Indicative Audit Plan

Noted Finance 2 papers

AI summaryThe Audit and Risk Committee noted Grant Thornton's indicative audit plan for the 2025/26 accounts. Waverley already holds an unmodified opinion for 2024/25, ahead of most district and borough councils.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee recorded external auditor's plan
MoneyNot stated
What happens nextImplement the planProduce and sign 2025/26 accounts on time
Who it affectsWaverley's accountsCouncil's annual statement of accounts

What was decided

The committee noted the indicative audit plan for 2025/26 from the external auditors, Grant Thornton. Report 2.1, 15.1

The plan is intended to support the production of signed accounts by the statutory deadline. Report 16.1, P1

Why

Part of the committee's remit is to review and approve the annual Statement of Accounts, including considering whether appropriate accounting policies have been followed. Report 3.1, 11.1

Waverley received an unmodified opinion for the 2024/25 accounts, putting it ahead of most district and borough councils, 68% of which received disclaimed opinions for 2023/24. Report 7.2, P13

The finance team has reviewed the plan and agreed the key points and timelines with the external auditors. Report 8.1

What happens next

Follow the indicative audit plan so the 2025/26 accounts can be signed and published by the statutory deadline. Report 16.1, 7.1

The cost of audit fees sits within the 2026/27 budget, with no direct financial implications from this report. Report 10.1

Options considered

  • Chosen: Note the indicative audit plan for 2025/26. Recommended so the committee can fulfil its role reviewing the annual accounts. Report 15.1, 2.1, 3.1

Implications

  • Legal: The committee is required to review and approve the annual Statement of Accounts under the Audit and Accounts Regulations 2015. Report 11.1, 7.1
  • Risk: Failure to comply with the statutory publication requirements can raise the risk of inadequate control over the proper use of public funds. Report 9.1
  • Financial: No direct financial implications; the budget for audit fees is included in the 2026/27 budget. Report 10.1
  • Staffing: No direct human resource implications. Report 12.1
  • Equalities: No direct equality and diversity implications. Report 13.1
  • Climate: No direct climate change or sustainability implications. Report 14.1

Who and where

  • Waverley Borough Council, as the body whose accounts are audited Report P1, 6.1
  • Council taxpayers and the public, through the assurance of proper management of public funds Report 6.1

Timeline

  • End of February 2024: 68% of district and borough councils received a disclaimed opinion for their 2023/24 audits. Report 7.2
  • 2024/25: Waverley received an unmodified audit opinion. Report 7.2
  • 2025/26: The financial year covered by the indicative audit plan. Report P1, 2.1
  • 2026/27: Audit fees are budgeted for in this year's budget. Report 10.1

Plain English for the jargon

  • Unmodified opinion: An auditor's statement that the accounts give a true and fair view, with no significant concerns raised.
  • Disclaimed opinion: An auditor's statement that they cannot form an opinion on the accounts, often because evidence is insufficient.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAUD 62/25

Resolved

Resolved that: The from Grant Thornton be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Audit & Risk Committee

Executive summary

Our external auditors, Grant Thornton, have provided the indicative audit plan the 2025/26 audit of Waverley’s accounts.

2. Recommendation to Executive/ Committee/ Council

That the committee notes:

2.1The indicative audit plan 2025/26 (Annexe 1)

3. Reason(s) for Recommendation:

3.1Part of the remit of audit and risk committee is to review and approve the annual Statement of Accounts. Specifically, to consider whether appropriate accounting policies have been followed and whether there are concerns arising from the financial statements or from the audit that need to be brought to the attention of the Full Council. This plan outlines the timeline, risks and approach to the annual audit.

4. Exemption from publication

4.1No

Purpose of report

5.1The purpose of this report is to present our external auditor, Grant Thornton’s, indicative audit plan for 2025/26 to the audit committee. 6. Strategic Priorities

6.1The audit and publication of the statement of accounts fulfils a statutory and strategic requirement demonstrating value for money and the proper management of public funds.

Background

7.1The Audit and Accounts Regulations 2015 set out the requirements for local authorities to prepare and publish their statement of accounts. These regulations have been amended due to the delays in the publication and audit of accounts across the sector which have occurred for a variety of reasons.

7.2Waverley received an unmodified opinion for the 2024/25 accounts. As at the end of February 2024, 68% of district/borough Councils received a disclaimed audit opinion for their 2023/24 audits. Data suggests that similar, or higher levels of disclaimed opinion are expected for the 2024/25 audits, due to lack of assurance over prior-year balances.

This puts Waverley in a good position compared to other authorities, being one of a few Councils with up to date accounts with unmodified opinions, and this indicative audit plan and timeline will help support the Council to ensure a quality and timely audit of the accounts.

8. Consultations

8.1The finance team have reviewed this plan with the external auditors and agree to the key points and timelines.

9. Key Risks

9.1Production and publication of the statement of accounts is a statutory requirement and failure to comply with these requirements can raise the risk of inadequate control being in place for the proper use of public funds. 10. Financial Implications

10.1No direct financial implication as a result of this report. The budget for the audit fees is included in the 2026/27 budget.

11.1The Audit and Risk Committee is responsible for reviewing and approving the annual Statement of Accounts. This is a requirement as set out in the Audit and Accounts Regulations 2015.

12. Human Resource Implications

12.1No direct implications.

13. Equality and Diversity Implications

13.1No direct implications.

14. Climate Change/Sustainability Implications

14.1No direct implications.

15. Summary of Options

15.1The committee is asked to note this audit plan.

16. Conclusion

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Indicative Audit PlanReport 462 KB DownloadRead as text
PDF
WBC Indicative Audit Plan 25-26 030326 62/25Report 4.7 MB Download

At this meeting

Whole meeting

Who was there

5 of 7 attended
JS
Councillor Julian SpenceChair, present
MH
Councillor Michael HigginsVice Chair, apologies
ZB
Councillor Zoe Barker-LomaxCommittee Member, present
DB
Councillor David BeamanCommittee Member, present
JD
Councillor Jerome DavidsonCommittee Member, present
MG
Councillor Maxine GaleCommittee Member, apologies
GM
Councillor George MurrayCommittee Member, present

More from Waverley Audit & Risk Committee

All decisions
MeetingDecisionOutcome
27 Jul 2026 Management of Asbestos containing Material in Corporate Property and AssetsRESOLVED that the Management of Asbestos containing Material in Corporate Property or Assets be noted. Noted Open
27 Jul 2026 Whistleblowing PolicyRESOLVED that the be adopted. Approved Open
27 Jul 2026 Annual Information Governance and Data Transparency ReportRESOLVED that the Annual Information Governance and Data Transparency report be noted. Noted Open
27 Jul 2026 Local Code of Corporate GovernanceRESOLVED that the Local Code of Corporate Governance be approved and adopted. Approved Open
27 Jul 2026 Data Protection Annual ReportRESOLVED that: · The Data Protection Annual report be noted. · A further report be brought to the final meeting of Wa... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies