Matters arising from the formal review of the Inter-Authority Agreement and the Collaboration Risk Register (December 2022)

Agreed Committee 1 paper

Guildford & Waverley Joint Governance Committee agreed this item on Friday 17 March 2023. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED to recommend to Guildford and Waverley Councils that clause 21.1 of the Inter-Authority Agreement be amended to read: “21 TERMINATION FOR CLAUSE 21.1 Without affecting any other right or remedy available to it, any Party may terminate this Agreement with immediate effec t by giving written notice to a minimum of three months’ notice in writing to the other Party.”
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Guildford & Waverley Joint Governance Committee

Background

1.1The Joint Government Committee’s terms of reference include a requirement to undertake periodically a formal review (at least once every 12 months) of the inter-authority agreement (IAA), ensuring it continues to be fit for purpose and recommending to both Full Councils any changes required. The Committee is also required to undertake a six-monthly review of the Collaboration Risk Register.

1.2The Joint Governance Committee undertook the first formal review of the IAA and the Collaboration Risk Register at its meeting held on 9 December 2022. In their discussion on the review of the risk register, the Committee raised a number of queries in respect of specific risks. With regard to Risk No. 6 (that either or both councils will decide to terminate the partnership), councillors queried the relation of this risk to clauses 21 and 22 of the IAA, which currently read as follows:

“21. TERMINATION FOR CAUSE

21.1Without affecting any other right or remedy available to it, any Party may terminate this Agreement with immediate effect by giving written notice to the other Party: 21.1.1. if the other Party commits a material breach of any term of this Agreement which breach is irremediable or (if such breach is remediable) fails to remedy that breach within a period of fourteen days after being notified in writing to do so;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Matters arising from the formal review of the Inter-Authority Agreement and the Collaboration Risk Register (December 2022)Report 543 KB DownloadRead as text

At this meeting

Whole meeting
8Minutes of the previous meetingOn the agenda
10Matters arising from the formal review of the Inter-Authority Agreement and the Collaboration Risk Register (December 2022)This decision
11Collaboration Risk Register ReviewAgreed

Who was there

11 of 14 attended
PF
Councillor Paul FollowsJoint Chair, present
JM
Councillor Julia McShaneJoint Chair, present
PC
Councillor Peter ClarkCommittee Member, present
JB
Councillor Joss BigmoreCommittee Member, apologies
GE
Councillor Graham EyreCommittee Member, apologies
MG
Councillor Michael Goodridge MBECommittee Member, present
PM
Councillor Peter MarriottCommittee Member, present
SM
Councillor Stephen MullinerCommittee Member, present
RN
Councillor Ramsey NagatyCommittee Member, present
GP
Councillor George PotterCommittee Member, apologies
JR
Councillor John RedpathCommittee Member, present
JR
Councillor John RobiniCommittee Member, present

All 14 on the meeting page

More from Waverley Guildford & Waverley Joint Governance Committee

All decisions
MeetingDecisionOutcome
17 Mar 2023 Collaboration Risk Register ReviewAgreed that the Residual likelihood and impact of #22 (risk that employees ... view the full minutes text for item 11. Agreed Open
9 Dec 2022 Formal Review of the Inter-Authority AgreementRESOLVED to recommend to the Guildford Corporate Governance & Standards Committee and the Waverley Standards & Genera... Decided Open