FP2193 AFFORDABLE HOUSING PROGRAMME: COMMENCE PROCUREMENT

Approved Executive 1 paper

AI summaryWelwyn Hatfield Cabinet approves starting procurement for new council homes on two cleared garage sites, with £5.72m reallocated from the Burfield scheme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedHaseldine Meadows and Lockley Crescent to proceed to tender
MoneyNet nil impact on capital programme£5.720m moved from Burfield to other budgets
What happens nextTender via Pretium frameworkCompetitive process, 70% cost, 30% quality weighting
Who it affectsAffordable housing programme and residentsCouncil direct delivery of new homes in the borough

What was decided

Cabinet approved progression of the Phase 3 garage sites, Haseldine Meadows and Lockley Crescent, to commence procurement of a contractor. Report 2.1

Cabinet approved a virement increasing the AHP New Schemes budget by £1.72m, Haseldine Meadows by £2.25m, Lockley Crescent by £1.75m, and decreasing Burfield by £5.720m. Report 2.2, P8, P9, P10, P11

Cabinet acknowledged that the Burfield development will be revisited as part of the Affordable Homes Programme review after Howlands House, and approved the disposal of the Hazel Grove Garage site under delegated authority. Report 2.3, 2.4, 3.24

Why

Both sites have been decanted and demolished, leaving them ready for redevelopment, and a pre-tender estimate has been received from the Employer's Agent, Press & Starkey. Report 3.9, 3.10

Significant pre-tender costs led officers to recommend a national framework route to create efficiencies, secure better market value and improve scheme viability. Report 3.11, 3.12, 3.14

Burfield currently operates as temporary accommodation and is needed during the redevelopment of Howlands House, with its options best reassessed once that scheme is further forward. Report 3.19, 3.20

What happens next

Procurement of a contractor for the two sites will begin through the Pretium framework, with tender evaluation based on 70% cost and 30% quality. Report 3.13, 3.14, 3.15, 8.1

Following tender returns, a viability assessment will be carried out and a further report will return to Cabinet with recommendations. Report 3.17

A refreshed Affordable Housing Programme pipeline, informed by the current site review, is expected to be reported to Cabinet in the new year. Report 3.22

The money

  • £1.72m Increase to AHP New Schemes budget Report P8, 3.22
  • £2.25m Increase to Haseldine Meadows budget Report P9
  • £1.75m Increase to Lockley Crescent budget Report P10
  • £5.720m Decrease to Burfield budget Report P11, 3.21
  • circa £5m Pre-tender estimate for the two Phase 3 garage sites combined Report 3.11
  • £1.533m Existing combined allocation for Haseldine Meadows and Lockley Crescent Report 3.11
  • £4m Reallocated from Burfield to the Phase 3 garage site developments Report 3.21
  • £10,000 Estimated procurement and cost development fees, funded from the AHP Report 5.2
  • £10,000 Estimated revenue writeback if tenders are non-viable Report 6.3

Options considered

  • Chosen: Procure the contractor via the Pretium framework. Creates efficiencies, drives competitive value and improves scheme viability Report 3.12, 3.13, 3.14
  • Chosen: Reallocate £4m of Burfield's £5.72m to the Phase 3 garage sites. Covers the totality of the project and provides a contingency if tender returns exceed estimate Report 3.21
  • Chosen: Reallocate the remaining £1.72m from Burfield to AHP New Schemes. To support a refreshed pipeline to be reported to Cabinet in the new year Report 3.22
  • Chosen: Dispose of the Hazel Grove Garage site. Garage condition and viability challenges make direct delivery unsuitable, and a land receipt could fund other AHP sites Report 3.23, 3.24
  • Chosen: Revisit Burfield after the redevelopment of Howlands House. Allows continued use as temporary accommodation and a more informed assessment of housing needs Report 3.20

Implications

  • Financial: The virement has a net nil impact on the overall capital programme.
  • Legal: Cabinet has appropriate authority under the Council's constitution and Contract Procedure Rules to agree the recommendations. Report 4.1
  • Risk: The main project risk is scheme viability; the Pretium framework is PCR 2015 compliant and reduces procurement risk. Report 6.1, 6.2
  • Risk: If tenders are non-viable and construction does not proceed, an estimated £10,000 of capital costs would be written back to revenue. Report 6.3
  • Equalities: No Equality Impact Assessment was completed at this stage; one will be prepared if the project progresses. Report 14.1
  • Climate: No climate change implications identified at this stage. Report 9.1
  • Staffing: No human resources implications identified. Report 10.1

Who and where

  • Households on the council's housing waiting list seeking affordable rented homes in Welwyn Hatfield Report 1.1, 3.4
  • Families currently placed in the Burfield temporary accommodation facility Report 3.19, 3.20
  • Existing council tenants benefiting from new socially rented stock and temporary accommodation supply Report 3.3

Timeline

  • March 2019: Cabinet resolved that Phase 3 garage sites were suitable for direct housing delivery Report 3.5
  • 2022: Planning approval secured for Haseldine Meadows and Lockley Crescent Report 3.8
  • 23/4: Council completed 159 homes, 139 added to socially rented stock and 20 used as temporary accommodation Report 3.3
  • September 2025: Demolition of Haseldine Meadows and Lockley Crescent completed Report 3.9
  • 04th November 2025: Report dated by Assistant Director for Regeneration and Economic Development Report P78, P79
  • 02 December 2025: Cabinet considered and approved the recommendations
  • New year: Refreshed Affordable Housing Programme pipeline expected to be reported to Cabinet Report 3.22
  • Circa 5 years: Estimated timeframe before Burfield redevelopment Report 3.21

Plain English for the jargon

  • AHP: Affordable Housing Programme
  • HRA: Housing Revenue Account, the ringfenced account for council housing income and spend
  • ITT: Invitation to Tender, the document issued to contractors to bid for the work
  • PCR 2015: Public Contracts Regulations 2015, the procurement rules that public bodies must follow
  • EqIA: Equality Impact Assessment, a structured assessment of equalities effects
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item515a

Resolved

Decision taken Cabinet a) approved progression of the Phase 3 garage sites ( Haseldine Meadows and Lockley Crescent) to commence procurement of a contractor. b) approved the virement below, • Increase AHP New Schemes budget by £1.72m • Increase Haseldine Meadows budget by £2.25m • Increase Lockley Cresent budget by £1.75m • Decrease Burfield budget by £5.720m c) acknowledged that the Burfield development would be revisited as part of the Affordable Homes Programme review following the redevelopment of Howlands House.. d) approved the disposal of Hazel Grove Garage site in accordance with the delegated authority for disposals within the constitution.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The Affordable Housing Programme continues to aspire to deliver modern high- quality homes within the Borough. The direct delivery of affordable housing across the borough remains a key strategic objective.

1.2The Affordable Housing Programme is currently reviewing a number of sites to establish a new pipeline for development for the next 3-5 years. As part of this review, some historic sites have been reviewed to ensure that there is a refined focus on ensuring that the delivery of different typologies align with identified housing needs.

1.3This report presents an update on development sites Haseldine Meadows and Lockley Crescent, Phase 3 Garage sites, which have recently been demolished in preparation for development.

1.4This report also provides an update on two historic schemes, Burfield and Hazel Grove.

2 Recommendation(s)

2.1That Cabinet approves progression of the Phase 3 garage sites (Haseldine Meadows and Lockley Crescent) to commence procurement of a contractor.

2.2That Cabinet approves the virement below, which is detailed further in the report:

• Increase AHP New Schemes budget by £1.72m

• Increase Haseldine Meadows budget by £2.25m

• Increase Lockley Cresent budget by £1.75m

• Decrease Burfield budget by £5.720m

2.3That Cabinet acknowledges that the Burfield development will be revisited as part of the Affordable Homes Programme review following the redevelopment of Howlands House

2.4That Cabinet approves the disposal of Hazel Grove Garage site in accordance with the delegated authority for disposals within the constitution.

-1- 3 Background

3.1The Council’s five priorities as agreed by Full Council in November 2023 are set out as follows:

• Homes to be proud of

• Enable an economy that delivers for everyone

• Action on climate change

• Run an effective council

• Together, create opportunities for our communities

3.2The new Cabinet formed since May 2024 acknowledged that good progress has been made on the delivery of the business plan; the Affordable Housing Programme continues to make progress. Within the last 18 months the programme has delivered a variety of homes for the residents of Welwyn Hatfield Borough. The rankings for 2023-24 have been compiled by Inside Housing Magazine, the trade publication for the UK’s social housing sector. Overall, the Council was ranked 10th for social rented completions in the UK and was 1st for councils in England outside of London.

3.3WHBC completed 159 homes in 23/4, 139 of which were added to the Council’s stock of socially rented properties, with the remaining 20 being used by the Council as temporary accommodation for families in urgent need.

3.4With this phase of construction completed, the attention has turned to the next phase of direct delivery for the Affordable Housing Programme and catalysing the delivery of more homes. The challenges facing the borough in relation to housing affordability, remains evident, and the council remains committed to the direct delivery of affordable housing as part of the Corporate Business Plan.

Phase 3 Garage Sites

3.5In March 2019 Cabinet resolved that a number of garage sites (Phase 3 garage sites) were considered suitable for direct housing delivery and would be included within the Affordable Housing Programme.

3.6Two of the sites included within the programme have been completed. The Commons was redeveloped and delivery of 4 two bed homes and Marshall Close, formerly Ludwick Way, delivered 6 three-bedroom homes. These sites were considered more straight forward, with better viability and as such were delivered first.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FP2193 AFFORDABLE HOUSING PROGRAMME: COMMENCE PROCUREMENTReport 175 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
AS
Councillor Astrid ScottCommittee Member, present
BC
Bernice ComptonOfficer, in attendance
RM
Roxanne MisirSecretary, absent
SB
Councillor Sandreni BonfanteCommittee Member, present
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, in attendance
HO
Helen O'KeeffeOfficer, absent
JH
Jenny HowellOfficer, absent
MS
Michael SherryOfficer, in attendance
CC
Clare CadeSecretary, in attendance

All 17 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. FP2193 AFFORDABLE HOUSING PROGRAMME: COMMENCE PROCUREMENTThis decision
  2. FP2213 Affordable Housing Programme UpdateNoted
  3. FP2213 Affordable Housing Programme UpdateApproved
  4. Update on current affordable housing programmeNoted
  5. Affordable housing programme updateNoted
  6. Affordable Housing: 9,000 LevelAgreed

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies