AI summaryWealden Joint Waste and Recycling Committee noted the requested 2027/28 budget provision for the Biffa contract and asked that figures be passed to each council's Chief Finance Officer. A 6.6% inflation rise was recommended for 2026/27 budgeting.
What happens nextBudget implications to Chief Finance OfficersEach partner council to set 2027/28 budget
Who it affectsHastings, Rother and Wealden councilsJoint Waste Partnership members
What was decided
The Committee noted the requested budget provision for Joint Waste Contract costs in 2027/28. Report P3
The Committee ensured that budget implications would be fed back to each council's Chief Finance Officer. Report P3
Why
To keep Members up to date on finance and budget for the Waste Collection, Recycling and Street Cleansing contract and allow adequate budget setting for 2027/28. Report P4
Without adequate provision, each council could face an overspend in 2027/28. Report P4, P17
Inflation, updated property numbers and the introduction of food waste collections have raised the core contract sum by £2.3m across the Partnership. Report P6
What happens next
Each partner council should make provision for the contract cost in its 2027/28 budget, taking account of a full year of food waste and property growth. Report P10, P15
The administering authority will advise each council of its share of the 2027/28 administering budget once pay inflation is confirmed. Report P13
£550,106.52 HBC increase in core contract cost from 2025/26 to 2026/27 Report P9
£671,166.96 RDC increase in core contract cost from 2025/26 to 2026/27 Report P9
£1,150,579.08 WDC increase in core contract cost from 2025/26 to 2026/27 Report P9
£2,371,852.56 Total Partnership increase in core contract cost from 2025/26 to 2026/27 Report P9
£256,100.00 Administering authority budget set at the beginning of April 2026 Report P13
£18,100.00 Forecast underspend on the administering authority budget to year end Report P13
£62,260 Forecast administering authority spend for HBC Report P13
£86,870 Forecast administering authority spend for RDC Report P13
£86,870 Forecast administering authority spend for WDC Report P13
£17,103 Tetra Tech Local Environmental Quality Surveys cost for Rother in 2026/27 Report P14
£17,103 Tetra Tech Local Environmental Quality Surveys cost for Wealden in 2026/27 Report P14
£461k Partnership spend on containers in 2024/25 Report P12
£414k Partnership spend on containers in 2025/26 Report P12
£420k - £450k Estimated Partnership cost of containers in 2026/27 Report P12
6.6% Recommended inflationary increase for the 2026/27 contract budget forecast Report P15
Options considered
Chosen: Note the requested 2027/28 budget provision and feed implications to each council's Chief Finance Officer. To allow adequate budget setting and avoid an overspend in 2027/28 Report P3, P4, P18
Implications
Financial: Core contract cost across the Partnership has risen by £2.37m, driven by inflation, updated property numbers and food waste collections. Report P6, P9
Financial: An inflationary increase of 6.6% is recommended for 2026/27 contract budget forecasts. Report P15
Financial: The 2027/28 core budget must allow for a full year of food waste and property growth. Report P10
Financial: Recoverable item costs for containers are expected to stay at about £420k to £450k in 2026/27. Report P12
Financial: The administering authority budget is forecast to underspend by about £18,100 in 2026/27. Report P13
Risk: Each council risks an overspend in 2027/28 if it does not make adequate budget provision. Report P4, P17
Other: Food waste collections started during 2026, with nine months of costs included in the 2026/27 figures. Report P5, P10
Who and where
Hastings Borough Council (HBC) as a Joint Waste Partnership member Report P7, P8
Rother District Council (RDC) as a Joint Waste Partnership member Report P7, P8
Wealden District Council (WDC) as a Joint Waste Partnership member Report P7, P8
Biffa Municipal Ltd as the contract holder Report P5
Timeline
October 2025: Committee advised members to allow 3.3% inflation for 2026/27 contract spending. Report P5
Beginning of April 2026: Administering authority budget was set at £256,100.00. Report P13
Financial year 2027/28: Core budget must allow for a full year of food waste and property growth. Report P10
April to June 2026: Food waste inflation PR1 was 3.33%. Report P5
April to June 2026: End of original term inflation was 2.73%. Report P5
July 2026: Contract extension with Biffa Municipal Ltd began and food waste collections were introduced. Report P5
July 2026 to March 2027: Start of extension period inflation was 3.20%. Report P5
Plain English for the jargon
Core sum: The base partnership-wide contract cost covering scheduled collections, street cleansing (Rother and Wealden), national insurance, ABS pension and the Annual Cost Price Reduction capital element.
Non-core activities: Non-routine and on-demand services such as bulky waste collections and fly-tip clearances, which vary month to month.
Recoverable items: The capital cost of procuring containers and sacks for customers, tracked and reported quarterly.
Administering authority: The council that runs the joint waste partnership finances on behalf of the partners; budget covers running costs and is split between the three councils.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item852026
Resolved
a) To note the requested budget provision with regards to Joint Waste Contract cost, for the financial year 2027/28; and b) That the Joint Waste Partnership Manager ensure that the budget implications be fed back to each Councils’ respective Chief Finance Officer. a) Noted the requested budget provision with regards to Joint Waste Contract cost, for the financial year 2027/28; b) Ensured that the budget implications would be fed back to each Councils’ respective Chief Finance Officer.
Word for word from the decision Wealden published for this meeting.Source: council.wealden.gov.uk
Joint Waste Partnership Finance Report Report To: Joint Waste and Recycling Committee Date of decision: Friday, 09 October 2026 Access: Public document (not exempt from disclosure)
Purpose of the Report To update Members on the Biffa Contract and Joint Waste Partnership expenditure and provide inflation forecasting for 2027/28.
Recommendations Joint Waste and Recycling Committee is recommended to: a) Take note of the requested budget provision with regards to Joint Waste Contract cost, for the financial year 2027/28; and b) Ensure that the budget implications are fed back to each Councils’ respective Chief Finance Officer.
Reasons for the recommendation This report is required to keep Members of the Joint Waste and Recycling Committee abreast of finance and budget matters relating to the Waste Collection, Recycling and Street Cleansing Services contract and to allow for adequate budget setting for the financial year 2027/28. Failure to provide adequate budget provision in 2027/28 could leave each Council with an overspend.
Background 1. At the Joint Waste and Recycling Committee in October 2025, Members were advised to make a 3.3% allowance for inflation on 2025/26 in preparation for contract expenditure 2026/27. 2. Entering into the contract extension with Biffa Municipal Ltd in July 2026 together with introducing food waste collections, meant that the inflationary mechanism as per the updated Schedule 4 – Payment Mechanism, allowed for three different inflationary values to be calculated and applied to the bill rates for the periods April to June 2026 and July 2026 to March 2027. Meaning that the actual inflation applied was. a. Food Waste-PR1 for the period April to June 2026 was 3.33%. b. End of original term April to June 2026 was 2.73%. c. Beginning of extension period July 2026 to March 2027 was 3.20%.
Core 3. The Core sum in 2026/27 is made up of - a. routinely scheduled collections Partnership wide and street cleansing work in Rother and Wealden only, b. National insurance contribution, c. ABS Pension element and the d. Annual Cost Price Reduction for the capital element. 4. Inflation, together with the updated property numbers in line with each Councils’ council tax base (CTB1) and the introduction of food waste collections, has led to the core sum increasing by £2.3m across the Partnership. The increase per council is included in Table 1. 5. Table 1 – Summary of Core costs 2025/26 against 2026/27
6. Please note figures in Table 1 account for nine months of food waste costs. Core budget in 2027/28 will need to allow for a full year of food waste, calculated in line with property growth.
Non-Core 7. Non-Core activities include non-routine and “on demand” activities such as bulky waste collections and fly-tips. These costs therefore vary month on month and year on year. 8. Each authority monitors the quantity and cost of these services monthly through the invoicing process, and in addition to this, quarterly reports are provided by the Joint Waste team. Local finance and waste colleagues use this information to make adequate budget provision for each financial year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.