Presentation: Social Housing Decarbonisation

Noted Executive 1 paper

AI summaryThe Climate Biodiversity Cabinet Panel noted a presentation on social housing retrofit programmes, including £6.4m in government grants matched by £13m for 653 homes over three years, and work completed on 120 Wimpey no-fines properties.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further resolution passed at this meeting
Money£6.4m grant, £13m matchWave 3 funding for 653 properties, April 2025 to March 2028
What happens nextContinue Wave 3 retrofitYear 2 covers 245 properties in Welwyn Garden City and Hatfield
Who it affectsCouncil social housing tenantsTargeted 1,600 of 9,167 properties rated EPC D or below

What was decided

The Panel noted the presentation on Social Housing Decarbonisation Fund 2.1 and Warm Homes Social Housing Fund Wave 3. Report P1

Why

The Panel was updated on work to reduce carbon emissions from the council's housing stock, which accounts for around a fifth of UK greenhouse gas emissions. Report P2

Officers reported progress on retrofitting the worst-performing properties, including 120 Wimpey no-fines homes treated under a full fabric-first approach. Report P3, P4

What happens next

Wave 3 retrofit continues: 186 properties in Hatfield in year 1, 245 across Welwyn Garden City and Hatfield in year 2, and 222 in Welwyn Garden City in year 3. Report P9

The council is shortlisted for the NHMF Maintenance Conference January 2026 Awards in the Keeping Residents Warm category. Report P8

A new contractor, EverWarm, has been mobilised to help the council meet the 2030 EPC 'C' target for rented homes. Report P3

The money

  • £2.7m Grant funding under Social Housing Decarbonisation Fund for Wave 2.1 Report P3
  • 5.8m Match funding for Wave 2.1 retrofit of 234 properties Report P3
  • £6.4m Government grant mobilised for Wave 2.1 retrofit of 653 properties Report P3
  • £13m Match funding for Wave 2.1 retrofit of 653 properties Report P3
  • £6.4m Grant funding secured for Warm Homes Social Housing Fund Wave 3 Report P9
  • £13m Match funding for Wave 3 retrofit of 653 homes Report P9

Implications

  • Climate: Retrofit measures including external wall insulation, heat pumps and solar panels are intended to cut carbon emissions from the housing stock. Report P2, P3
  • Financial: Government grants of £6.4m (Wave 2.1 and Wave 3) are matched by £13m of council or partner funding. Report P3, P9
  • Equalities: Work aims to reduce fuel poverty and make homes healthier and more comfortable for residents. Report P3
  • Risk: All rented homes must reach EPC 'C' or above by 2030, requiring continued retrofit progress. Report P3
  • Staffing: The council is partnering with Morgan Sindall on Wave 2.1 and has mobilised EverWarm to support delivery. Report P3

Who and where

  • Tenants in 1,600 council properties rated EPC 'D' or below Report P3
  • Residents of 120 Wimpey no-fines properties receiving full fabric-first retrofit Report P3, P4
  • Residents of 653 homes targeted under Wave 3 across Hatfield and Welwyn Garden City Report P9
  • A resident interviewed about retrofit works (named in source, not quoted in this summary) Report P7

Timeline

  • 1940-1960: Around 300,000 Wimpey no-fines properties built across the UK Report P4
  • April 2025 - March 2028: Wave 3 retrofit programme covers 653 properties Report P3, P9
  • January 2026: NHMF Maintenance Conference Awards shortlisting Report P8
  • 2030: Deadline for all rented homes to reach EPC 'C' or above Report P3
  • Year 1 (to April 2026): 186 properties in Hatfield Report P9
  • Year 2: 245 properties in Welwyn Garden City and Hatfield Report P9
  • Year 3: 222 properties in Welwyn Garden City Report P9

Plain English for the jargon

  • EPC: Energy Performance Certificate, rating the energy efficiency of a property
  • Wimpey No Fines: Post-war housing built with concrete poured on site without insulation
  • EWI: External Wall Insulation added to the outside of a building
  • IWI: Internal Wall Insulation fitted to the inside of solid walls
  • Fabric-first approach: Improving the building fabric (walls, roof, windows) before adding heating systems
  • Wave 2.1: Second round of the Social Housing Decarbonisation Fund
  • Wave 3: Warm Homes Social Housing Fund round covering 2025 to 2028
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item73

Resolved

RESOLVED The Panel noted the presentation.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Climate Biodiversity Cabinet Panel

Social Housing Decarbonisation Fund 2.1 & Warm Homes Social Housing Fund 3

By Jamie Norman Planned Works Delivery Manager Investment Programme Delivery  “The process of reducing or eliminating carbon dioxide (CO₂) emissions, primarily from energy consumption, industrial processes, and transportation”. How is this linked to Housing?  In the UK, residential buildings are a significant source of carbon emissions, accounting for about a fifth (20%) of the country's greenhouse gas emissions. This is partly due to the high proportion of gas-heated homes and the relatively poor energy efficiency of many existing homes. What is How can we reduce our carbon emissions to WHBC Housing stock?

Decarbonisation?  Improving insulation to the building fabric such as external wall insulation  Switching to electric heating (like heat pumps)  Using renewable energy sources like solar panels/air/ground source heat pumps. What are the benefits of Decarbonisation?  Reduces fuel poverty  Make homes healthier and more comfortable for residents How are the Government tackling climate change?  Phasing out fossil fuels in new homes starting in 2025 with no new oil or coal heating systems from 2028.  Retrofitting existing homes – providing social housing landlords grant funding to upgrade older homes with energy efficient measures to reduce their carbon footprint.  All rented accommodation must have an energy performance certificate (EPC) rating of ‘C’ or above by 2030. What are WHC doing to tackle climate change in social housing?  Council undertook 82% stock condition surveys on dwellings and 100% on blocks which identified 1600 out of 9167 properties had an EPC rating ‘D’ or below.  We applied for £2.7m grant funding under social housing decarbonisation fund (5.8m match fund) to retrofit 234 properties to bring them from a grade G/F to C.  Partnering with Morgan Sindall Decarbonisation team to support us with the delivery of wave 2.1 (234 properties)  Procured and mobilised £6.4m government grant (£13m match funded) to retrofit 653 properties between April 2025-March 2028  Mobilised a new contractor (EverWarm) to assist with improving the thermal efficiency to additional properties to ensure we meet the 2030 target. Social Housing Decarbonisation Wave 2.1  Wave 2.1 programme consisted of our worst performing properties (120 Wimpey no fines properties with metal roofs and 114 traditional cavity wall properties).  120 properties we tackled as a “full fabric first approach”. Which consists of external wall insulation, new flat roofs, triple glazed windows and ventilation.  114 properties were cavity wall insulation, pitched roof insulation, bay window insulations and ventilation. Wimpey No Fines

 After World War 2 there was a need for mass production of social housing for families that was quick to build and affordable.  Wall construction made up of solely concrete which was poured directly into formwork on-site with no insulation. Compared to traditional building that are built out of brick and block with a cavity that can be insulated.  Approximately 300,000 properties built between 1940-1960 Retrofit to Wimpey No Fines  Installed 110mm external wall insulation to the outerleaf wall.  New flat roofing with 150mm insulation and associated fire compartmentation breaks between party walls.  Triple glazed windows and doors

 Extractor fans within the kitchen, bathrooms

 Undercuts to internal doors to provide cross room ventilation  Damp and mould fungicidal wash Customer feedback following retrofit  ‘All went fine and no issues at all, everything looks really nice!’  ‘Happy with all of the works. Really impressed with the windows & doors and the contractors’  ‘Noticed difference in energy cost’  ‘Happy something nice has been done to the home, looks a lot nicer and energy cost down’  ‘My Goodness, the house is looking so much better! :)’

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Presentation: Social Housing DecarbonisationReport 4.7 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 21 attended
BC
Bernice ComptonSecretary, expected
JW
Janice WhiteOfficer, expected
EW
Emma WalkerCouncil Staff, in attendance
RB
Richard BakerOfficer, expected
CC
Clare CadeOfficer, expected
SM
Sue McDaidOfficer, in attendance
KM
Kelly MurphyOfficer, in attendance
KN
Ka NgOfficer, expected
HO
Helen O'KeeffeOfficer, expected
ER
Eliska RobovaOfficer, expected
GS
Geoff SampsonOfficer, expected
RM
Roxanne MisirSecretary, expected

All 21 on the meeting page

More from Welwyn Hatfield Climate Biodiversity Cabinet Panel

All decisions
MeetingDecisionOutcome
1 Jul 2026 Climate and Biodiversity Cabinet Panel IntroductionThat the Panel noted the key documents that define and underpin the Council’s climate change and wider sustainability... Noted Open
1 Jul 2026 Climate and Biodiversity Declaration RequestResolved that the Panel – a) Declared a Climate and Biodiversity Emergency; b) Recognised that nature and climate cha... Decided Open
1 Jul 2026 Smoke Control Area UpdateResolved – that the Council would not introduce a smoke control area covering the Borough of Welwyn Hatfield. Decided Open
14 Jan 2026 Aprroval of support for the carbon offsetting standards for local authorities in hertfordshireRESOLVED The Panel recommended that Cabinet delegate authority to the Executive Director (Resident Services and Clima... Approved Open
14 Jan 2026 Retrofit for One Stop ShopRESOLVED The Panel approved the drawdown of £2,000 from the Climate Change Earmarked Reserve as the Council’s contrib... Approved Open