Investment in outdoor community/ sports facilities at Brightling Road Leisure Ground, Polegate
ApprovedExecutive7 papers
AI summaryCabinet recommends allocating up to £1.2 million of retained Community Infrastructure Levy receipts to improve sports and community facilities at Brightling Road Leisure Ground in Polegate, subject to Full Council approval.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedAllocate up to £1.2m from retained CIL receipts
MoneyUp to £1.2m from retained CIL receipts. Total project estimated at £1,472,009.79
What happens nextSubject to Full Council approvalWorks scheduled December 2026 to August 2027
Who it affectsBrightling Road Leisure Ground, PolegateCommunity, leisure and sports facilities
What was decided
Cabinet welcomed exploration of community led projects that fall outside Sports Infrastructure Fund and Community Led Infrastructure Fund funding thresholds. Report P4
Cabinet approved the use and allocation of up to £1.2m from retained Community Infrastructure Levy receipts, subject to Full Council approval, and gave delegated authority to the Head of Planning Policy, Economy and Climate Change to conduct due diligence and enter into agreements. Report P6, P7
Cabinet recommended to Full Council that up to £1.2m be allocated to the Capital Programme from retained Community Infrastructure Levy receipts. Report P9
Why
Polegate has received significant housing growth, and the improvements would address a current deficit of community and sports facilities, supporting health, wellbeing and access to outdoor recreation. Report P2, P16, P17
The investment supports the Council Strategy priorities on Community Resilience and Wellbeing, Climate Change and the Environment, and the Health and Wellbeing Strategy adopted in June 2026. Report P10, P11, P12, P13, P14, P15
Without the Council contribution, the proposed improvements are unlikely to be delivered in full and the site would remain underutilised. Report P17
What happens next
Full Council will be asked to approve the allocation of up to £1.2m to the Capital Programme from retained Community Infrastructure Levy receipts. Report P9
If approved, the Council will enter into a Grant Funding Agreement with Polegate Town Council setting out eligible expenditure, grant release conditions, maintenance requirements and clawback provisions. Report P41, P52
The Head of Planning Policy, Economy and Climate Change, in consultation with the Chief Financial Officer, will conduct due diligence and finalise agreements; the majority of works are scheduled between December 2026 and August 2027. Report P7, P42
The money
£1,472,009.79 Total estimated project cost including preliminaries and a 6.25% contingency Report P39
£1.2m Up to this amount sought from the Council's retained Community Infrastructure Levy receipts Report P6, P9, P39
£295,000 Match funding confirmed by Polegate Town Council Report P39
£1.5 million Polegate Town Council proposed redevelopment scheme value (overview figure) Report P19
£750,001 Threshold above which Full Council approval is required for new capital budget under Financial Procedure Rules Report P51
Options considered
Chosen: Support the project and provide the full funding amount requested. Delivers a significant upgrade, addresses local demand, supports a growing population, and provides best value for money when delivered in full Report P43, P44
Rejected: Support the project but provide less funding than requested. Some elements would not be delivered, and the main benefits and best value for money are only realised once the full project is completed Report P43
Rejected: Do not support the project. Would leave the demand for community and sports facilities unmet Report P43
Implications
Financial: Approval would allocate a proportion of retained CIL receipts to the Community Led Infrastructure Fund, reducing the level of CIL funding available to support other infrastructure projects across the district, and will be monitored through CIL governance arrangements. Report P47
Legal: The Council is empowered to enter into funding agreements under Section 1 of the Localism Act 2011, with CIL applied under Section 216(2) of the Planning Act 2008 and Regulation 59 of the Community Infrastructure Levy Regulations 2010; due regard will be given to the UK Subsidy Control regime under the Subsidy Control Act 2022, and clawback provisions will be included in any advance funding. Report P48, P49, P50, P51, P52
Equalities: Improvements are consistent with the Public Sector Equality Duty, with widened paths, accessible play provision, improved seating, lighting, parking and safer site layout; a Grant Funding Agreement could require an Equality Impact Assessment to be prepared, maintained and reviewed. Report P64, P65
Climate: The scheme delivers climate benefits through improved drainage, sustainable drainage measures, landscaping, tree planting including fruit trees and hedgerows, and energy efficient or solar powered lighting, while bringing unused pitches back into active use. Report P54, P55, P57
Risk: Timescales are subject to weather and the putting in place of funding release schedules; without the Council contribution, the improvements are unlikely to be delivered in full and the site would remain underutilised. Report P17, P42
Other: Local Government Reorganisation is not expected to alter the strategic case for investment, and delivering the project now would secure long term community infrastructure before any future transfer or reconfiguration of local authority functions. Report P78
Who and where
Polegate Town Council (as site owner, manager and accountable body for delivery) Report P19, P40
Residents of Polegate and the surrounding area, including children, families and older residents Report P2, P16, P68, P70
Existing and new local sports clubs, including football, BMX, skate, tennis and basketball users Report P2, P9, P19
Visitors and users of existing site features such as the mini railway Report P31
Council staff in Planning Policy, Economy and Climate Change, Legal, Finance, Climate Change Projects, Inclusion and Diversity, and Leisure and Wellbeing Report P47, P53, P58, P60, P63, P65, P77
Timeline
23 April 2026: Community Wellbeing and Safety considerations provided by Senior Leisure and Wellbeing Officer Report P77
27 May 2026: Legal considerations and Climate Change considerations provided Report P53, P58
June 2026: Council adopted the refreshed Health and Wellbeing Strategy Report P15, P18
16 July 2026: Local Government Reorganisation considerations reviewed Report P79
22 July 2026: Equalities considerations provided Report P65
29 July 2026: Environmental and Sustainability considerations provided Report P63
25 September 2026: Financial review by Chief Finance Officer Report P47
07 October 2026: Cabinet decision to recommend allocation to Full Council Report P1
December 2026 to August 2027: Majority of works scheduled for completion Report P42
March to Summer 2027: Final completion indicated, subject to weather and funding release schedules Report P42
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge that local authorities can apply to new development to fund infrastructure
SIF: Sports Infrastructure Fund, referenced as a funding programme threshold
CLIF: Community Led Infrastructure Fund, referenced as a funding programme threshold
GFA: Grant Funding Agreement, the contract to be put in place with Polegate Town Council
MUGA: Multi Use Games Area, a court used for multiple sports such as tennis and basketball
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
To welcome the exploration of community-led projects for new and/or improved community facilities that fall outside the threshold of the Sports Infrastructure Fund (SIF) and Community Led Infrastructure Fund (CLIF) funding programme thresholds; and 2. Subject to Full Council approval of the approved budget allocation set out in recommendation 3 below: a) To note the contents of this report, including the financial appraisal, and to approve the use and allocation of up to £1.2m from the Council’s retained Community Infrastructure Levy receipts to fund and support the delivery of improvements to the community, leisure and sport facilities at Brightling Road Leisure Ground, Polegate. b) To give delegated authority to the Head of Planning Policy, Economy & Climate Change, in consultation with the Chief Financial Officer: i. To conduct appropriate due diligence, including the obtaining of legal and financial advice where appropriate; ii. To negotiate, agree, finalise, approve and enter into any agreements and associated documents to support the delivery of the project and give effect to the above recommendations. To recommend to Full Council: 3. To approve an allocation of up to £1.2m to the Capital Programme from retained Community Infrastructure Levy receipts to fund and support the delivery of improvements to the community, leisure and sport facilities at Brightling Road Leisure Ground, Polegate.
Word for word from the decision Wealden published for this meeting.Source: council.wealden.gov.uk
Investment in outdoor community and sports facilities at Brightling Road Recreation Ground, Polegate Report To: Cabinet Date of decision: Wednesday, 07 October 2026 Portfolio: Public Health and Asset Management Access: Public document (not exempt from disclosure)
Executive Summary This report seeks approval for the Council to work in partnership with Polegate Town Council and allocate up to £1.2m from retained Community Infrastructure Levy receipts towards the improvement of Brightling Road Recreation Ground. The proposed investment would help deliver a coordinated package of community, leisure and sports facilities, supporting local health and wellbeing, improving access to outdoor recreation, and safeguarding long-term community use of the site. Council support for this project would provide a high-quality community facility and improve sports and recreational provision within the south of the district. It would benefit residents, existing and new sports clubs who currently are unable to play at this site, whilst helping to safeguard the long-term future of sports provision and outdoor facilities in Polegate and the surrounding area.
Recommendations The Portfolio Holder for Public Health and Asset Management recommends that Cabinet:
1. To welcome the exploration of community-led projects for new and/or improved community facilities that fall outside the threshold of the Sports Infrastructure Fund (SIF) and Community Led Infrastructure Fund (CLIF) funding programme thresholds; and
v25/02 2. Subject to Full Council approval of the approved budget allocation set out in recommendation 3 below:
a) To note the contents of this report, including the financial appraisal, and to approve the use and allocation of up to £1.2m from the Council’s retained Community Infrastructure Levy receipts to fund and support the delivery of improvements to the community, leisure and sport facilities at Brightling Road Leisure Ground, Polegate. b) To give delegated authority to the Head of Planning Policy, Economy & Climate Change, in consultation with the Chief Financial Officer:
i) To conduct appropriate due diligence, including the obtaining of legal and financial advice where appropriate; ii) To negotiate, agree, finalise, approve and enter into any agreements and associated documents to support the delivery of the project and give effect to the above recommendations.
That Cabinet Recommends to Full Council:
3. To approve an allocation of up to £1.2m to the Capital Programme from retained Community Infrastructure Levy receipts to fund and support the delivery of improvements to the community, leisure and sport facilities at Brightling Road Leisure Ground, Polegate.
Council Strategy The proposed enhancement project at Brightling Road Recreation Ground will support delivery of the following Council Strategy priorities:
Community Resilience & Wellbeing
CW1 Community resilience CW2 Infrastructure CW5 Leisure and Culture Services CW6 Equality, diversity and inclusion
Climate Change and the Environment
CE1 Tackle the Climate Emergency
Reasons for the recommendation The health and wellbeing of our residents is pivotal to supporting thriving communities. A partnership approach to the provision of enhanced and new sports facilities helps support community led provision, as well as contributing to the priorities of the Council Strategy, the Council’s refreshed Health and Wellbeing Strategy, adopted in June 2026 and priorities within the Council’s Playing Pitch and Outdoor Sports Strategy, adopted in April 2022.
Polegate and the surrounding area has received significant housing growth and development and the new and improved community and sports facilities being proposed at Brightling Road Recreation Ground will provide a wide range of health, wellbeing and social benefits for the growing population. It will also ensure residents have access to fit for purpose, high-quality, accessible, local facilities for years to come.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Allocation of Asylum Grant 2026/27a) To note the receipt of the Asylum Grant funding and the opportunity it presents to support partners and community ...
Wealden Local Plan (Regulation 19)To recommend to Full Council: a) The Proposed Submission Wealden Local Plan (Appendix 1) be approved for publication ...
Performance Report - Quarter 1 2025/26a) To celebrate our achievements and performance for the first quarter of 2026/27 and in particular our progress towa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.