FOOTBRIDGE, HYDEWAY, WELWYN GARDEN CITY - 6/2016/0457/FULL - IMPROVEMENTS TO FOOTBRIDGE TO INCLUDE A NEW FLOOR FINISH, LIGHTING AND THE RESTORATION OF THE EXISTING LATTICE STEEL STRUCTURE

Approved Committee 1 paper

Development Management Committee approved this item on Thursday 30 March 2017. Below is the council's own wording, with the papers it was decided on.

Item150

Resolved

(unanimous) That planning permission be approved for application 6/2016/0457/FULL as set out in the report of Officers.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Development Management Committee

Background

1.1This application was submitted in April 2016 but the determination has been delayed in order that it can be considered in conjunction with the substantive planning and listed building consent applications on the adjacent site.

2 Site Description

2.1The application site is the existing pedestrian footbridge which runs from the end of Hydeway over the east coast mainline to the Howard Centre shopping centre and provides access to the platforms of Welwyn Garden City railway station.

3 The Proposal

3.1The application proposes improvements to the railway bridge to include the upgrading of the floor surface to a resin bonded finish, the repainting of the lattice steel structure and the provision of pedestrian level lighting on the bridge. Precise details of all of these features would need to be agreed with Network Rail before works could commence.

4 Reason for Committee Consideration

4.1This application is presented to the Development Management Committee because it is linked to the major planning application at the adjacent site for the redevelopment of the former Shredded Wheat factory. 5 Relevant Planning History

5.1There is no planning history directly associated with the footbridge.

5.2Planning application N6/2015/0294/PP and listed building consent application N6/2015/0293/LB are both of relevance and related to the adjacent site of the former Shredded Wheat factory and a planning application to redevelop that site for mixed use to provide up to 850 residential units, office, retail and commercial uses as well as open space and other matters.

6 Planning Policy

6.1National Planning Policy Framework – Chapters 4 and 7

6.2Welwyn Hatfield District Plan 2005

6.3Broadwater Road West Supplementary Planning Document 2008

7 Site Designation

7.1The site lies within Welwyn Garden City as designated in the Welwyn Hatfield District Plan 2005.

8 Representations Received

8.1The application was advertised by means of a site notice. 1 representation has been received from the occupier of 83 Gresley Close as well as Welwyn Hatfield Access Group. Their comments may be summarised as:

 The proposal is a great step forward, the sooner the better.  Welwyn Hatfield Access Group has made comments which are related to the linked major planning application rather than specifically to this application for works to the railway bridge.

9 Consultations Received

9.1The following have responded advising that they have no objections to the proposal:

9.2Hertfordshire County Council Transport Programmes and Strategy – Support the proposals.

9.3Network Rail – Support the proposals in principle, subject to a number of conditions. Note ongoing dialogue with the applicant.

10 Analysis

10.1The main planning issues to be considered in the determination of this application are:

1. Features high quality design which incorporates the design principles of the plan and Supplementary Design Guidance (GBSP1, GBSP2, D1) and that the proposal respects and relates to the character and context of the area, as a minimum maintaining and where possible enhancing or improving the character of the existing area (D2)

10.2The proposal represents a long sought after improvement to the existing pedestrian footbridge from the east side of the town to the railway station and the town centre beyond. In that sense it seems clear that the proposal should be supported.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FOOTBRIDGE, HYDEWAY, WELWYN GARDEN CITY: 6/2016/0457/FULL: IMPROVEMENTS TO FOOTBRIDGE TO INCLUDE A NEW FLOOR FINISH, LIGHTING AND THE RESTORATION OF THE EXISTING LATTICE STEEL STRUCTUREReport 584 KB DownloadRead as text

At this meeting

Whole meeting
148FORMER SHREDDED WHEAT FACTORY, BRIDGE ROAD, WELWYN GARDEN CITY, AL8 6UN - N6/2015/0294/PP - OUTLINE PLANNING PERMISSION FOR PART DEMOLITION, REPAIR, RESTORATION, EXTENSION AND CONVERSION OF THE FORMER SHREDDED WHEAT FACTORY COMPLEX TO INCLUOn the agenda 149FORMER SHREDDED WHEAT FACTORY, BRIDGE ROAD, WELWYN GARDEN CITY, AL8 6UN - N6/2015/0293/LB - PART DEMOLITION, REPAIR, RESTORATION, EXTENSION AND CONVERSION OF THE FORMER SHREDDED WHEAT FACTORY COMPLEX TO INCLUDE DEMOLITION OF ALL BUILDINGS AApproved
150FOOTBRIDGE, HYDEWAY, WELWYN GARDEN CITY - 6/2016/0457/FULL - IMPROVEMENTS TO FOOTBRIDGE TO INCLUDE A NEW FLOOR FINISH, LIGHTING AND THE RESTORATION OF THE EXISTING LATTICE STEEL STRUCTUREThis decision
15145 NORTHAW ROAD EAST, CUFFLEY, POTTERS BAR, EN6 4LU - 6/2016/1855/VAR - VARIATION OF CONDITION 2 (OBSCURED GLAZED DORMER WINDOWS) ON PLANNING PERMISSION 6/2016/0391/VAR FOR THE VARIATION OF CONDITION 1 (APPROVED PLANS) ON PLANNING PERMISSIOOn the agenda 152THE CEMETERY HOUSE, SOUTH WAY, HATFIELD AL10 8HS - 6/2016/2623/MAJ - ERECTION OF A NEW CHAPEL, MACHINERY STORE AND CREMATORY, TO INCLUDE NEW CAR PARKING PROVISION AND ENHANCED LANDSCAPING FOLLOWING DEMOLITION OF EXISTING CHAPEL, MACHINERY STORE, LODGE HOUSE AND CENTRAL COLONNADEApproved 15340 BURROWFIELD, WELWYN GARDEN CITY, AL7 4SR - 6/2016/1848/FULL - CHANGE OF USE TO ENERGY GENERATION AND INSTALLATION AND OPERATION OF THREE GAS ENGINES AND ANCILLARY DEVELOPMENTOn the agenda 154APPEAL DECISIONSNoted 155PLANNING UPDATE - FUTURE PLANNING APPLICATIONSNoted

Who was there

15 of 24 attended
SB
Councillor Stephen BoultonChairman, present
NP
Councillor Nick PaceVice-Chairman, present
RB
Councillor Rachel BaschCommittee Member, present
DB
Councillor Darren BennettCommittee Member, present
MB
Councillor Margaret BirlesonCommittee Member, present
AC
Councillor Alan ChestermanCommittee Member, present
ID
Councillor Irene DeanCommittee Member, present
CG
Councillor Caroline GillettCommittee Member, present
ML
Councillor Mike LarkinsCommittee Member, present
SM
Councillor Steven MarkiewiczCommittee Member, present
HM
Councillor Howard MorganCommittee Member, present
PS
Councillor Pankit ShahCommittee Member, present

All 24 on the meeting page

More from Welwyn Hatfield Development Management Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 6/2025/2484/FULL - 109 Woods Avenue, Hatfield, AL10 8QQ(for 11, against 0, abstain 0) That planning permission be granted, subject to the conditions set out in the report. Decided Open
25 Jun 2026 Appeal Decisions 2 March 2026 to 12 June 2026 ReportResolved – the Committee noted the report. Noted Open
25 Jun 2026 Future Planning ApplicationsResolved – the Committee noted the report. Noted Open
12 Mar 2026 Appeal Decisions 2 February 2026 to 2 March 2026 ReportRESOLVED It was resolved to note the contents of the report. Noted Open
12 Mar 2026 Future Planning ApplicationsRESOLVED To note the contents of the report. Noted Open