Resolved
Unanimous to agree the officer’s recommendation, that Officers should drawdown funding from the Climate Change Reserve for increased contract costs until June 2022.
Climate Change Sub-Group agreed this item on Wednesday 22 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Unanimous to agree the officer’s recommendation, that Officers should drawdown funding from the Climate Change Reserve for increased contract costs until June 2022.
1.1This report seeks to consult the Members of the Climate Change Sub Group about using funds from the Climate Change Reserve to cover an increased to rental cost for our electric pool cars until contract expiry in June 2022.
1.2A separate report will be made regarding the future options for the contract after June 2022.
2 Recommendation(s)
2.1That the Climate Change Sub Group agree that Officers should drawdown funding from the Climate Change Reserve for increased contract costs until June 2022.
3.0Explanation
3.1The contract for an electric car club scheme for staff commenced in June 2017 for an initial period of two years, with an option to extend for a further three years, until June 2022. The contract was let through a mini-competition using a Crown Commercial Services call off contract.
3.2As the contract was initially for a two-year period, the cars we received were a few months old at the outset of the contract. As such, they came to the end of the lease in May 2021. Ubeeqo (formerly ECar Club) therefore had to replace the vehicles from June 2021. The initial option was for new vehicles at an increase of £400 per month, which was considered too expensive.
3.3The Procurement Manager was consulted and advised that maintaining the contract until its end (June 2022) would be the preferred approach in order to avoid any expensive contractual remedies. Additionally there were reputational issues to be considered in that the electric pool cars are a demonstration of action to reduce the council’s carbon footprint in the face of the declared climate emergency. While the cars have been used much less during the pandemic, with public use suspended until May 2021, usage has been growing and enquiries have been received from public users asking when the public use would be reintroduced.
3.4The Risk and Resilience Manager and Procurement Manager subsequently met with the Ubeeqo Account Manager. Both parties clearly had the same overall objective of keeping the scheme functioning until the end of contract in June 2022. As electric vehicle technology has improved, this has led to increases in
Classification: Unrestricted -1- Classification: Unrestricted
vehicle pricing. Remaining at the previous price was therefore not an option, as Ubeeqo stated that the contract would no longer be viable, neither could they justify a standalone publicly available operation. Ubeeqo were able to supply two vehicles from another contract that were newer than the ones we had at a cost of £200 extra per month until the end of contract. Following consultation with the Corporate Director, this offer was accepted. Comments were also sought from the Head of Resources.
3.5As the increase exceeds the current budget, agreement is sought to draw down budget from the Climate Change Reserve to meet this amount. This works out at £2000 in 2021/22, and £600 in 2022/23.
Implications
Legal Implication(s)
2.2Contract Procedure Rules have been applied and the Procurement Manager involved.
3 Financial Implication(s)
3.1The overall net financial effect is £2600 met from existing budgets, but requires draw down from the Climate Change Reserve (£2,000 in 2021/22, and £600 in 2022/23). The Finance Team have checked and confirmed these figures.
4 Risk Management Implications
4.1The risks highlighted in reaching this approach were:
Not proceeding would have lost the scheme, which has proved popular with employees and the public;
Any attempt to invoke contractual remedies could have lost the scheme, or resulted in officer costs exceeding the amount of the increase and causing a delay;
Reputational damage by terminating the scheme in the face of a declared climate change emergency;
An increase in the council’s carbon footprint.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
USE OF CLIMATE CHANGE FUNDING FOR UBEEQO VEHICLESReport | 235 KB | DownloadRead as text |
Follow Climate Change Sub-Group at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Sep 2023 | Update report on climate change(1) That the update be noted. | Noted | Open |
| 12 Jul 2023 | Hertfordshire climate change and sustainability partnership (hccsp)Members noted the update from the Executive Member. | Noted | Open |
| 8 Mar 2023 | General update on climate change( unanimous ) That the update be noted. | Noted | Open |
| 8 Mar 2023 | Hertfordshire climate change and sustainability partnership (hccsp)( unanimous ) Members noted the update from the Service Director. | Noted | Open |
| 18 Jan 2023 | General update on climate change( unanimous ) That the update be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.