bridge to be provided.
Following this refusal, permission was granted in March 2011 for the provision of a single lane temporary construction access bridge from the A31 (WA/2010/1650). This permission was later renewed under application ref. no. WA/2012/0911. This permission has been implemented through the digging of a trench to make way for the foundations of the bridge. On this basis, this single lane bridge permission is extant in perpetuity and the single lane bridge can be constructed at any time.
This current application seeks to widen the bridge to provide two lanes (one for vehicles entering the site and one for vehicles leaving) rather than one. The decision to seek to widen the temporary bridge was made by the applicant in order to improve the overall efficiency of the main construction site and to enhance its operational safety for users of the bridge and traffic along the adjacent A31 corridor. The dual lane bridge allows construction vehicles to enter and exit the site simultaneously where the single lane bridge would not.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.