Approval to commence tendering for Kitchen and Bathroom Installation Contract
DecidedExecutive1 paper
Executive Co-Portfolio Holder for Housing Decisions decided this item on Thursday 26 September 2024. Below is the council's own wording, with the papers it was decided on.
Having considered the comments of the Landlord Services Advisory Board (Executive Working Group), the Executive Co-Portfolio Holder for Housing (Operations) and Services, Councillor Paul Rivers, RESOLVED to, Recommendation 1. Commence the procurement for kitchen and bathroom replacements with the assistance of GBC Procurement. 2. The recommended route to market of a mini competition run through the LHC Framework (Refurbishment & Modernisation Framework (RM3) and in accordance with the relevant procurement legislation. 3. The involvement and engagement of the Tenant Panel as part of the procurement process. Reason(s) for Recommendation: 1. The current contract with the incumbent contractor is due to expire in March 2026, but due to an uplift in kitchen and bathroom installation works required we are seeking enhanced supplier capability. 2. A mini competition run through the LHC Framework - Refurbishment & Modernisation Framework (RM3) will deliver value for money to the Council.
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
Report to Executive Co-Portfolio Holder for Housing Decisions
Executive summary
1.1.The report outlines the request for approval to commence procurement for kitchen and bathroom replacements for a period of up to four years on an initial 2yr award with an extension period of 1yr + 1yr. The anticipated value of the contract is up to £12m over the four years.
2. Recommendation to Executive
2.1.That the Executive Co-Portfolio Holder for Housing (Operations) and (services) approves commencement of procurement for kitchen and bathroom replacements with the assistance of GBC Procurement. 2.2.That the Executive Co-Portfolio Holder for Housing (Operations) and (services) approves the recommended route to market of a mini competition run through the LHC Framework (Refurbishment & Modernisation Framework (RM3) and in accordance with the relevant procurement legislation.
3. Reason(s) for Recommendation:
3.1.The current contract with the incumbent contractor is due to expire in March 2026, but due to an uplift in kitchen and bathroom installation works required we are seeking enhanced supplier capability.
3.2.A mini competition run through the LHC Framework - Refurbishment & Modernisation Framework (RM3) will deliver value for money to the Council.
4. Exemption from publication – No
Purpose of report
5.1.To seek authority to commence procurement for the kitchen and bathroom replacement contract for the financial years 2025 to 2029 on a 2yr (+1yr+1yr) duration. The is initially for the period 2025 to 2027 with an extension provision for the years 2027/8 and 2028/9. 6. Strategic Priorities
6.1.The report supports the Council’s Corporate Commitment to promote Safe Compliant Homes for our tenants and aim to be the best council landlord in the Southeast and to be acknowledged as such.
Background
7.1.The Council is responsible for providing new kitchens and bathrooms when these assets become beyond economic repair and in keeping with decent homes standards.
7.2.The current contract with the incumbent supplier expires in March 2026, but due to an uplift in contract spend we are seeking to re- procure due to supplier capacity requirements.
8. Consultations
8.1.No formal consultations are required
9. Key Risks
9.1.The recommendation ensures that capital works programmes for the replacement of kitchens and bathrooms can continue.
Financial implications
10.1As part of the budget setting for 2025/26 finance will work with the service to ensure the cost of this new contract is included. Contracts will be delivered within the budgets approved at Council in February.
Legal implications
11.1The Council wishes to procure a contractor for kitchen and bathroom replacements Works. The estimated value of the proposed procurement is £12m thus falling within Threshold 4 (Procurements valued over £150,000) of the Council’s Contract Procedure Rules which means that a competitive tender process should be followed in accordance with the relevant legislation. 11.2. As the value of the proposed contract exceeds the relevant threshold for Works under both the Public Contracts Regulations 2015 and the Procurement Act 2023 (the “Procurement Legislation”) (depending on when the procurement exercise will commence), there is an express obligation on the Council to comply with the Procurement Legislation.
11.3Legal advice shall be sought to ensure that the proposed procurement exercise is compliant with the relevant requirements and the Best Value duty is complied with.
12. Human Resource Implications - None
13. Equality and Diversity Implications - None
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive Co-Portfolio Holder for Housing Decisions at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.