Overview and Scrutiny Committee - Resources noted this item on Tuesday 23 September 2025. Below is the council's own wording, with the papers it was decided on.
RESOLVED that 1. The significant achievements of the project, and the lessons learned, while recognising the need for continued evaluation of cost-effectiveness and benchmarking against sector standards, be noted. 2. The successful completion of the Ockford Ridge Deep Retrofit Pilot, including the delivery within budget and the achievement of enhanced ... view the full minutes text for item OSCR20/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
Report to Overview and Scrutiny Committee - Resources
Deep Retrofit Green Technology Pilot Project Update
Ockford Ridge, Godalming September 2025 Ockford Ridge, Deep Retrofit - Green Technology Pilot • Background & Objectives • Delivery • Finance • Key Achievements and successes • Photographs • Questions Background Whole house deep retrofit, green technology pilot. • Project aim – to provide seven (6 x 2b 4p and 1 x 3b 5p adapted) modern, affordable and energy efficient homes with enhanced fabric using external and floor insulation and replacement of the use of fossil fuels with green renewable energy sources and technology. Objectives A number of objectives were set out in the committee report considered in March 2023
• Demonstrate its commitment to its Climate Emergency declaration and how it can retrofit its homes to ensure their energy performance is fit for a carbon-neutral energy system • Demonstrate its intent to invest in our housing stock and how much implementing the commitment costs, informing the details required as part of the Council’s call to government to provide long term funding solutions to support delivery of local and national climate targets • Take a ‘learning through doing’ approach which with monitoring, evaluation, and documentation, will provide an enhanced understanding of the whole house retrofit process and identify areas of cost reduction, replicability, and scalability to potentially develop larger-scale programmes • Develop handover advice and training on the upgrade of fabric envelop and systems that ensure efficient interaction and operation of the property • Undertake post retrofit insitu measurement and monitoring of the performance of the property and post occupancy evaluation • Use the pilot and lessons learnt to assist when bidding for future funding programmes • Maximise the potential and value of a Council owned asset
Links to Committee Papers - Executive – 7 March 2023 Full Council – 21 March 2023 Delivery • The original fixtures and fittings were removed, including the old gas boilers, and the walls were stripped back to the original brick / block and some homes were reconfigured. • The homes were re-wired, plastering renewed, new flooring and loft insulation added and the EWI fitted to bring an entirely new and considerably higher level of overall insulation • For further improvements in energy efficiency beyond the insulation, we have installed Air Source Heat Pumps (ASHP) and photovoltaic (solar) panels • The homes also have Mechanical Ventilation and Heat Recovery (MVHR) to extract stale, moist air from a building and simultaneously bring in fresh, filtered air from outside. The key feature of MVHR is its ability to recover heat from the extracted air, transferring it to the incoming air to minimize heat loss and improve energy efficiency. Delivery • Key Risks • Contractor and contract management • A number of challenges faced and overcome • JCT contract programme – works commenced September 2023 and completed a year later, two months behind schedule • Lessons Learned Finance Full Council 21 March 2023 - Post tender budget funded from the Major Repairs Reserve was approved £1.765m.
(The original budget £981k was approved in February 2022 however inflationary pressures and construction cost uplifts impacted on the value of the works and tenders received so and an additional budget £784k was sought) Approved Budget vs Actual Spend 2.1
1.8£108k underspend 1.5 on £1.76m budget 1.2 £m
0.9
0.6
0.3
0 Budget (£1.76m) Actual spend (£1.61m) Finance Total increase in property value £785k Property valuation (UK House Price Index states that value of 3.4 property in the area declined in this period) 3.1 2.8 2.5 The financial appraisal for the project shows that the units £m
2.21.9 within the pilot still have positive impact to the business 1.6 plan over both 30 and 60 years. 1.3 1 January 2023 April 2024 • Net Income over Business Plan (30 years) -£3,912,153 • Net income over life of asset (60 years) -£13,713.867
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Committee - Resources at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.