Resolved
Resolved that the report be noted.
Overview & Scrutiny Committee - Housing noted this item on Tuesday 26 February 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the report be noted.
WAVERLEY BOROUGH COUNCIL
HOUSING OVERVIEW & SCRUTINY COMMITTEE
26 February 2019
Title:
HOUSING DEVELOPMENT UPDATE
[Portfolio Holder: Cllr Carole King] [Wards Affected: Borough wide]
Background and purpose
Provision of affordable housing is central to community well being. It is consistent with the council’s corporate strategy people goals for 2018-2023 by investing in our homes to ensure that they are pleasant and safe, maximising the supply of affordable housing by developing new council homes and implementing Housing Strategy 2018-2023.
Members are asked to note this report which provides an update on the progress since January 2018 on delivery of well designed, sustainable and energy efficient homes for the council to meet the housing need of Waverley residents.
Completed schemes
Sherrydon, Cranleigh
Two new 2 bed homes were handed over in February 2018.
Nursery Hill, Shamley Green
Five new homes consisting of 3 x 2 bed and 2 x 3 bed houses were handed over in April 2018.
Wey Court, Godalming
Twenty four new homes consisting of 2 x 2 bed houses and 22 x 1 and 2 bed flats were handed over in June 2018.
Site D, Godalming
Sixteen new homes consisting of 6 houses and 10 flats were handed over in July 2018.
On Site
Community Rooms: conversion to 1 bed flats: Stonepit Close, Godalming, Griggs Meadow, Dunsfold and Woodyers Close, Wonersh
3 x 1 bed flats Niblock builders were appointed as the contractor with the final completion date of all three units forecast for April 2019.
Site A – 37 new homes
The site is cleared and hoarded. Thakeham Client has been appointed as the contractor. Start on site is now agreed for April 2019.
A 3-phase delivery programme has been proposed and agreed by the contractor, with the first handover of up to 15 units by the end of May 2020. This will require the council to bring forward partial demolition of site B in order to avoid the expiry of the planning consent.
Pre-development
Ockford Ridge
Site B: 17 new homes Site C: 30 new homes (planning application submitted) Site E: 14 new homes (concept designs) Site F: 22 new homes (concept designs)
Site B
Agreement is being sought with planning services to allow for the activation of the current consent through partial demolition (21-24 Ockford Ridge) of the site, programmed for summer 2020, subject to successful tendering, decanting and appointment of disconnection and demolition works.
The appointment of relevant consultancies to support this accelerated programme will commence in the next two months. Early notification of the council’s programme to affected tenants and residents is also in preparation.
Site C
Formal public consultation was extended following the late request for further information from Surrey CC, Thames Water and Surrey Wildlife Trust. The Planning Committee will now consider the application at its March 2019 meeting.
Sites E & F
Site E: 89 – 94 Ockford Ridge: three pairs of small, semi-detached houses whose rear gardens fall away steeply down to Cliffe Road.
Site F: 119 - 134 Ockford Ridge (excluding 125,126): a mixture of small semi-detached and terraced houses.
Following Management Board approval of the business case to deliver new build housing on this site rather than undertake refurbishment works, the communications and housing development teams prepared an information pack for tenants impacted by the proposals. Appointments were made so each tenant could talk to officers. A Drop In Surgery was also arranged and well attended. The Tenant Liaison Officer will continue to liaise with tenants living on this site.
Refurbishment
Phase 1
Waverley Officers and our appointed Contract Administrator continue to monitor the completion of the final snagging works at one property. The final account has been agreed and signed off by Head of Service, with a retention held for a further twelve months.
Phase 2 & 3
All survey works are now completed. It is expected the successful contractor will commence works in March 2019 with a completion date no later than December 2019.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HOUSING DEVELOPMENT UPDATEReport | 86 KB | DownloadRead as text |
Follow Overview & Scrutiny Committee - Housing at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2021 | Scrutiny reportRESOLVED That the Committee endorsed the Biennial Scrutiny Report. | Decided | Open |
| 8 Jun 2021 | Annual kpi reviewRESOLVED That: Housing Delivery and Communities (Housing Delivery only) – The Committee agreed to no changes to indic... | Agreed | Open |
| 8 Jun 2021 | Report from the housing design standards task and finish groupRESOLVED That the Committee were happy for the report to go forward to the Executive. | Decided | Open |
| 9 Mar 2021 | Tenants panel updateRESOLVED To highlight the committee’s concerns regarding the isolation of elderly people to the Community and Wellbei... | Decided | Open |
| 26 Jan 2021 | Asset management strategy 2021/22RESOLVED That a verbal update on the Asset Management Strategy would be a standing item on subsequent Housing Overvie... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.