Written from the decision and the officer reportPDF Pro
OutcomeAgreedH Taylor and Son (RS Sailing) for 18 boats
MoneyCost met from 2026/27 capital budget, no figure given
What happens nextDeliver before Easter school holidaysSailing provision restarts after winter break
Who it affectsStanborough Lakes watersport centre usersOver 1000 customers per year of all ages and abilities
What was decided
Cabinet agreed unanimously to make a direct award to H Taylor and Son (Brockley) Ltd trading as RS Sailing for the purchase of 18 sailing boats. Report 2.1
Cabinet agreed to waive the Council's Contract Procedure Rules to allow the direct award. Report 2.2, 4.1
Why
The existing sailing boat fleet failed the Royal Yachting Association annual inspection in Autumn 2025 and was removed from service in November 2025. Report 1.3, 3.1
The report argues a direct purchase from an approved RYA manufacturer avoids third party mark-up and ensures quality, and notes an existing partnership between GLL and the contractor. Report 3.4, 3.6
Officers warn that a lack of boats would harm customer satisfaction and the visitor offer, with negative effects on income and reputation. Report 6.2
What happens next
Purchase 15 RS Zest Complete with Jib Pack and 3 RS Feva S Complete boats, each 3.7m, to be delivered before the Easter school holidays. Report 3.3, P12, P13, 3.4
Costs will be drawn from the 2026/27 capital budget that Full Council approved on 6th February 2026. Report 1.4, 5.1
The money
2026/27 capital budget Source of funding for the 18 sailing boats and associated equipment Report 5.1, 1.4
Options considered
Chosen: Direct award to RS Sailing for 18 sailing boats. Existing partnership with GLL, approved RYA manufacturer, avoids third party charges, ensures timely delivery for Easter holidays Report 2.1, 3.4, 3.6
Rejected: Purchase through a third party. Third parties would add charges for sourcing the boats Report 3.4
Implications
Legal: Recommendation relies on section 33.2(g) of the Council's Contract Procedure Rules, allowing waiver when Cabinet agrees it is to the Council's advantage. Report 4.1
Financial: Cost to be met from the 2026/27 capital budget; no specific figure is given in the report. Report 5.1
Risk: Without replacement boats, customer satisfaction, visitor perception, income and reputation at Stanborough Lakes would all suffer. Report 6.2
Equalities: No Equality Impact Assessment completed; no negative impacts identified on protected groups. Report 14.1
Other: Report notes health and wellbeing benefits of sailing, including cardiovascular health, reduced stress and anxiety, and improved concentration and coordination. Report 11.1, P36
Who and where
GLL, the operator at Stanborough Lakes watersport centre Report 3.6
Over 1000 customers per year using Stanborough Lakes for sailing, across a range of ages and abilities Report 3.7
Residents and visitors to the borough using the watersport centre Report 1.1
Timeline
1973: Sailing commenced at Stanborough Lakes Report 1.2
Autumn 2025: Boat fleet failed the annual Royal Yachting Association inspection Report 3.1
November 2025: Sailing boats removed from service following the half term activities Report 1.3, 3.1
6th February 2026: Full Council approved capital budget to replace 18 boats and associated equipment Report 1.4, 3.3
19th February 2026: Report authored by Executive Director, Place Report P43
3 March 2026: Cabinet resolved to make direct award and waive Contract Procedure Rules
School Easter holidays (2026): Sailing programme restarts; boats to be delivered in time for the start of the season Report 3.2, 3.4
Plain English for the jargon
GLL: The operator running the Stanborough Lakes watersport centre on behalf of the Council.
RS Sailing: Trading name of H Taylor and Son (Brockley) Ltd, the approved Royal Yachting Association manufacturer supplying the boats.
RYA: Royal Yachting Association, the national body for sailing in the UK that carries out annual inspections of sailing fleets.
Contract Procedure Rules: The Council's internal rules governing how contracts must be procured, which Cabinet agreed to waive for this purchase.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item581
Resolved
Cabinet resolved unanimously to: a) Agree to make a direct award to H Taylor and Son (Brockley) Ltd trading as RS Sailing for the purchase of the 18 sailing boats b) Agrees it is to the advantage of the Council that the Contract Procedure Rules are waived to facilitate a direct award.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1Stanborough Lakes watersport centre is a popular visitor attraction within the borough and provides watersport activity for residents.
1.2Sailing commenced on site in 1973
1.3The boating stock failed its Royal Yachting Association annual inspection and the boats were taken out of commission in November 2025 in line with the recommendations from the report
1.4A capital bid was prepared and agreed by Full Council on 6 th February 2026 to replace 18 boats and associated equipment
2 Recommendation(s)
2.1That Cabinet agree to make a direct award to H Taylor and Son (Brockley) Ltd trading as RS Sailing for the purchase of the 18 sailing boats
2.2That cabinet agrees it is to the advantage of the Council that the Contract Procedure Rules are waived to facilitate a direct award.
3 Explanation
3.1The sailing boat fleet at Stanborough failed their inspection of the annual RYA inspection in Autumn 2025 and were removed from service in November following the half term activities.
3.2Over the winter months there is no sailing provision but the programme restarts in time for the school Easter holidays with lessons and courses being made available throughout the peak times in the year.
3.3The budget was approved on 6th February for the capital expenditure for the boats to purchase the following:
RS Zest Complete inc. Jib Pack - 3.7m x 15
FEV-CB-001 RS Feva S Complete - 3.7m x 3
3.4In order to receive delivery of the boats in time for the start of the Easter Holidays, it is preferred to purchase directly from an approved RYA manufacturer -1- at cost rather than through a third party who will add charges for sourcing the boats.
3.5The sailing craft chosen are replacements (now in line with changes in the industry) for the craft that has been taken out of commission.
3.6There is an existing partnership/relationship between GLL and the approved contractor and this greatly reduces the risk regarding the suitability and quality of the boats ensuring that the Council’s assets will be of the highest quality.
3.7The sailing provision at Stanborough Lakes attracts in excess of 1000 customers per year from across a range of ages and abilities.
Implications
4 Legal Implication(s)
4.1The recommendation is in accordance with section 33.2(g) of the Council’s Contract Procedure Rules ‘Where the Cabinet agrees a report, from an Executive Director or the Chief Executive, detailing a case where it is to the advantage of the Council that these rules should be waived ‘.
5 Financial Implication(s)
5.1The costs will be met from the 2026/27 capital budget.
6 Risk Management Implications
6.1None directly associated with this recommendation.
6.2Lack of boats will have a significant impact on customer satisfaction and perception of quality visitor experience making Stanborough lakes less desirable as a visitor destination, resulting in a negative effect on income and reputation.
7 Security and Terrorism Implication(s)
7.1None directly associated with this report.
8 Procurement Implication(s)
8.1See Legal implications
9 Climate Change Implication(s)
9.1None directly associated with this report.
10 Human Resources Implication(s)
10.1None directly associated with this report.
11 Health and Wellbeing Implication(s)
11.1There are many health benefits associated with sailing activity including improved cardio vascular health, reduced stress and anxiety, enhanced muscle strength and endurance.
-2- 11.2 Sailing has been proven to improve concentration and coordination skills - especially for those who may have additional needs
12 Communication and Engagement Implication(s)
12.1None directly associated with this report.
13 Link to Corporate Priorities
13.1Supports the priority ‘Together create opportunities for our community’.
14 Equality and Diversity
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.