(1) That the Bereavement services are delivered in accordance with section 3.2 of the report. (2) That delegated authority is given to the Chief Executive, in consultation with the Cemetery Procurement Board to award the contract for the main construction contractor.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
Part I Main author: Andrew Harper / Kirsten Roberts Executive Member: Cllr Stephen Boulton Welham Green and Hatfield South Wards
WELWYN HATFIELD BOROUGH COUNCIL CABINET – 15 JUNE 2021 REPORT OF THE CHIEF EXECUTIVE
BEREAVEMENT SERVICES CONTRACTS
1 Executive Summary 1.1 Following agreement of planning permission, the Cemetery Procurement Board has been overseeing the delivery of the future services. This report provides an update on the future delivery model for the Bereavement Service and the main construction contract.
2 Recommendation(s) 2.1 That the Bereavement services are delivered in accordance with section 3.2 of this report 2.2 That delegated authority is given to the Chief Executive, in consultation with the Cemetery Procurement Board to award the contract for the main construction contractor
3 Explanation – Cemetery Services 3.1 An options appraisal has taken place of all the services that will be required under the new Bereavement Services operation cemetery / crematorium operation and this is contained in Appendix 1. 3.2 If is recommended that the services are delivered in the following manner: 3.2.1 New Cemetery and Crematorium Management Contract (7 year contract with additional 2 years extension) Grounds Maintenance (mowing / hedge cutting) Grounds Maintenance – Horticulture Grave digging / ashes interment Emptying of all external litter bins To provide back-up cleaning To provide back-up cremator operator Note: As the crematorium is not due to be open until early 2023, there will need to be a staggered start to the contract 3.2.2 Services to be delivered by in house staff: Registrar ‘Front of House’ (e.g., preparation of the facility and first line daily cleaning) Cremator operation 3.2.3 Utilisation of existing contracts
-1- Daily clean – Corporate Cleaning Contract All other FM and compliance (e.g. Minor Building Works, Fire Risk Assessment. Legionella etc) Road Sweeping – Cleansing Contract Corporate Utility Contract Cremator Maintenance – new supplier / installer 4 Explanation – Main Contractor Procurement 4.1 The Procurement for a main contractor to undertake the construction of the new Bereavement Complex is now taking place and is being overseen by the Cemetery Procurement Board. 4.2 The Cemetery Procurement Board have agreed to shortlist to 5 contractors and the bids are due to be returned on 28h June 2021. 4.3 To provide a comprehensive service to residents there is a desire to get the Bereavement Centre operational as soon as possible. 4.4 By delegating the award of contract to the Chief Executive (in consultation with the Cemetery Procurement Board), approximately 4 weeks will be saved on the procurement process
Implications 5 Legal Implication(s) 5.1 None directly at this stage
6 Financial Implication(s)
6.1None directly at this stage
7 Risk Management Implications
7.1A thorough risk analysis will need to be developed as the services are rolled out, but the following risk has been identified at this stage:
7.2Business Continuity: This is a critical service and all aspects of the service need to be delivered effectively and with business continuity arrangements in place. Some of these are identified in the options appraisal (i.e. trained back up to operate the cremators), but other will need to be developed.
8 Security and Terrorism Implication(s)
8.1A risk assessment will need to be undertaken regarding the public spaces and if any special measures need to be put in place.
9 Procurement Implication(s)
9.1The proposed procurements will /are being undertaken in accordance with the Public Contracts Regulations 2015
10 Climate Change Implication(s)
10.1In accordance with the adopted procurement strategy – climate change will be evaluated as part of any tender process. -2- 11 Human Resources Implication(s)
11.1New staff will need to be employed if the recommendations are accepted and this strategy will be developed in accordance with corporate policies
12 Health and Wellbeing Implication(s)
12.1None at this stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.