Decision taken The Cabinet: a) approved progression of the scheme and endorsed the procurement approach. b) approved the appropriation of the land from the General Fund to the Housing Revenue Account at £4 million in line with the external valuations previously conducted at the time the agreement was signed. c) approved that the procurement exercise commences for a contractor to develop the site, utilising the Pretium Framework. d) noted the requirement for allocation of further funding to be completed as part of the standard budget setting process.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1The Affordable Housing Programme continues to aspire to deliver modern high- quality homes within the Borough. The direct delivery of affordable housing across the Borough remains a key strategic objective.
1.2Cabinet approved recommendations to the Land Purchase Agreement with the YMCA in June 2021. This gave delegated authority to negotiate the purchase of the land entering into land purchase agreement. The agreement included three milestones, with the last one including a final payment on receiving planning permission. This payment is already part of the capital strategy and budget allocated appropriately.
1.3The Council held the benefit of a number of covenants over the site, which impacted the value. The benefit of these covenants were held by the Council’s General Fund.
1.4The YMCA scheme continues to progress with a 4 storey, 100-unit hostel currently being delivered by the YMCA to the north of the site.
1.5This report presents the proposal for the development to construct 40 homes (18 two bedroom and 22 one bedroom). The land was purchased as a General Fund asset to allow the merger of the land and covenants and to allow a final decision on the use of the land to be made at a later date. The options were disposal on the private market or appropriation to the Housing Revenue Account (HRA) as part of the Affordable Housing Programme.
1.6A planning application was submitted for the site and now has been granted full permission.
1.7With planning permission secured the Housing Development team have assessed viability and procurement routes for the development route collaborating with employer’s agent Press and Starkey to secure a pathway to construction of the site.
2 Recommendation(s)
2.1That Cabinet approve progression of the scheme and endorse the procurement approach.
2.2That Cabinet approve the appropriation of the land from the General Fund to the Housing Revenue Account at £4 million in line with the external valuations previously conducted at the time the agreement was signed.
-1- 2.3 That Cabinet approve that the procurement exercise commences for a contractor to develop the site, utilising the Pretium Framework.
2.4The Cabinet notes the requirement for allocation of further funding to be completed as part of the standard budget setting process.
Background
3.1The Council’s five priorities as agreed by Full Council in November 2023 are set out as follows:
• Homes to be proud of
• Enable an economy that delivers for everyone
• Action on climate change
• Run an effective council
• Together, create opportunities for our communities
3.2The new Cabinet formed since May 2024 acknowledged that good progress has been made on the delivery of the business plan; the Affordable Housing Programme continues to progress. Within the last 18 months the programme has delivered a variety of homes for the residents of Welwyn Hatfield Borough. The rankings for 2023-24 have been compiled by Inside Housing Magazine, the trade publication for the UK’s social housing sector. Overall, the Council was ranked 10th for social rented completions in the UK and was 1st for councils in England outside of London.
3.3WHBC completed 159 homes in 23/4, 139 of which were added to the Council’s stock of socially rented properties, with the remaining 20 being used by the Council as temporary accommodation for families in urgent need.
3.4With this phase of construction completed; the attention has turned to the next phase of direct delivery for the Affordable Housing Programme and catalysing the delivery of more homes. The challenges facing the Borough in relation to housing affordability, remains evident, and the Council remains committed to the direct delivery of affordable housing as part of the corporate plan.
YMCA and Peartree
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.