Audit and Governance Committee, Wednesday 16 September 2026

Internal Audit Progress Report - April to August 2026

Decided Finance 4 papers

AI summaryAudit and Governance Committee notes April to August 2026 internal audit progress, with no new high risk areas found and control systems judged adequate and effective.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee considered contents appropriate to its governance role
MoneyNot stated
What happens nextQ3 audits due to commenceBenefits, ICT-Digital, Creditors, Recovery, Assets, AI Governance
Who it affectsCouncil's internal control systemsFound adequate and effective, with no new high risk areas

What was decided

The committee noted the contents of the Internal Audit Progress Report covering April to August 2026 and considered them appropriate to its governance role. Report P3

Why

Work in 2026/27 has not identified any new areas of high risk, so the Council's internal control systems currently remain adequate and effective. Report P2, P17

The report meets expectations for openness and transparency in local government and the requirements of the Global Internal Audit Standards (UK public sector). Report P5

What happens next

Six further audits are due to commence in Quarter 3, covering Benefits, ICT-Digital Services, Creditors, Recovery and Enforcement, Asset Management, and AI Governance. Report P6

The Audit Manager will continue to follow up the nine outstanding recommendations on a quarterly basis. Report P6

Options considered

  • Rejected: Options for the committee to consider. Not applicable for this progress update Report P7

Implications

  • Legal: Noting the report supports compliance with internal audit requirements under the Accounts and Audit (England) Regulations 2015. Report P11
  • Staffing: Long-term sickness absence in the internal audit team has temporarily affected resources, though good progress against the Audit Plan has still been achieved. Report P6
  • Climate: There are no climate implications arising from the recommendations of the report. Report P11
  • Equalities: The report has been written in plain English and reviewed for accessibility as it is a public document. Report P14

Who and where

  • Wealden District Council's governance and assurance framework Report P4, P2
  • Council services subject to completed, in progress, or upcoming internal audits, including Climate Change, Payroll, Cash and Banking, Treasury Management, General Ledger, Debtors, Council Tax, Housing Rents, Procurement, Accessibility, NDR, Benefits, ICT-Digital Services, Creditors, Recovery and Enforcement, Asset Management, and AI Governance Report P6

Timeline

  • April to August 2026: Period covered by the Internal Audit Progress Report, during which two final reports (Climate Change and Payroll) were issued and one draft report (Cash and Banking) was issued to the client service. Report P1, P2, P6
  • Quarter 3 2026: Six further audits are scheduled to commence: Benefits, ICT-Digital Services, Creditors, Recovery and Enforcement, Asset Management, and AI Governance. Report P6
  • Financial year-end 2026/27: All governance audits remain on track to be completed. Report P6
  • 16 September 2026: Audit and Governance Committee noted the progress report at its meeting. Report P1

Plain English for the jargon

  • Internal audit: An independent review function that identifies areas requiring improvement and recommends actions to help the Council achieve its objectives.
  • Global Internal Audit Standards (UK public sector): The standards that set expectations for internal audit work in UK local government bodies.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAGC59/26

Resolved

That the contents of the report and comments was considered appropriate to its governance role.
Word for word from the decision Wealden published for this meeting. Source: council.wealden.gov.uk

Follow this further

Built from Wealden's papers

What the report saysPro

Report to Audit and Governance Committee

Internal Audit Progress April - August 2026 Report To: Audit and Governance Committee Date of decision: Wednesday, 16 September 2026 Access: Public document (not exempt from disclosure)

Executive Summary This report provides the Committee with an update on the internal audit work undertaken during the period April to August 2026 and advises on the projected completion of the remaining internal audits. It is management’s responsibility to establish and maintain a sound internal control system and ensure that risks are appropriately managed. Internal audit work aims to identify areas requiring improvement and to recommend actions to enable the Council to achieve its objectives. Work conducted has concluded that there are no new areas of high risk and that consequently, the Council's internal control systems remain adequate and effective.

Recommendations The Committee is recommended to: Note the contents of this report and make any comments considered appropriate to its governance role.

Council Strategy The role of internal audit is integral to the Council’s governance and assurance framework and supports the priorities in the Council Strategy.

Reasons for the recommendation The report meets the expectations for openness and transparency within local government, and the requirements of the Global Internal Audit Standards (UK public sector).

v25/02 Summary of Audit Activity 1. The Annual Audit Plan consists of a mix of self-contained audits of specific services or functions. The governance audits are completed every year and worked on incrementally throughout a rolling year. This approach provides for the early detection of issues as, or very soon after they arise. It also reinforces the understanding that Internal Audit is a service to management and there to support the organisation in achieving good governance in delivering its objectives. 2. Two final reports were issued during the period covered by this report. The summary findings from each of these audits are provided at Appendix A and the assurance level definitions are at Appendix C. a. Climate Change b. Payroll 3. Draft reports have been issued to the client service for the following audit: a. Cash and Banking 4. Fieldwork has been completed and reports are currently being drafted for: a. Treasury Management b. General Ledger c. Debtors 5. The following audits are work in progress at this stage: a. Council Tax b. Housing Rents c. Procurement d. Accessibility e. NDR 6. Audits commencing in Quarter 3 are: a. Benefits b. ICT-Digital Services c. Creditors d. Recovery & Enforcement e. Asset Management f. AI Governance 7. The team has experienced some long-term sickness absence this year which has temporarily affected our resources. However good progress has still been achieved against the Audit Plan and we remain on track to complete all governance audits by the financial year-end. Outstanding Recommendations 8. When a recommendation is made during an audit, an implementation date is agreed and a responsible officer identified. These are agreed with the service and referenced in the final report. All recommendations are followed up by Internal Audit on a quarterly basis to ascertain whether the recommendations have been actioned and any reasons for non-implementation are sought, including a revised implementation date. The Global Internal Audit Standards (UK public sector) require the following ‘the Committee should also oversee the tracking and implementation of the actions agreed following audits’. Accordingly, a summary of the nine recommendations which are currently outstanding has been provided in Appendix B.

Options 9. Not applicable

Consultation 10. Not applicable

Considerations The following considerations were taken into account in making the recommendation in this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audits completed April-Aug 2026 /26Appendix A 301 KB Download
PDF
Outstanding recommendations /26Appendix B 81 KB Download
PDF
Assurance Level Definitions /26Appendix C 72 KB Download
PDF
Internal Audit Progress Report: April to August 2026Report 88 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 21 attended
JH
Councillor Jessika HulbertChair, present
BC
Councillor Ben CoxVice-Chair, present
CC
Councillor Christina ColemanMember, present
JC
Councillor Jane ClarkMember, present
NC
Councillor Neil CleaverMember, present
ME
Councillor Martyn EverittMember, present
CP
Councillor Chris PrimettMember, present
SS
Councillor Stephen ShingMember, present
DW
Councillor David WhiteMember, present
AW
Councillor Alison WilsonMember, present
GW
Councillor Glynn WhiteMember, present
AW
Councillor Andrew WilsonMember, present

All 21 on the meeting page

On this subject at Wealden

Search all
  1. Internal Audit Progress Report - April to August 2026This decision
  2. Internal Audit Progress - September to December 2025Decided
  3. Internal Audit Progress Report- April to August 2025Noted
  4. Annual Report on Internal Audit ActivityNoted
  5. Report of the Internal & Audit and Community & Environment Scrutiny Committees - Work ProgrammesApproved

More from Wealden Audit and Governance Committee

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the meeting dated 22 July 2026RESOLVED – That the minutes of the meeting held on 22 July 2026 as circulated on the agenda be taken as read, confirm... Decided Open
16 Sep 2026 Farningham Project Review Scoping ProjectThat Councillors Everitt, Alison Wilson, Glynn White, Andrew Wilson and David White form the Farningham Project Revie... Agreed Open
16 Sep 2026 Risk Management Update Reporta) That the Risk Management Policy and Framework be approved; b) That the Corporate Risk Register and the actions bei... Approved Open
16 Sep 2026 Financial Management 2026/27 - Quarter 1 Forecast to Year Enda) That the General Fund Revenue Budget forecast surplus of (£0.031) million, a variance of £0.418 million against th... Noted Open
16 Sep 2026 2025/26 Statement of Accounts and External Audit Reporta) Acknowledged the comment on the draft 2025/26 statement of accounts and that the audit was underway but not yet co... Approved Open