UPDATE ON PROGRESS WITH ARBITRATION CASES

Agreed Committee 2 papers

Estate Management Appeals Panel agreed this item on Thursday 28 July 2016. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That Members agree the closure of the 219 Knightsfield , Welwyn Garden City case and note the further cases to be presented to the next Panel meeting for consideration and those where arbitration should be sought .
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Estate Management Appeals Panel

Executive summary

1.1This report is to update Panel Members with regard to the arbitration cases that were put before the Panel on 15th June 2015.

1.2As you are aware, the recommendations that were put forward to the Panel in April 2015 were approved. For ease they are listed below:

1. With the exception of the case detailed at 7.3 below, that the Head of Planning be authorised to refer the cases for determination by an independent arbitrator in accordance with section 8 of the Management Scheme for Welwyn Garden City.

2. That Members authorise the Head of Planning to take no further action with regard to the case detailed at paragraph 7.3 below [15th June 2015 report].

3. That the Head of Planning be authorised to take such further action that may be required by the Panel on a case by case basis.

4. In the event of a failure to comply with any binding award made by an independent arbitrator, that the Head of Planning be authorised , at his discretion, to take legal action through the County or High Court to enforce the requirements of any arbitration award, if necessary.

1.3It was agreed that officers would write to the property owners informing them of the Panel’s decision and of the likely cost of arbitration. The letter would offer a final opportunity for the owners to comply with the Scheme’s requirements within a reasonable timescale, thereby removing the need to refer the case to arbitration.

1.4As stated in the report in April 2015, given the number of cases involved, officers further considered that it would be necessary to progress the authorised cases through the process in small batches, as resources permit.

1.5To date six of the letters have been sent to property owners informing them of the Panel’s decision and a brief update on each property can be found in section 7 below. The previous report that went to the Panel on 30th April 2015 has been appended to this report and where matters are identical; they have not been duplicated within this report.

Recommendation

2.1That Members agree the closure of 219 Knightsfield, note the contents of the report and for further cases to be presented to the next Panel meeting for Members consideration.

3 Individual Cases

3.1219 Knightsfield

Nature and date of breach: Formation of hardstanding in front garden, date unknown.

Details: A 100% block paving hardstanding has been formed in the front garden. Although it is not entirely clear when the work was completed, the request for investigation was received in May 2010.

UPDATE: Arbitration is not being considered for the adjacent property, 217 Knightsfield, due to the length of time that it has been in situ. However it is considered that the Council could be liable to costs should the owner of 219 Knightsfield be successful at arbitration as they have installed a similar amount of unauthorised hardstanding as 217 Knightsfield. No complaint by an “owner” or “lessee” within the Scheme has been received by the Council in respect of 217 Knightsfield Road.

Update: Recommend closure

Photograph:

217 Knightsfield 219 Knightsfield

3.2179 Parkway

Nature and date of breach: Brick pillars and steel gates erected adjacent to footway in 2011. Details: 1.7 metre high concrete capped pillars and black powder coated steel gates were erected at the site and were subsequently reduced in height in 2011 to comply with planning ‘permitted development’ regulations.

Update: Letter to be sent to owner in July 2016.

Photograph:

3.39 Coltsfoot

Nature and date of breach: Non-matching roof tiles used in construction of an approved extension to property; reported in March 2012.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2016.07.28_Item 10_Arbitration Cases: Appendix 1Appendix 2.8 MB Download
PDF
UPDATE ON PROGRESS WITH ARBITRATION CASESReport 2.7 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 6 attended
SJ
Councillor Sara JohnstonChairman, present
JB
Councillor Jon BeckermanCommittee Member, present
MB
Councillor Margaret BirlesonCommittee Member, present
AC
Councillor Alan ChestermanCommittee Member, apologies
MC
Councillor Malcolm CowanCommittee Member, present
FT
Councillor Fiona ThomsonCommittee Member, apologies

On this subject at Welwyn Hatfield

Search all
  1. UPDATE ON PROGRESS WITH ARBITRATION CASESThis decision
  2. Update on progress with arbitration casesApproved
  3. Update on progress with arbitration casesRefused
  4. Update on progress with arbitration casesNoted
  5. Update on progress with arbitration casesApproved
  6. Update on progress with arbitration casesAgreed

More from Welwyn Hatfield Estate Management Appeals Panel

All decisions
MeetingDecisionOutcome
18 Aug 2021 Exclusion of press and publicThat under Section 100(A )( 2) and (4) of the Local Government Act 1972, the press and public be now excluded from th... Decided Open
24 Mar 2021 Exclusion of press and publicThat under Section 100(A )( 2) and (4) of the Local Government Act 1972, the press and public be now excluded from th... Decided Open
27 Jan 2021 8 handside green, welwyn garden city, al8 6sq - 6/2020/1479/em - erection of a front porch(Unanimous) That Members uphold the delegated decision and dismiss the appeal. Decided Open
27 Jan 2021 9 handside green, welwyn garden city, al8 6sq - 6/2020/1480/em - erection of a front porch(Unanimous) That Members uphold the delegated decision and dismiss the appeal. Decided Open
27 Jan 2021 Any other business of a confidential or exempt nature at the discretion of the chairmanThat Members note the verbal report. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies