Resolved
RESOLVED to approve a budget of £20,000 to progress and complete works at College Gardens, Farnham to install electric vehicle charge points, traffic management measures and associated costs.
Executive (Acting as Trustee of the Joseph Ewart Bequest) approved this item on Tuesday 28 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to approve a budget of £20,000 to progress and complete works at College Gardens, Farnham to install electric vehicle charge points, traffic management measures and associated costs.
The expenditure will be funded from reserves.
Trust funds must be spent within the boundary of the Trust and for the benefit of the Trust’s tenants. The Council shall seek the Charity Commission’s approval for expenditure of the funds where necessary. The Trustees should therefore seek independent legal advice that the proposed expenditure is within the boundary of the Trust.
1. Introduction
1.1Waverley Borough Council is the sole trustee of the Joseph Ewart Bequest, a registered charity with the objective of providing small bungalow cottages suitable as homes for the elderly people with limited financial resources who have lived in the former Farnham Urban District area for at least five years. The charity owns 19 properties for elderly people in Farnham, including 16 bungalows at College Gardens and three bungalows at Arthur Road, Farnham
1.2The unrestricted funds which are available to the trustees for the general purposes of the charity as set out in its governing document, with approval from the Charities Commission, are currently in excess of £1m.
2. Request for additional funding to install on-site electrical street charging points at College Gardens, Farnham. 2.1 The Executive acting as Trustee of the Ewart Trust bequest agreed a budget of £85,000 to a carry out a parking and landscaping project at College Gardens on 1st March 2016. 2.2 Planning permission was granted on 30th March 2016 with 6 planning conditions including landscaping, signage, use of walls or fences, insertion of electric charge points and traffic management. 2.3 Work commenced in November 2018 with a budget of £85,000. The cost to date includes:
£68,044 in build costs
£1,093 in planning conditions to date
£15,707 in service and utility changes/ enablement
£6,705 in consultancy and utility fixed fees
Totalling £91,549 Some expenses have been met by HRA, for example, repair works outside the bungalow curtilage and some landscaping. 2.4 Surrey County Council has now implemented its parking strategy in December 2019 and its on-street electric charge point strategy for this area within the last month. This now enables the Council to finally complete the remaining conditions in the planning permission. 2.5 Surrey County Council has confirmed that it does not wish to use one of the points in the proposed electric charge points in College Gardens. It will instead, use a point in West Street. 2.6 This leaves Housing with the proposed option as recommended by JOJU, (the Housing framework provider for ECP charge points) which was for it to be situated at the edge of no. 18. 2.7 It is anticipated that the cost of this work will be £20,000 which will include traffic management measures, road contract and connection. This also allows for the associated administration to use of the charge point for up to 3 years. 2.8 Whilst current demand from the residents is low, there are opportunities to use this point by Council officers, and contractors, along with the wider tenant base in the locality. Recommendation
It is recommended that the Executive acting as Trustees of the Joseph Ewart Bequest, gives approval to progressing and completing the works at College Gardens, Farnham at a total budget of £20,000.
There are no background papers (as defined by Section 100D(5) of the Local Government Act 1972) relating to this report.
CONTACT OFFICER: Name: Hugh Wagstaff Telephone: 01483 523363 E-mail: [email protected]
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Parking improvements at College Gardens, FarnhamReport | 91 KB | DownloadRead as text |
Follow Executive (Acting as Trustee of the Joseph Ewart Bequest) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Apr 2022 | Funding Request - Replacement of timber and glazed porches at College Gardens, FarnhamRESOLVED That the Executive acting as Trustee of the Joseph Ewart Bequest gives approval to progressing and completin... | Approved | Open |
| 3 Nov 2020 | Ewart Bequest - Greenfield Road UpdateRESOLVED to: 1. note the contents of the update report; 2. agree to the proposed enhanced level of specification to s... | Noted | Open |
| 12 Jul 2016 | Exclusion of Press and PublicRESOLVED that, pursuant to Procedure Rule 20, and in accordance with Section 100A(4) of the Local Government Act 1972... | Decided | Open |
| 1 Mar 2016 | Parking Improvements at College Gardens, FarnhamRESOLVED that 1. approval be given to progressing the car parking improvements at College Gardens including the procu... | Approved | Open |
| 1 Mar 2016 | Delivery of Affordable Homes at Greenfield Road, FarnhamRESOLVED that approval be given to: 1. a budget of £10,000 to enable legal and surveyor’s advice to be sought on the ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.