Local Plan - Objective Assessment of Need and Final Site Selection (Forward Plan Reference FP982)

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 19 November 2020. Below is the council's own wording, with the papers it was decided on.

Item197a

Resolved

That Cabinet agreed the recommendations from the meeting of the Cabinet Planning and Parking Panel on 17 November 2020:- (1) That the new objective assessment housing need (OAN) is 690 per year equivalent to 13,800 over the plan period of 2016-2036 based on the ten year projection identified. and RECOMMENDS TO COUNCIL: (2) That a strategy is put forward for 13,277 dwellings plus allocation of site PB1 for safeguarding.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Part I Item No: For Decision

WELWYN HATFIELD BOROUGH COUNCIL CABINET – 3 NOVEMBER 2020

Recommendation from the Cabinet Planning and Parking Panel on 17 November 2020:-

100. LOCAL PLAN - OBJECTIVE ASSESSMENT OF NEED AND FINAL SITE SELECTION

Members received a presentation from the Head of Planning. This set out what the Local Plan has to do and the legal requirements. The submitted version included provision for 12,000 homes, but the Inspector is concerned this does not meet the Objectively Assessed Need (OAN). In January, members received a report from officers that would deliver just under 16,000 in accordance with the OAN at that time. This was debated and Members ultimately selected additional sites totalling 14,011 homes for public consultation. Tonight’s report takes account of this consultation, the Inspector’s interim report and additional site information.

The consultation received around 770 comments. These were well split between agreeing or disputing legal compliance and soundness. Site PB1 received the most (88) representations.

The report records that 2121 completions have taken place, with 961 commitments (not the 1141 shown in the report) and an estimate of 1402 windfall. There are also some new assumptions on capacity on some sites.

The Inspector’s interim report says that the Council should align its housing and economic strategies. The Inspector’s OAN is 16,000 but he recognises that this may fall as a result of 2018-based household projections, though a substantially lower figure wouldn’t meet national policy. He proposes two possible courses of action; (i) to propose additional sites to try to meet the OAN; or (ii) withdraw the plan. A number of deadlines set out are contained in the report. If these are not met, he will determine that the Plan is unsound.

Recommendation 1: Determination of Objectively Assessed Need (OAN)

Members need to identify an appropriate precise figure including annual rate for the period 2016-2036. Usually this is one definitive figure but the ONS has published multiple projections. Best practice guidance does not specify how this should be addressed. The Head of Planning set out a number of projections and consequent figures:

i) Turley Associates Five Year Alternative Projection: 715 homes/year = 14,300 ii) ONS 10 Year Projection: 690 homes/year = 13,800 iii) ONS 2 year principal projection: 507 homes/year = 10,140

The current standard methodology = 875 homes/year. The proposed standard methodology (still in draft format and subject to consultation) = 667 homes/year Recommendation 2: Selection of Sites

Members consider whether to change the proposed 14,011 homes selected for consultation in January based on consultation responses, the Inspector’s interim report and new site information. This new figure of 13,277 homes does not include sites proposed for removal and assumes 2,000 at the Wheat Quarter and 250 at Biopark. It also removes 700 homes at Birchall Garden Suburb South and 160 at PB1 East of Potters Bar.

Whatever is decided at this meeting, the Head of Planning will write to the Inspector with an agreed OAN figure. Sites selected will be considered by Cabinet and then Full Council, and then those selected will be presented as a request to the Inspector as main modifications.

The Head of Planning set out a number of risks: Judicial challenge, the plan being declared unsound, the lack of a 5 Year Land Supply, continued difficulty in resisting applications on employment land and Green Belt, speculative applications, planning by appeal and costs, Government instructing another body to prepare a plan.

In respect of Recommendation 1, the Objectively Assessed Need (OAN), the panel raised and discussed the following points:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Plan: Objective Assessment of Need and Final Site Selection (Forward Plan Reference FP982)Forward_plan 198 KB DownloadRead as text

At this meeting

Whole meeting
197aLocal Plan - Objective Assessment of Need and Final Site Selection (Forward Plan Reference FP982)This decision
199CABINET DECISIONAgreed

Who was there

7 of 13 attended
TK
Councillor Tony KingsburyChairman, present
DB
Councillor Duncan BellVice-Chairman, present
SB
Councillor Stephen BoultonCommittee Member, present
TM
Councillor Terry MitchinsonCommittee Member, present
NP
Councillor Nick PaceCommittee Member, present
BS
Councillor Bernard SarsonCommittee Member, present
FT
Councillor Fiona ThomsonCommittee Member, present
KN
Ka NgOfficer, in attendance
NL
Nick LongOfficer, in attendance
SR
Simone RussellOfficer, in attendance
MM
Margaret MartinusOfficer, in attendance
AM
Alison MarstonOfficer, in attendance

All 13 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. Local Plan - Objective Assessment of Need and Final Site Selection (Forward Plan Reference FP982)This decision
  2. FP2143 Local Plan Regulation 18 consultationApproved
  3. Local plan review: vision and objectives to 2043Approved
  4. FP2147 Local Plan Call for Sites UpdateNoted
  5. Local Government Reorganisation - Interim Plans SubmissionAgreed
  6. FP2092 Local Plan Early Engagement Reporting and LDSAgreed

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open