WOOD GREEN TIMBER COMPANY LTD, COOPERS LANE, NORTHAW, POTTERS BAR, EN6 4NE - WITHOUT PLANNING PERMISSION THE ERECTION OF A 7.2 METRE HIGH COVERED RACKING STRUCTURE
DecidedCommittee1 paper
Development Management Committee decided this item on Thursday 5 January 2017. Below is the council's own wording, with the papers it was decided on.
(unanimous) That the Head of Planning be authorised to issue and serve a planning enforcement notice under Section 172 of the Town and Country Planning Act 1990 requiring the recipient(s) to take the following steps, and to take any other further action, including prosecution proceedings if necessary, to rectify the breach of planning control subject to a compliance period of three months. Requirements (a) Demolish and completely remove the racking structure (b) Remove from the land, all materials and debris resulting from the demolition of the unauthorised racking structure and restore the land to its previous condition.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
Part I Item No 15 Executive Member: Councillor Perkins
WELWYN HATFIELD BOROUGH COUNCIL DEVELOPMENT MANAGEMENT COMMITTEE – 5 JANUARY 2017 REPORT OF THE DIRECTOR (GOVERNANCE)
Part I - Enforcement Item
WITHOUT PLANNING PERMISSION THE ERECTION OF A 7.2 METRE HIGH COVERED RACKING STRUCTURE.
WOOD GREEN TIMBER COMPANY LTD, COOPERS LANE, NORTHAW, POTTERS BAR, EN6 4NE
(Northaw and Cuffley)
1 Site Description
1.1The site is a timber yard; approximately 0.5 ha in size. It is located on the western side of Coopers Lane. The site has a long history of use as a timber yard; planning records would suggest that use has existed for over 40 years.
1.2The timber yard operated on a larger site totalling approximately 1.0 ha until earlier this year when part of the land was sold to the adjacent recycling centre operation.
1.3Vehicular access to the site is off Coopers Lane; accessed by an access road shared with the adjacent recycling centre operator.
1.4Although the surrounding area is predominately residential in nature, it is noted that the site is immediately adjacent to a number of other commercial operations.
2 Details of Investigation
2.1It was first reported to the Council 29th July 2016 that a storage structure had been erected on the site.
2.2A Planning Contravention Notice (PCN) was served on the owner of the site on 22nd August 2016. This was completed and returned to the Council on 7th September 2016. The PCN confirmed that the owners had not applied for planning permission prior to erecting the structure and had, instead relied upon the advice of the company that had sold the structure to them: ‘that planning permission was not required’.
3 Planning Constraints
3.1The site lies within the Green Belt and a Landscape Character Area as designated in the Welwyn Hatfield District Plan 2005.
4 Relevant Planning History 4.1 Application number: S6/1997/0415/FP
Proposal: Erection of a new building after demolition of existing building
Decision: Granted
Decision date: 04/07/1997
4.2Application number: S6/1995/0812/FP
Proposal: Single storey extension to office building to provide staff
Restroom, canteen and toilets.
Decision: Granted
Decision date: 19/12/1995
4.3Application number: S6/1981/0448/
Proposal: Sawmill and offices (details)
Decision: Granted
Decision date: 01/10/1981
4.4Application number: S6/1980/0659/
Proposal: Replacement offices, sawmill and new gatehouse (outline)
Decision: Granted
Decision date: 22/01/1981
4.5Application number: S6/1980/0359/
Proposal: Retention of portable building
Decision: Refused
Decision date: 04/09/1980
4.6Application number: S6/1979/0635/
Proposal: Incorporation of strip of land into timber yard for landscaping and tree planting
Decision: Granted
Decision date: 29/11/1979
4.7Application number: S6/1976/0636/
Proposal: Site for replacement offices, sawmill and new gatehouse
Decision: Granted Decision date: 08/09/1977
5 Planning Policy and Guidance
5.1National Planning Policy Framework (NPPF)
5.2Welwyn Hatfield District Plan 2005
5.3Welwyn Hatfield District Plan, Supplementary Design Guidance, February 2005
5.4Welwyn Hatfield Landscape Character Assessment 2005
6 Main Issues
6.1The main planning issues with this case are:
i) Whether the development is appropriate development within the Metropolitan Green Belt and whether the proposal would have an impact on the character and openness of the Green Belt (Section 9 of the NPPF 2012); ii) Whether there are any very special circumstances to outweigh any harm to the Green Belt; iii) Impact on the character and context of the Landscape Character Area (Policy RA10); iv) Whether planning permission is required for the development. v) Whether the development is immune from enforcement action by reason of time. vi) Other matters
7 Analysis
i) Whether the development is appropriate development within the Metropolitan Green Belt and whether the proposal would have an impact on the character and openness of the Green
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
WOOD GREEN TIMBER COMPANY LTD, COOPERS LANE, NORTHAW, POTTERS BAR, EN6 4NE: WITHOUT PLANNING PERMISSION THE ERECTION OF A 7.2 METRE HIGH COVERED RACKING STRUCTUREReport
119WOOD GREEN TIMBER COMPANY LTD, COOPERS LANE, NORTHAW, POTTERS BAR, EN6 4NE - WITHOUT PLANNING PERMISSION THE ERECTION OF A 7.2 METRE HIGH COVERED RACKING STRUCTUREThis decision
Follow Development Management Committee at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.