Resolved
(34 voting for and 10 against) That the Council approves the addition of £4.5M to the Capital Programme budget for the Tewin Road depot upgrade, specifically £1.2M in 2019/20 and £3.3M in 2020/21.
Council approved this item on Monday 25 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
(34 voting for and 10 against) That the Council approves the addition of £4.5M to the Capital Programme budget for the Tewin Road depot upgrade, specifically £1.2M in 2019/20 and £3.3M in 2020/21.
1.1The Council own a depot, located at Tewin Road. This site is leased to Serco, and it is used to operate the Streetscene services, including waste collection, street cleansing and grounds maintenance.
1.2The site is primarily used for the storage of vehicles and equipment, workshop to undertake vehicle and equipment maintenance and repair, offices for Serco management and administration, welfare facilities for crews and bin storage etc. In addition to this, some waste are bulked at the depot, such as trade waste, street sweepings, bulky waste and fly tipping.
1.3The site is about 1.9 hectare in size but the operations are currently spread over a large area, and it is recognised that these operations could be undertaken in a smaller area of the site. It should be noted that the depot has not received any major investment for over 20 years and is now outdated and is not fit for modern operational purpose.
1.4Therefore, the Council has taken an opportunity to review the design of the depot to maximise space and improve operations. This was discussed at the last Cross Party Streetscene Procurement Group and that it was agreed by Cabinet on 5th March to recommend to Council to add £4.5m to the capital programme for the upgrade of the Tewin Road depot.
1.5It should be noted that whilst this project sits outside the scope of the Streetscene procurement, all bidders have had the opportunity to discuss and provide comment on the proposed depot designs during dialogue.
2 Recommendation(s)
2.1That Council approve to add £4.5m to the Capital Programme budget for the Tewin Road depot upgrade, specifically £1.2m in 2019/20 and £3.3m in 2020/21.
3 Explanation
3.1The Tewin Road depot site is currently used for the Council’s ‘Streetscene’ contract which includes;
waste collection
street cleansing
grounds maintenance
-1- 3.2 The site comprises:
offices;
crew welfare facilities;
vehicle workshop;
grounds maintenance workshop and store;
staff and fleet parking (including a raised car park);
bin storage area;
tipping bays for waste;
fuel tanks;
vehicle wash; and
storage sheds.
3.3The site is located off Tewin Road in Welwyn Garden City, as outlined in orange in the picture below. The site is surrounded predominantly by commercial and industrial areas.
3.4The site is an old site and it is no longer fit for purpose. In particular, a number of old buildings no longer have power connection and the existing workshops on site are not large enough to accommodate the new size of waste collection vehicle, the central reservation needs to be removed and the whole site requires a new resurface.
-2- 3.5 It is proposed that £4.5m will be required to upgrade and create a depot that will be well suited and fit for purpose for streetscene services. The capital will cover costs of survey work, design, planning, permitting and construction (which will include the provision of a vehicle workshop, vehicle wash area, waste transfer station, office space with welfare facilities, container space, bin stores, staff and visitors parking).
3.6Hertfordshire County Council have been seeking to provide a significantly improved Household Waste and Recycling Centre (HWRC) to serve Welwyn Hatfield residents. This would replace the existing Cole Green HWRC. This site currently occupies a 0.18 hectare area and the projected population growth within the catchment area of the Cole Green site is expected to increase use of the centre to above capacity level during peak times. Officers from both County Council and Borough Council have jointly commissioned a feasibility study to explore the co-location of a HWRC and streetscene contractor depot. This was discussed at the last Cross Party Streetscene Procurement Group.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TEWIN ROAD DEPOTReport | 985 KB | DownloadRead as text |
Follow Council at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Community governance review for welwyn garden cityRESOLVED (Unanimously) Council resolved to approve: a) The second consultation document, frequently asked questions a... | Approved | Open |
| 16 Sep 2026 | Planning committees and the national scheme of delegation: constitutional updatesRESOLVED (FOR: 29, AGAINST: 0, ABSTAIN: 15) It was resolved that: a) Council notes and endorses the recommendations o... | Approved | Open |
| 16 Sep 2026 | Notices of motions under procedure rule 16(FOR: 29, AGAINST: 15, ABSTENTIONS:0) The amendment to the motion was approved. The motions as amended is set out bel... | Approved | Open |
| 15 Jul 2026 | Matters arising from the cabinetRESOLVED The Council agreed the Annual Report 2025/26 | Agreed | Open |
| 21 May 2026 | Election of MayorThat Councillor Michal Siewniak elected as Mayor of the Borough of Welwyn Hatfield for the municipal year 2026/27. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.