Item A1, WA/2018/1776 - Land At Mill Farm Cottage, Mill Lane, Bramley GU5 0HW
ApprovedPlanning1 paper
Area Planning Committee (Eastern) approved this item on Wednesday 16 January 2019. Below is the council's own wording, with the papers it was decided on.
Decision RESOLVED that permission be GRANTED subject to conditions 2 – 4 and 6 – 18 set out in the agenda report, amended condition 1 on the update sheet, amended condition 5 and additional conditions 19 and 20 set out below, as well as informatives 1 – 5. 5. Condition Before any work on site begins, cross sections/details indicating the proposed finished floor levels, existing and proposed ground levels above ordnance datum shall be approved in writing by the Local Planning Authority. The works shall be carried out in strict accordance with the approved details. Reason In the interest of the character and amenity of the area in accordance with Policy TD1 of the Local Plan 2018 (Part 1) and retained Policies D1 and D4 of the Local Plan 2002. 19. Condition Construction works to and from the site in connection with these works shall take place only between 08:00-18:00 Monday to Friday and 08:00 – 13:00 Saturdays and shall not take place at any time on Sundays or on Bank or Public Holidays. Reason In the interests of the character and amenity of the area in accordance with Policy TD1 of the Local Plan (Part 1) 2018 and retained Policies D1 and D4 of the Local Plan 2002. 20. Condition Deliveries to and from the site in connection with these works shall take place only between 09:00-18:00 Monday to Friday and 09:00 – 13:00 Saturdays and shall not take place at any time on Sundays or on Bank or Public Holidays. Reason In the interests of the character and amenity of the area in accordance with Policy TD1 of the Local Plan (Part 1) 2018 and retained Policies D1 and D4 of the Local Plan 2002. Public speaking In accordance with the Council’s arrangements for public participation at meetings, the following made representations in respect of the application, which were duly considered: Roger Mahoney - Objector Toby Shea - Agent
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
A1 WA/2018/1776 Erection of a detached dwelling with new T Shea vehicular access and associated works at Land At 19/10/2018 Mill Farm Cottage, Mill Lane, Bramley GU5 0HW
Committee: Eastern Area Meeting Date: 16/01/2019
Parish: Bramley Ward: Bramley, Busbridge and Hascombe Case Officer: Alex Inglis
Neighbour Notification Expiry Date 30/11/2018 Expiry Date 13/12/2018 Extended expiry date 18/01/2018
RECOMMENDATION That, subject to conditions, permission be GRANTED
Introduction
This application has been brought before the Area Committee at the request of the Local Member.
Location Plan Site Description
The application site is located on the northern side of Mill Lane, Bramley and measures 0.09ha. The site features the western half of the garden space associated with Mill Farm Cottage and is accessed via a private driveway. The area is rural/residential in character.
Proposal
Permission is sought for: - The erection of a detached dwelling with associated access. The proposed dwelling would measure 12m deep by 11.4m wide and would feature a hipped roof profile with maximum ridge height of 7.8m, with eaves at 3.95m, 4.5m and 4.2m. The dwelling would have a feature gable frontage projecting 1.6m at first floor level on stilts to create an open porch below. - A 10.2m long section of hedgerow would be removed at the front of the site to create an independent access driveway with a permeable gravel surface providing three car parking spaces.
Proposed Elevations
Front Side
Rear Side
Proposed Floorplans
Ground Floor Plan First Floor Plan Proposed Streetscene
Proposed Site Plan
Relevant Planning History
WA/2016/2027 Erection of a detached dwelling and Refused: associated vehicular access (as 09/12/2016 amended by plans received 17/11/2016, 18/11/2016 and Appeal Allowed: 23/11/2016 and as amplified by email 27/09/2017 dated 23/11/2016). Extant WA/2007/1890 Application for a Certificate of Certificate of Lawfulness under Section 192 for the Lawfulness installation of a solar energy system. Refused: 22/10/2007
Appeal Dismissed: 29/08/2008 WA/2002/1761 Construction of a dormer window Full Permission: together with the erection of a 12/11/2002 summerhouse following demolition of existing outbuildings (as amplified by letter dated 16/10/02). WA/2000/1148 Erection of extensions and alterations. Full Permission: 30/08/2000 WA/1999/1802 Erection of extensions and alterations. Full Permission: 09/12/1999 WA/1982/1521 Construction of detached garage Full Permission: 06/01/1983 HM/R7070 Bungalow Approve: 29/04/1954
Planning Policy Constraints
Green Belt – outside any defined settlement area Ancient Woodland 500m Buffer Zone Bramley Conservation Area Flood Zone 2 Flood Zone 3 Area of High Archaeological Potential
Development Plan Policies and Guidance
The development plan and relevant policies comprise:
Waverley Borough Local Plan, Part 1, Strategic policies and sites (adopted February 2018): SP1, TD1, RE2, HA1 and NE1. Farnham Neighbourhood Plan (made May 2017): N/A Waverley Borough Local Plan 2002 (retained policies February 2018): D1, D4, D6, D7, D9, HE8, HE14 and HE15. South East Plan (saved policy NRM6): N/A In accordance with the National Planning Policy Framework (NPPF) due weight has been given to the relevant policies in the above plans.
Other guidance: The National Planning Policy Framework 2018 (NPPF) The National Planning Practice Guidance 2014 (NPPG) Council’s Parking Guidelines (2013) Surrey Vehicular and Cycle Parking Guidance (2012) Bramley Conservation Area Appraisal SPD
Consultations and Town/Parish Council Comments
Bramley Parish Council No objection Waverley Environmental Health – No objection, subject to conditions. Potentially Contaminated Land Waverley Environmental Health – The applicant will be required to comply with Waste the Guide for Developers document: http://www.waverley.gov.uk/downloads/file/412 3/guidance_on_refuse_and_recycling_provision _for_new_homes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.