Resolved
RESOLVED that the Quarter 2 Performance Monitoring report be noted.
AI summaryWaverley Overview and Scrutiny Committee noted the Quarter 2 financial monitoring report, which forecasts a £452k General Fund saving and a £933k Housing Revenue Account saving, plus a £246,000 supplementary estimate for homelessness.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that the Quarter 2 Performance Monitoring report be noted.
1.1This report summarises the forecast outturn for General Fund Revenue, Housing Revenue Account and General Fund Capital for the 2025/56 financial year. Included is the Quarter 2 position.
2.1That the committee:
2.1.1 Notes the Quarter 2 financial monitoring report contained in Appendix 1 – 8 of this report. 2.1.2 Note the request for a supplementary estimate of £246,000 to cover the cost of additional temporary accommodation in the Homelessness Service, to be funded from the Homelessness Prevention Grant Reserve.
3 Reason(s) for recommendation:
3.1To ensure that Councillors fulfil their responsibilities for the overall financial management of the Council’s resources.
3.2To ensure budget is in place to deliver specific service requirements.
4 Next steps
4.1This report will be taken to Executive and Council.
4.2The 2025/26 forecast outturn and any variances will be used to help inform budget setting for 2026/2027.
5 Exemption from publication
5.1This report is not exempt from publication.
6 Background and Proposal
6.1The purpose of this report is to present the quarterly financial reporting for Quarter 2 of the 2025/26 financial year. The Appendices will detail any variances reported to date and include Assistant Director commentary on
2 Financial Monitoring 2025-26 Qtr 2
those variances. Also included is an update on the debt position and reserves.
General Fund Revenue
6.2As shown in Appendix 1, there is currently a saving on £452k forecast within the general fund. Appendix 2 provides Assistant Directors’ commentary on the reason behind variances within their service areas.
6.3The key variances forecasts are as follows:
6.4Establishment budget underspends. £727k of underspend is being forecast on staffing budgets for 2025/26. This is not reflective of resourcing need and is often as a result of hard to fill posts or job evaluation/market testing being required.
6.5Overachievement of building control income totalling £53k is being forecast for 2025/26. This is compared to a budget of £664k. Performance in the first quarter was increased versus prior years, this will continue to be monitored throughout the year.
6.6Waverley Training Services is forecasting an underachievement of income of £102k. However, the Service has made efforts to mitigate this shortfall, including vacancy savings and other cost reductions, bringing the overall variance down to £22.8k. A three-year business plan has been introduced to address the ongoing deficit, and progress will be monitored throughout the financial year 2025/26.
6.7Planning fee income is forecast to overachieve by £143k based on Quarter 1 performance. This will be monitored throughout the financial year 2025/26. It should be noted that there is a requirement to increase budgets for staffing and appeals spend in this area and this additional income will likely be utilised for this.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FINANCIAL MONITORING 2025-26 QTR. 2Report | 760 KB | DownloadRead as text |
PDF |
Financial Monitoring Q2: Appendix 1 to 8 finalAppendix | 492 KB | Download |
PDF |
TM Mid Year ReportReport | 373 KB | Download |
Follow Overview and Scrutiny Committee at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | Committee Work ProgrammeThat subject to the following amendments, the work programme submitted to the Committee be approved: 1. Wey Court Eas... | Approved | Open |
| 9 Mar 2026 | Committee Work Programmethat the Committee Work Programme be noted. | Noted | Open |
| 9 Feb 2026 | Ombudsman Complaints Received and Closed in 2024 - 25That the Committee notes the 100% rate of maladministration found by the Ombudsman in respect of Landlord Services fo... | Agreed | Open |
| 9 Feb 2026 | Committee Work ProgrammeThat the Committee Work Programme be noted. | Noted | Open |
| 26 Jan 2026 | Housing Revenue Account Budget 2026-27(1) To thank the team for production of the HRA Budget, be agreed. (2) That the 4.8% increase on weekly rent for coun... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.