RESOLVED that on a without prejudice basis, the application be DEFERRED to request additional information and amendments to the layout of the proposal to resolve matters relating to drainage and the identified flood risk of the development. The following member of the public spoke in favour of the application. Graham Wilson – Planning Consultant John Longhorn – Applicant ( Vistry ) Note: 1. Councillor White declared a personal interest in this item. 2. The Committee adjourned for a 15 minute comfort break at 12.30pm following consideration of this item.
Word for word from the decision Wealden published for this meeting.Source: council.wealden.gov.uk
For: Planning Committee South Date: 1 December 2022 WD/2021/2678/MRM - LAND TO THE WEST OF ERSHAM ROAD, SUMMERHILL, HAILSHAM
Summary of Proposal
Major Application - Reserved Matters application for:- RESERVED MATTERS PURSUANT TO OUTLINE APPLICATION WD/2019/2692/MAO (OUTLINE APPLICATION FOR THE ERECTION OF UP TO 241 NO. RESIDENTIAL DWELLINGS INCLUDING AFFORDABLE HOUSING AND PROVISION OF A NEW VEHICULAR ACCESS FROM ERSHAM ROAD. ALL OTHER MATTERS ARE RESERVED) TO CONSIDER ALL OUTSTANDING MATTERS INCLUDING APPEARANCE, LANDSCAPING, LAYOUT AND SCALE, AND ASSOCIATED CAR PARKING AND INFRASTRUCTURE.
Received date: 7 December 2021 Parish: Hailsham 8/13 week date: 8 March 2022 Ward: Hailsham South Grid Ref: 558618 107676 Link to website: https://planning.wealden.gov.uk/plandisp.aspx?recno=155822 https://council.wealden.gov.uk/ieListMeetings.aspx?CommitteeId=660
Recommendation Reserved Matters BE APPROVED, subject to the following conditions:-
1. The development hereby approved shall be commenced no later than one year from the date of this decision notice. STD5
REASON: For the avoidance of doubt.
2. Prior to the commencement of development, a details of the proposed fluvial flood mitigation measures shall be submitted to and approved in writing by the Local Planning Authority. These shall be in accordance with Ardent Drawing No. 2103570- SK08 Rev A dated October 2022 and incorporate the following:
a. Detailed and construction drawings which show the proposed bund, the culverts, swales and a swale from the culvert crossing the bund to the watercourse. These should include long sections and cross-sections. Erosion protection measures on the flow path within the play areas should be provided. b. Calculations and design from a geo-technical engineer demonstrating that the bund design is structurally stable and resilient with minimal risk of failure. c. Details of the proposed attenuation basins and the site levels around them. These should demonstrate that there will not be any ingress of surface water overland flow or fluvial flows into the attenuation basin and that there is a freeboard provided above the predicted flood level during a 1 in 100 (plus climate change event). The site levels shall show that surface water flows will be conveyed around the basins to lower levels and the watercourse. For: Planning Committee South Date: 1 December 2022
d. Details demonstrating that the finished floor levels of the foul pumping station are above a predicted flood level during at least a 50% blockage scenario of the culvert under the Cuckoo Trail. This should also be accompanied by details demonstrating that the foul manholes within the fluvial flood plain will not allow the ingress of surface water flows into the foul drainage system. e. Evidence that overland flow routes that can affect more than one property have been located in communally maintained spaces.
REASON: In order to secure a satisfactory standard of development, having regard to SPO12, SPO13 and WCS14 of the Wealden Core Strategy Local Plan 2013 and Saved Policy CS2 of the adopted Wealden Local Plan 1998.
3. Prior to occupation of the first house the following information shall be submitted and agreed to in writing by the Local Planning Authority:
a. A simplified Flood Plan for the LAP detailing measures which should be taken during a flood event to prevent significant risk to the life of the users of the area. b. Evidence that appropriate signs have but displayed to show that both the NEAP and LAP have been designed to flood. c. Evidence that an appropriate maintenance programme is in place for all the flood mitigation measures including the bund and culverts together with the details of the organisation which will be responsible for the maintenance for the lifetime of the development.
REASON: In order to secure a satisfactory standard of development, having regard to SPO12, SPO13 and WCS14 of the Wealden Core Strategy Local Plan 2013 and Saved Policy CS2 of the adopted Wealden Local Plan 1998.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.