West Surrey Constitution: Contract and Procurement Procedure Rules
AgreedFinance3 papers
AI summaryWest Surrey shadow committee agrees approach to new Contract and Procurement Procedure Rules ahead of 1 April 2027 Vesting Day, with detailed rules to return in October 2026.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedRevised rules to return with more detail
MoneyNo direct financial implicationsDifferent thresholds may add resource costs
What happens nextDetailed rules back in October 2026Then Standards Committee, Shadow Authority
Who it affectsNew West Surrey unitary authorityEffective from 1 April 2027 Vesting Day
What was decided
The committee agreed the proposed approach and details for the Contract and Procurement Procedure Rules set out in the report. Report P6
Members asked for the revised Procedure Rules to return to a future committee with more detail on contract management arrangements and governance thresholds. Report P7
Why
Section 9P of the Local Government Act 2000 and section 135 of the Local Government Act 1972 require the new unitary authority to have approved standing orders in place by Vesting Day. Report 1.2, P62
Robust rules are needed to comply with the Procurement Act 2023, the Procurement Regulations 2024 and the Public Services (Social Value) Act 2012. Report 8.2, P63
Without rules in place by Vesting Day, the new authority would be at risk of breaching section 151 of the Local Government Act 1972 and facing unlawful procurement activity. Report 8.1, P66
What happens next
High Level Principles go to the Constitution Sub Committee on 17 September 2026. Report 4.2
Detailed Procedure Rules return to the Audit and Governance Committee in October 2026, then the Constitution Sub Committee on 29 October 2026. Report 4.3, 4.4
Standards Committee on 2 November 2026, then Shadow Authority approval, with adoption into the West Surrey Constitution from Vesting Day. Report 4.5, 4.6
Options considered
Chosen: Adopt thresholds based on existing Surrey County Council values, as proposed. Familiar to transferring managers, matches existing procurement capacity, supports post-vesting aggregation Report P41, P42
Rejected: Set lower financial thresholds than those proposed. Would need extra procurement resource or slow down procurement activity Report P55
Implications
Legal: Supports compliance with the Local Government Act 2000, Local Government Act 1972, Procurement Act 2023 and Procurement Regulations 2024. Report P62, P63
Financial: No direct financial impact, but the Section 151 Officer notes a very challenging financial environment from 2027/28 and the need to protect value for money. Report P53, P57, P58
Risk: Main risk is not having comprehensive Contract and Procurement Procedure Rules in place by Vesting Day, leading to non-compliant procurement and potential challenge. Report 8.1, 8.2, P66
Staffing: No immediate staffing restructure, but officers across the new authority will need training on the procurement lifecycle, thresholds, delegations and contract management. Report P70
Equalities: No direct equality impacts from this report; equality duty is considered for each individual procurement. Report P72
Climate: No direct climate or sustainability impacts from this report; considered per procurement. Report P74
Who and where
Officers of the new West Surrey Council, who must sign up to the constitution and abide by the procedure rules Report P61
Members of the Shadow Authority and future West Surrey Council Report P68
Suppliers and contractors tendering for work with the new authority Report P66
Predecessor district and borough councils whose activity will be aggregated into the new unitary Report P42
Timeline
3 September 2026: High Level Principles considered by Audit and Governance Committee Report 4.1
17 September 2026: High Level Principles to Constitution Sub Committee Report 4.2
October 2026 (date to be agreed): Detailed Procedure Rules to Audit and Governance Committee Report 4.3
29 October 2026: Detailed Procedure Rules to Constitution Sub Committee Report 4.4
2 November 2026: Standards Committee considers for recommendation to Shadow Authority Report 4.5
1 April 2027: Vesting Day for the new West Surrey Council, when the Standing Orders take effect Report 1.4, 4.6
Plain English for the jargon
LGR: Local Government Reorganisation, the process creating the new West Surrey unitary authority.
Vesting Day: The date the new unitary authority comes into legal existence, set for 1 April 2027.
Standing Orders: Formal written rules governing how the council operates, makes decisions and handles contracts.
Shadow Authority: The interim body preparing for the new West Surrey Council before it formally takes over.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11AG
Resolved
RESOLVED that 1. The proposed approach and details provided in respect of the Contract and Procurement Procedure Rules as set out in the agenda report be agreed. 2. the revised Contract Procurement Procedure Rules be brought back to a future Committee with further detail on contract management arrangements and governance thresholds.
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1This report presents and invites comment on the principles of the proposed content for the Contract and Procurement sections of the new Standing Orders for West Surrey.
1.2Section 9P of the Local Government Act 2000 requires every local authority to prepare, maintain, and keep up to date a formal constitution. This document controls how the local council operates, makes decisions, and handles its governance.
1.3The sections relating to Contracts and Procurement set out how the Council authorises and manages expenditure and resulting commercial contracts with other organisations.
1.4It is therefore essential that the new unitary authority of West Surrey Council establishes new Standing Orders to be effective from Vesting Day on 1 April 2027, and that the detail of the Contract and Procurement elements of those standing orders are agreed in time to establish required process and controls ahead of vesting day.
Recommendations
2.1It is recommended that the West Surrey Shadow Authority Audit and Governance Committee resolves to:
2.1.1. Agree the proposed approach and details provided in respect of the Contract and Procurement Procedure Rules as set out in this report;
2.1.2. Comment on the proposed heads of terms set out in Annex 1 to this report, ‘Proposed Procurement and Contract Procedure Rules Structure and Content Framework’; and
2.1.3. Comment on the proposed key governance thresholds and related detail set out in Annex 2 to this report ‘Proposed Thresholds, routes to market, delegation of authority for contract award etc’.
3. Reason(s) for recommendation:
3.1It is a legal requirement for the new unitary authority to have an approved set of Standing Orders effective from Vesting Day. Officers need a steer from Members as to the development of the Contract and Procurement sections of the Standing Orders.
2 West Surrey Constitution: Procurement and Contract Standing Orders/Procedure Rules
4. Next steps –
4.1High Level Principles to Audit and Governance Committee 3 September 2026
4.2High Level Principles to Constitution Sub Committee 17 September 2026
4.3Detailed Procedure Rules to Audit and Governance Committee in October 2026 on a date to be agreed
4.4Detailed Procedure Rules to Constitution Sub Committee 29 October 2026 for recommendation to Standards Committee
4.5Standards Committee 2 November 2026, for recommendation for approval to the Shadow Authority
4.6Approval by the Shadow Authority and adoption into the West Surrey Constitution from Vesting Day, at a date to be arranged.
5. Exemption from publication
5.1None of this report is exempt from publication.
6. Background and Proposal
6.1Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.