Resolved
RESOLVED to note the progress in implementation of internal audit recommendations.
Audit & Risk Committee noted this item on Tuesday 24 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the progress in implementation of internal audit recommendations.
Internal audit work helps management in achieving good value for money and, individual recommendations may have value for money implications.
There are no direct legal implications, although good governance is strengthened by attention to the matters raised in audit recommendations.
Introduction
1. This report provides the Audit Committee with the latest position regarding the implementation of Internal Audit recommendations.
Annexe 1 provides the current position on recommendations due for completion at the end of the month after the date of the Audit Committee.
2. Recommendations relate to the control environment and hence contribute to the overall governance and risk management of the Council and it is important that agreed actions are completed within timeframes agreed with the relevant Head of Service.
It is recommended that the Committee considers the information contained in Annexe 1 and, following discussion at the Audit Committee meeting, identifies any action it wishes to be taken.
There are no background papers (as defined by Section 100D (5) of the Local Government Act 1972) relating to this report.
CONTACT OFFICER:
Name: Gail Beaton Telephone: 01483 523260 E-mail: [email protected]
2 ANNEXE 1
Audit Recommendations overdue or due within the end of the month after the AC Generated on: 12 July 2018
Action Status
Cancelled
Overdue; Neglected
Unassigned; Check Progress
Not Started; In Progress; Assigned
Completed
Head of Service Vickers, Peter
We noted three Final Accounts threshold 4 Exit Meeting 10-Apr-2018 contracts closed since January 2017. Date Reviewing these we confirmed that the final account amount was subject to Officer scrutiny and review. Through review of the Agresso approval Action Code workflow we confirmed that an appropriate IA18/21.005 Final Payment & budget holder approved the payment Process Description within the system, however we could not Due Date 30-Jun-2018 confirm any independent review of the final account figure by anyone external to the team. There is a risk that final account figures or payments could be miscalculated and missed without adequate review. This can lead to an adverse affect on cash flow. Audit Report Code and Description IA18/21 Contract Final Accounts The Council will implement a formal review of the final payment process for large contracts where stage payments have been made. This will include as a minimum: -The sign off process by a member of staff independent of the team which the contract sits within; - Sign off to be completed prior to the final account payment; Agreed Action - Guidance on when to deliver the contract to legal for retention (where applicable); and The target timeframe to complete this from the date final account from contractor is received. The Head of Finance is of the opinion that this is the responsibility of the Service Managers to ensure that payments in relation to contract are accurate and that retention of funds are accurately recorded and released at the appropriate time. Head of Status Overdue Progress 0% Peter Vickers Service All Notes
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PROGRESS ON THE IMPLEMENTATION OF INTERNAL AUDIT RECOMMENDATIONSAppendix | 118 KB | DownloadRead as text |
Follow Audit & Risk Committee at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Management of Asbestos containing Material in Corporate Property and AssetsRESOLVED that the Management of Asbestos containing Material in Corporate Property or Assets be noted. | Noted | Open |
| 27 Jul 2026 | Whistleblowing PolicyRESOLVED that the be adopted. | Approved | Open |
| 27 Jul 2026 | Annual Information Governance and Data Transparency ReportRESOLVED that the Annual Information Governance and Data Transparency report be noted. | Noted | Open |
| 27 Jul 2026 | Local Code of Corporate GovernanceRESOLVED that the Local Code of Corporate Governance be approved and adopted. | Approved | Open |
| 27 Jul 2026 | Data Protection Annual ReportRESOLVED that: · The Data Protection Annual report be noted. · A further report be brought to the final meeting of Wa... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.