Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 10 January 2017. Below is the council's own wording, with the papers it was decided on.

Item111a

Resolved

(1) That the Council be recommended to agree that urgent repairs are required to the tower at Campus West and to agree a budget of £60,000 in this financial year 2016/17 to cover the estimated cost of the repairs required to the building. (2) That initially the cost be funded from the Emergency Reserve using the urgent incident procedure.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1In August this year, a large piece of concrete separated and then fell from the around a window on the fourth floor of the Campus West Tower. This highlighted there could be a problem with the window reveals and other isolated areas on the tower.

1.2Officers immediately fenced off the area and scaffolding was erected to allow for the tower to be inspected. Ashton Consulting were instructed to carry out that inspection and to produce a report to ascertain if the incident was likely to be a one-off or if there was a more widespread risk.

1.3This report advised that the risk did affect more of the building and also recommended that testing should be carried out for chlorides in the concrete.

1.4The purpose of this report is now to advise Members that urgent repairs are required to the tower to restore the external finishes to a safe state. Because these works are repairs, the cost cannot be treated as a capital expenditure and so the estimated requirement is for a one off revenue budget of £60,000 including fees

2 Recommendation(s)

2.1That Cabinet recommend to Council that it agrees that the urgent repairs outlined in this report are required and recommends to Council to agree a budget of £60,000 in this financial year 2016-17 to cover the estimated cost of the repairs required to the building.

2.2That initially the cost is funded from the Emergency reserve using the Urgent Incident Procedure.

3 Explanation

3.1During the refurbishment of the library by Hertfordshire County Council about 4 years ago, they encountered a problem with the finishes to a number of the window reveals where facing bricks (brick slips) were separating from the window lintels. This was happening because moisture had been able to penetrate the concrete behind the slips which had led to surface “spalling”.

3.2Spalling is the process where water penetrates a building material. This then may freeze due to the time of year. Ice occupies a larger volume than water which has the effect of pushing the material’s surface away allowing sections to fall. This regularly affects bricks at the foot of walls but can affect any hard material where moisture penetration can or has occurred. 3.3 The tower is subject to high temperature fluctuations and wind all of which, it now appears, has, over time, allowed moisture to penetrate the construction material. This has led to spalling occurring.

3.4Areas of the finishes to the tower have now shown signs of deterioration culminating in a section separating and falling.

3.5It is now essential that repairs are carried out to make the tower safer.

3.6These works are for remediation purposes only. They will not enhance the building nor extend its life.

Implications

4 Legal Implication(s)

4.1The forecourt area beneath the tower forms part of the fire and other evacuation routes for the Campus West complex. This route has to be as safe as reasonably possible. Now the Council is aware that this issue exists, it cannot not take action.

5 Financial Implication(s)

5.1The Council does have responsive and planned maintenance budgets but these budgets are already under significant pressure and cannot carry an additional level of expenditure of this nature.

5.2The Council is still incurring on-going costs for the scaffold hire. This was originally sourced through the minor works contract as the quickest way to ensure the area around the building was protected.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Campus West TowerReport 113 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 13 attended
JD
Councillor John DeanLeader, present
DB
Councillor Duncan BellCommittee Member, present
HB
Councillor Helen BromleyCommittee Member, present
TK
Councillor Tony KingsburyCommittee Member, present
MP
Councillor Mandy PerkinsDeputy Leader, apologies
BS
Councillor Bernard SarsonCommittee Member, present
RT
Councillor Roger TriggCommittee Member, present
MS
Michel SamindenOfficer, present
NL
Nick LongOfficer, present
KN
Ka NgOfficer, present
MM
Margaret MartinusOfficer, present
RB
Richard BakerOfficer, present

All 13 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. Campus West TowerThis decision
  2. Introduction of Parking Restrictions in Campus West Car Park, Welwyn Garden CityAgreed
  3. Award of Contract for Campus West Water Drainage ImprovementsDecided
  4. Cashless option for campus westAgreed
  5. Procurement of campus west water drainage improvementsDecided
  6. Campus west business recovery plans 2021Agreed

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies