(1) That the report to Cabinet which agreed an eight week period of public consultation on alterative options for the future of the Welwyn Garden City Estate Management Scheme be noted. (2) That the consultation would take the form of a letter to all residents within the Scheme area, a slightly different letter to all other residents who lived in Welwyn Garden City but were not within the Scheme area and less targeted consultation via the Council’s website and other communication channels such as newspaper adverts to other residents and bodies which may have an interest in the Scheme. Agreement of the consultation letter(s) would be with Counsel to mitigate any later challenges be noted. (3) That it be noted that Cabinet would receive a future report which set out the responses to the public consultation and recommends a preferred way forward as a consequence of those responses.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1Cabinet considered a report on the Welwyn Garden City Estate Management Scheme in July 2015 (Appendix 1) which sought to resolve on-going problems with its administration and enforcement. The main thrust of the recommendations was to replace the Scheme with Article 4 Directions and to apply to the High Court Land Tribunal to vary or terminate the Scheme, and these were agreed by Cabinet.
1.2In the preceding months officers have successfully progressed some of the recommendations, notably discussions with appropriate organisations as to whether another body might be prepared to manage the Scheme (with no such interest being expressed given the acknowledged problems) and a town- wide review to establish the merits of removing certain permitted development rights as part of an Article 4 Direction. Unfortunately progress was slowed by the resignation and replacement of the lead planning officer.
1.3In recognition of the fact that a sound case would need to be presented to the High Court if the Council was ultimately minded to vary or terminate the Scheme, officers sought legal advice on the merits of the intended way forward. That advice is set out in detail below but in summary it was that an Article 4 Direction would need to provide at least equivalent protection as the existing Scheme and that issues that cannot be satisfactorily covered by an Article 4 Direction should be retained as part of the Scheme. In addition, the Council should publicly consult on this and alternative options and analyse any responses before proceeding. This is in response to a growing area of case law concerning consultation by local authorities, and the risks of challenge if it is not done from an objective start point.
Recommendations
2.1That Cabinet agrees an 8 week period of public consultation on alterative options for the future of the Welwyn Garden City Estate Management Scheme. This will take the form of a letter to all residents within the Scheme area, a slightly different letter to all other residents who live in Welwyn Garden City but are not within the Scheme area and less targeted consultation via the Council’s website and other communication channels such as newspaper adverts to other residents and bodies who may have an interest in the Scheme. Agreement of the consultation letter(s) will be with Counsel to mitigate any later challenges. 2.2 That Cabinet receives a future report which sets out the responses to the public consultation and recommends a preferred way forward as a consequence of those responses.
3 Explanation
3.1In recognition of the importance of the Welwyn Garden City environment and in order to protect the amenities and values of the area and residents, in 1973 the High Court imposed a Scheme of management under the Leasehold Reform Act 1967. This is known as the Estate Management Scheme.
3.2The aim of the administration of the Scheme is:
“for the purpose of maintaining and enhancing amenities and values in Welwyn Garden City with due regard to the convenience and welfare of persons residing, working and carrying on business there”
3.3The Scheme does not cover the whole of Welwyn Garden City and was agreed by the Secretary of State in January 1971 and approved by the High Court in 1973. The Scheme does not apply to commercial properties and, for the avoidance of doubt, only covers residential properties where the freehold has been purchased under the Leasehold Reform Act, and it is understood including Right to Buy (RTB) properties. This means that it does not apply to leasehold properties, Housing Trust properties or newly built properties. The effect of this is that properties of different tenure types are located next door to each other, each subject to different controls and enforcement procedures.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.