CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Welwyn Hatfield Borough Council
Cabinet, Tuesday 5 September 2023 at 6.30pm

Supply of Kitchens (Forward Plan Reference FP1187)

Decided Executive 1 paper

Cabinet decided this item on Tuesday 5 September 2023. Below is the council's own wording, with the papers it was decided on.

Item136

Resolved

The Cabinet received the report on the supply of kitchens. DECISION TAKEN
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1Kitchen replacements are part of the Housing Capital Investment Programme.

1.2This report explains the process of appointing a supplier of kitchens for the programme.

2 Recommendation(s)

2.1That the Council enter into a Framework agreement with Howden Joinery Limited for a period of 5 years for the supply of kitchens.

3 Explanation

3.1Kitchen installation in council properties is part of the planned maintenance programme.

3.2A contractor (delivery partner) will install the kitchens and the Council nominates a supplier of these kitchens (cupboards, worksurfaces, sink etc).

3.3It will be mandatory for any delivery partners installing kitchens in our housing stock to use this framework.

3.4This is to ensure that there is consistency of supply, making maintenance easier in future years.

3.5The previous supplier has pulled out of the social housing market, meaning that a new supplier needed to be found.

3.6A tender process has been undertaken calling for a moisture resistant chipboard and delivery direct to properties.

3.7This is an increase in the specification. Previously the chipboard was to a specification known as P2 (Chipboard is ideally suited for use as interior fitments and furniture in dry conditions where exposure to moisture is limited). This has been increased to P3 (Moisture resistant chipboard panels) which will extend the lifespan of the kitchens.

3.8Only one bid was received from Howden Joinery Limited. This bid was evaluated and met all the minimum requirements. Implications

Legal Implication(s)

3.9The recommendations within this report are in accordance with the Public Contracts Regulations 2015.

3.10The Council will hold a framework contract with the successful supplier and any of the council delivery partners will have call off contracts with the successful supplier

4 Financial Implication(s)

4.1The delivery partner will pay the successful supplier directly for the kitchens.

4.2The cost of the kitchen will be included in the cost charged by the delivery partner to the council for the installation of the kitchen.

4.3A cost comparison has been undertaken and the rates quoted by Howdens are similar to the current market rates.

5 Risk Management Implications

5.1The risk of material availability will be reduced by entering into a call off contract.

5.2Subject to standard termination rights, Howdens will be required to provide kitchens for the duration of the capital works contract (approximately 5 years).

6 Security and Terrorism Implication(s)

6.1There are not considered to be any additional Security and Terrorism implications as a result of this recommendation.

7 Procurement Implication(s)

7.1See legal implications.

8 Climate Change Implication(s)

8.1Howdens have provided a number of climate change initiatives in their bid, including:

 The factories have achieved carbon net zero.

 Zero waste to landfill from the manufacturing operations.

 Improved quality control procedures to ensure no returns.

 All wood is from responsibly managed forests.

 A number of products from recycled stock

 Removing all non recyclable packaging

9 Human Resources Implication(s) 9.1 There are not considered to be any additional Human Resources implications as a result of this recommendation.

10 Health and Wellbeing Implication(s)

10.1There are not considered to be any additional Health and Wellbeing Implications as a result of this recommendation.

11 Communication and Engagement Implication(s)

11.1There are not considered to be any additional Security and Terrorism implications as a result of this recommendation.

12 Link to Corporate Priorities

12.1The subject of this report is linked to the Council’s Corporate Priority ‘Quality Homes through managed growth’.

13 Equality and Diversity

13.1An EqIA was not completed because this report does not propose changes to existing service-related policies or the development of new service-related policies.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Supply of Kitchens (Forward Plan Reference FP1187)Forward_plan 124 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 14 attended
PZ
Councillor Paul ZukowskyjLeader, present
LC
Councillor Lynn Chesterman OBEDeputy Leader, present
SB
Councillor Sandreni BonfanteCommittee Member, present
JB
Councillor James BroachCommittee Member, apologies
MH
Councillor Max HollowayCommittee Member, present
DJ
Councillor Duncan JonesCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, expected
SS
Sheila SaundersOfficer, expected
MS
Michael SherryCouncil Staff, in attendance
CC
Clare CadeSecretary, in attendance

All 14 on the meeting page

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies