Cabinet, Tuesday 6 March 2018 at 7.30pm

Transfer of Building Control Functions to Three Rivers District Council

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 6 March 2018. Below is the council's own wording, with the papers it was decided on.

Item106a

Resolved

(1) That the Council’s statutory building control functions (as set out in Appendix A to the report) be transferred to Three Rivers District Council so that it could carry out the duties and responsibilities of LA1 as described in the report on behalf of Welwyn Hatfield Borough Council. (2) That the Executive Director (Public Protection, Planning and Governance) be given delegated authority to authorise the Services Agreement and Inter-Authority Agreement referred to in the report using the power in Section 5(2)(a) of the Local Authorities (Arrangements for Discharge of Functions) (England) Regulations 2012 to transfer the functions listed in Appendix A to the report to Three Rivers District Council. (3) That the Head of Public Health and Protection be appointed as the Council’s “Commissioning Panel Representative” as part of the Commissioning Panel established in accordance with the Services Agreement and Inter-Authority Agreement. (4) That delegated authority be given to the Head of Public Health and Protection, in consultation with the Executive Director (Public Protection, Planning and Governance), to appoint a “Deputy Commissioning Panel Representative” to attend the Commissioning Panel in the event of the Panel representative’s absence. (5) That the Council be recommended to give delegated authority to the Head of Public Health and Protection, in consultation with the Executive Director (Resources, Environment and Cultural Services) as the Council’s Section 151 Officer and Executive Member (Resources), to negotiate and agree fees for both statutory and non-statutory building control activities, in negotiation with other members of the Commissioning Panel, Three Rivers District Council acting as LA1 and Hertfordshire Building Control Ltd. (6) That consideration be given to any consequential revisions to be made to the Council’s Constitution and schemes of delegation with recommendations made to the Council for adoption of these revisions. (2) Reasons for the Decision In July 2015 the Cabinet received a report setting out the challenges facing building control and it was agreed that the Council should explore the principle of transferring functions into a Hertfordshire joint arrangement. In August 2016 the Cabinet received a report setting out the business case and financial, legal and risk implications of a joint service. It agreed to form a holding company and two subsidiary companies and to transfer delegable building control functions to these companies. It also confirmed that non-delegable functions would be transferred to one of the authorities in the joint service. As a result the companies were formed and staff from the seven participating authorities including this Council were TUPE transferred into them in August 2016. It was now confirmed that Three Rivers District Council would be the company LA1 to whom non-delegable functions would be transferred. Contrary to the original proposal, it had been decided that LA1 would not employ a qualified building surveyor to make decisions, but would ... view the full minutes text for item 106a
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report updates members on the further work undertaken in connection with the joint building control outsourcing project (“the project”) and asks Cabinet to consider and agree the next steps which need to be taken in order to finalise the project.

Recommendations

2.1For the Cabinet to note the work to-date, and to consider the proposals set out in this report, and subject to Cabinet consideration, to agree:

a) To transfer the Council’s statutory building control functions (as set out in Appendix A) to Three Rivers District Council so that they can carry out the duties and responsibilities of LA1 as described in this report, on behalf of Welwyn Hatfield Borough Council.

b) That the Executive Director (Public Protection, Planning and Governance) be given delegated authority to authorise the Services Agreement and Inter- Authority Agreement referred to in this report using the power in Section 5(2)(a) of the Local Authorities (Arrangements for Discharge of Functions) (England) Regulations 2012 to transfer the functions listed in Appendix A to Three Rivers District Council.

c) That the Head of Public Health and Protection is appointed as the Council’s “Commissioning Panel Representative” as part of the Commissioning Panel established in accordance with the Services Agreement and Inter-Authority Agreement.

d) That delegated authority is given to the Head of Public Health and Protection in consultation with the Executive Director (Public Protection, Planning and Governance) to appoint a “Deputy Commissioning Panel Representative” to attend the Commissioning Panel in the event of the Commissioning Panel Representative’s absence.

e) That the Head of Public Health and Protection, in consultation with the Executive Director (Resources, Environment and Cultural Services) as the Council’s Section 151 Officer and Executive Member for Resources to have delegated authority to negotiate and agree fees for both statutory and non- statutory building control activities, in negotiation with other members of the Commissioning Panel, Three Rivers District Council acting as LA1 and Hertfordshire Building Control Ltd.

f) That consideration is given to any consequential revisions to be made to the Council’s Constitution and schemes of delegation with recommendations made to Council for adoption of these revisions.

3 Explanation

3.1The purpose of building control is to ensure buildings and structures within the borough are built to safe standards and there are also particular enforcement powers available to deal with dangerous structures.

3.2The building control functions carried out by District and Borough Local Authorities may be divided into non delegable and delegable functions. Those functions which are non-delegable may only be carried out by a Local Authority, but a Local Authority may choose to ask a private sector entity to carry out delegable functions on its behalf. In the case of the non-delegable functions, it is however lawful for one Local Authority to transfer some or all of these powers to another Local Authority to exercise these functions.

3.3In July 2015, the Cabinet received an exempt report which set out the challenges facing the Council’s current building control team. These included private sector competition and the loss of market share to approved inspectors, an ageing staff profile, the lower efficiency and effectiveness of small teams and a lack of resilience due to recruitment and retention difficulties. Cabinet agreed that Welwyn Hatfield Council should explore the principle of transferring its building control services into a Hertfordshire joint arrangement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transfer of Building Control Functions to Three Rivers District CouncilReport 170 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
JD
Councillor John DeanLeader, present
MP
Councillor Mandy PerkinsDeputy Leader, present
DB
Councillor Duncan BellCommittee Member, present
HB
Councillor Helen BromleyCommittee Member, present
TK
Councillor Tony KingsburyCommittee Member, present
BS
Councillor Bernard SarsonCommittee Member, present
RT
Councillor Roger TriggCommittee Member, present
TM
Councillor Terry MitchinsonGuest, in attendance
RB
Rob BridgeOfficer, in attendance
KN
Ka NgOfficer, in attendance
NL
Nick LongOfficer, in attendance
MM
Margaret MartinusOfficer, in attendance

All 15 on the meeting page

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open