CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Welwyn Hatfield Borough Council
Development Management Committee, Thursday 11 December 2025 at 7.30pm

6/2024/2035/OUTLINE ST.CHRISTOPHER'S NURSING HOME, DRAKES WAY, HATFIELD, AL10 8XY

Decided Committee 1 paper

AI summaryWelwyn Hatfield council grants outline planning permission for the former St Christopher's Nursing Home site in Hatfield, subject to a Section 106 agreement and 30 conditions covering drainage, ecology and transport.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedUnanimous, 11 votes to 0, with conditions
MoneySection 106 financial obligations requiredNo specific sums stated in report
What happens nextSection 106 and Section 278 agreements neededReserved matters application within three years
Who it affectsNot stated

What was decided

The Development Management Committee resolved to grant outline planning permission, with 11 members in favour, none against and no abstentions. Report 8.1

Permission is subject to completion of a Section 106 planning agreement and a Section 278 agreement, and to the conditions set out in the report. Report 8.1, P2, P3

Delegated powers were given to the Assistant Director (Planning) with the Chair of the Development Management Committee to negotiate the S106 obligations and amend draft conditions before the decision notice is issued. Report P4

Why

The recommendation followed assessment against the Welwyn Hatfield Local Plan, the National Planning Policy Framework, and consultee responses, including from the Lead Local Flood Authority, Affinity Water and Thames Water. Report P12, P22, P41, P91

Conditions were imposed to manage flood risk and surface water drainage, to protect a public water supply aquifer from contamination, and to secure biodiversity net gain of at least 10% on site. Report P16, P22, P45, P96

Further conditions address construction traffic, a pedestrian and cycle crossing on Travellers Lane, bus stop upgrades, tactile paving, noise from the nearby Hatfield Leisure Centre, and external lighting. Report P53, P56, P58, P60, P71, P79

What happens next

A Section 106 agreement covering financial and non-financial obligations, and a Section 278 highways agreement, must be completed, with extensions to the statutory determination period if needed. Report P2, P3, P4

An application for approval of reserved matters (appearance, landscaping, layout and scale) must be submitted to the council within three years of the permission being granted. Report P8, P10, P11

If the applicant fails to agree extensions to the determination period, the Head of Planning is delegated authority to refuse permission on the basis of an absent Section 106 agreement. Report P139, P140

The money

  • Financial contributions to be secured via Section 106 Mitigation of impact on local infrastructure and services Report P2, P4, P140

Options considered

  • Chosen: Grant outline planning permission subject to a Section 106 agreement and conditions. Recommended by the Assistant Director (Planning) as set out at [8.1] Report 8.1
  • Rejected: Refuse planning permission if no Section 106 agreement is completed. Held as a fallback delegation only if S106 negotiations fail Report P139, P140

Implications

  • Legal: A Section 106 legal agreement and Section 278 highways agreement must be completed before the permission is issued. Report P2, P3
  • Financial: Financial and non-financial obligations to mitigate impact on local infrastructure must be secured through the Section 106 agreement. Report P4, P140
  • Climate: Surface water drainage must be designed for the 1% annual exceedance probability event plus climate change, and Sustainable Drainage Systems (SuDS) must be used where feasible. Report P12, P16, P22
  • Risk: Contamination investigations, a remediation strategy, and a verification report are required, with Affinity Water consulted to protect a public water supply abstraction and aquifer. Report P25, P41, P45, P69
  • Other: The development must achieve and manage at least 10% biodiversity net gain on site for 30 years, with a Habitat Management and Maintenance Plan required. Report P94, P96, P97

Who and where

  • Future residents of the approved development at the former St Christopher's Nursing Home, Drakes Way, Hatfield Report P5, P7, P61
  • Existing residents on Drakes Way, Allen Court, Kingsmill Court and surrounding streets, including pedestrians using Travellers Lane Report P56, P60, P61
  • Hatfield Leisure Centre and users of its facilities, including football pitch floodlighting Report P75, P79, P80
  • Affinity Water, as statutory consultee for groundwater and public water supply protection Report P41, P45, P112
  • Thames Water, as statutory consultee for surface water network upgrades Report P91, P92
  • Lead Local Flood Authority, Hertfordshire Highways and Waste Planning Authority Report P15, P50, P53
  • Ecology, including bats, reptiles, great crested newts, badgers and nesting birds on and adjacent to the site Report P37, P38, P104, P106

Timeline

  • 03 October 2024: Flood Risk Assessment and SuDS Strategy submitted Report P12
  • 21 October 2024: Location plan received by the council Report P7
  • 07 November 2025: Officer report dated by Mark Peacock, Development Management Report P144
  • 11 December 2025: Development Management Committee resolves to grant outline planning permission
  • Three years from the date of permission: Deadline for submission of reserved matters application Report P10

Plain English for the jargon

  • Outline planning permission: Permission that establishes the principle of a development, with detailed matters reserved for later approval.
  • Reserved matters: Details of appearance, landscaping, layout and scale that must be submitted and approved before development begins.
  • Section 106 agreement: A legal agreement under Section 106 of the Town and Country Planning Act 1990 used to secure planning obligations such as financial contributions.
  • Section 278 agreement: A highways agreement under Section 278 of the Highways Act 1980 for works to the public highway.
  • SuDS: Sustainable Drainage Systems, such as basins, permeable surfaces and swales, that manage surface water runoff.
  • AEP: Annual Exceedance Probability, the chance of a flood event occurring in any given year, for example 1% AEP is a 1 in 100 year event.
  • Biodiversity Net Gain: A statutory requirement for development to deliver at least a 10% increase in biodiversity value relative to the pre-development baseline, managed for 30 years.
  • CEMP: Construction Environmental Management Plan, setting out measures to protect ecology and the environment during construction.
  • LEMP: Landscape Ecological Management Plan, covering long term management of landscaping and ecological features.
  • CTMP: Construction Traffic Management Plan, covering vehicle routing, parking, wheel washing and similar controls during construction.
  • SWMP: Site Waste Management Plan, setting out how construction waste will be reduced and managed.
  • RPA: Root Protection Area, the zone around a tree in which ground disturbance and construction activity must be controlled.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item250

Resolved

(for 11, against 0, abstain 0) That planning permission be granted, subject to the conditions set out in the report.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Development Management Committee

ADDENDUM REPORT

WELWYN HATFIELD BOROUGH COUNCIL DEVELOPMENT MANAGEMENT COMMITTEE – 11 DECEMBER 2025 REPORT OF THE ASSISTANT DIRECTOR (PLANNING)

6/2024/2035/OUTLINE

ST CHRISTOPHERS NURSING HOME DRAKES WAY HATFIELD AL10 8XY

OUTLINE PERMISSION FOR THE DEMOLITION OF EXISTING BUILDINGS (USE CLASS C2) AND ERECTION OF UP TO 72 NO. RESIDENTIAL DWELLINGS (USE CLASS C3), WITH ALL MATTERS RESERVED

APPLICANT: EVEN HATFIELD LTD 1 Introduction

1.1The application was considered at the Development Management Committee (DMC) of 19th December 2024. As set out in the minutes to the meeting, following discussions at the meeting, Members resolved to approve the application subject to the conditions set out in the Committee Report. The resolution is subject to the conditions and also:

“Completion of a satisfactory s106 planning agreement and the agreement of any necessary extensions to the statutory determination period to complete this agreement”

1.2Whilst not specifically listed in the resolution, the planning obligations sought by the Council in December 2024 were listed in Section 7 of the Committee Report.

1.3No amendments have been made to the substance of the application as it is described in the original Committee Report.

1.4An updated resolution is now sought to reflect the amended expected heads of terms of the ‘satisfactory s106 planning agreement’ to reflect the recent adoption and commencement of Community Infrastructure Levy charging.

2 Site Description

2.1The site is located directly south of Hatfield Leisure Centre, east of Travellers Lane and De Havilland Nursery and Primary School, and to the north and west of two-storey residential development on Drakes Way and Stanley Drive.

2.2The site is approximately 1.5 hectares in area and is occupied by five single storey buildings and a two-storey communal ‘hub’ which forms St Christopher’s residential care home (use class C2). St Christopher’s closed in August 2023, and it remains vacant. 2.3 The wider site includes landscaped communal areas for residents enclosed by a perimeter boundary hedge and fencing.

2.4The site is accessed by a single-entry point to the south of the site from Drakes Way, with an area of hard standing located to the centre of the site for parking.

2.5The site is located in Flood Zone 1 (least likely to flood) and is not located within a conservation area, nor is it within the Metropolitan Green Belt.

3 The Proposal

3.1Outline planning permission is sought for the demolition of existing buildings (use class C2) and erection of up to 72no. residential dwellings (use class C3), with all matters reserved.

3.2An indicative layout plan has been submitted to illustrate how the site could be developed. The indicative mix includes 1 and 2 bed apartments and 2, 3 and 4 bed houses at scales of two and three stories.

3.3The primary access into the site is proposed to be via the retained and adapted access off Drakes Way. In addition, a new secondary access is proposed to the east of the existing access. Parking provision is distributed across the site in a variety of forms, including private driveways, shared parking courts, and designated visitor bays. The indicative layout also incorporates landscaping and areas of open space throughout the development.

3.4While the submitted drawings provide an indication of how the site could be developed, the application is for outline permission with all matters reserved. Accordingly, only the site location plan is recommended for approval under Condition 1. All detailed design elements, including layout, scale, appearance, landscaping, and access, will be secured and assessed at the reserved matters stage.

4 Progress to Completion of the Legal Agreement

4.1The Council has been working with the applicant to seek to progress the legal agreement to completion so that a decision can be issued and the site can be delivered for housing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
6/2024/2035/OUTLINE ST.CHRISTOPHER'S NURSING HOME, DRAKES WAY, HATFIELD, AL10 8XYAddendum 726 KB DownloadRead as text

At this meeting

Whole meeting
2506/2024/2035/OUTLINE ST.CHRISTOPHER'S NURSING HOME, DRAKES WAY, HATFIELD, AL10 8XYThis decision
251Future Planning ApplicationsNoted

Who was there

13 of 30 attended
MW
Matthew WilsonOfficer, in attendance
JK
James KenyonCouncil Staff, absent
CG
Carl GriffithsOfficer, in attendance
RW
Rob WalkerPublic, absent
EK
Emily KingswellCouncil Staff, absent
BC
Bernice ComptonOfficer, in attendance
ZA
Zayd Al-JawadOfficer, absent
RM
Roxanne MisirSecretary, absent
JB
Councillor Jean-Paul Bernard SkoczylasChairman, present
DP
Councillor Darrell PanterCommittee Member, apologies
RT
Councillor Roger TriggCommittee Member, present
CW
Councillor Cathy WatsonCommittee Member, present

All 30 on the meeting page

More from Welwyn Hatfield Development Management Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 6/2025/2484/FULL - 109 Woods Avenue, Hatfield, AL10 8QQ(for 11, against 0, abstain 0) That planning permission be granted, subject to the conditions set out in the report. Decided Open
25 Jun 2026 Appeal Decisions 2 March 2026 to 12 June 2026 ReportResolved – the Committee noted the report. Noted Open
25 Jun 2026 Future Planning ApplicationsResolved – the Committee noted the report. Noted Open
12 Mar 2026 Appeal Decisions 2 February 2026 to 2 March 2026 ReportRESOLVED It was resolved to note the contents of the report. Noted Open
12 Mar 2026 Future Planning ApplicationsRESOLVED To note the contents of the report. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies