Overview and Scrutiny Committee, Wednesday 4 March 2026 at 7.30pm

Final Report of the Housing Voids Task & Finish Group

Noted Scrutiny 1 paper

AI summaryWelwyn Hatfield scrutiny committee backs recommendations to speed up re-letting of empty council homes, with tighter contractor oversight and revised performance measures.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted report and agreed all recommendations
MoneyWithin existing budgetSavings built into 2026/27 budget; no new sums quoted
What happens nextProgress report in Q2 2026/27Officers to report back to scrutiny in summer 2026
Who it affectsCouncil tenants and housing staffChanges cover pre-void process, recharges, contractors

What was decided

The committee endorsed six recommendations, including a standardised pre-termination visit form, consistent tenant recharges, strengthened contractor oversight with financial recovery mechanisms, revised void KPIs, and a progress report in Q2 of 2026/27.

The committee also noted planned operational changes: a digital inspection checklist with photos, earlier advertising of properties, open days for hard-to-let homes, ongoing staff recruitment, and training on the new tools and recharge policy.

Why

The void process is clearly defined but has been held back by staffing shortages in pre-inspections and mixed contractor performance, with Morgan Sindall missing targets and receiving a formal improvement notice.

Recharges for properties left in poor condition are inconsistently applied, and current KPIs do not cover key stages such as key handover or re-let times, so the group proposed new measures and a review.

Existing void targets are similar to those of other Hertfordshire councils that hold housing stock, and the group identified further operational gains such as digital inspections and earlier advertising.

What happens next

Officers will report back to the Overview and Scrutiny Committee in summer 2026, roughly Quarter 2 of 2026/27, on progress with the recommendations.

Contractors are working to a target of 31 March 2026 to complete long-standing voids, with an additional contractor (McConnells) taking on reallocated work to lift weekly output.

Staff recruitment will continue to address pre-inspection shortages, and training will be rolled out for the new digital inspection tools and refreshed recharge policy.

The money

  • built into the approved 2026/27 budget Savings on council tax and increased rental income from lower void rates Report 5.3

Options considered

  • Chosen: Agree the task and finish group recommendations and note operational improvements. Committee endorsed the report in full
  • Rejected: Reject or amend the recommendations. Not raised in the papers; the committee agreed them as set out

Implications

  • Legal: As a social housing landlord, the council must meet the Regulator of Social Housing's Safety and Quality Standard and Tenancy Standard when re-letting empty homes. Report 4.1, P10, P12
  • Financial: Faster turnarounds should improve HRA finances, with rent loss and council tax recoverable where contractor delays occur, and higher income expected from reformed recharge recovery. Report 5.2, 5.3
  • Staffing: Staffing shortages in pre-inspections remain, and the new digital inspection checklist will need skills training, change support, and updated procedures.
  • Risk: Operational risks include staffing shortages, inconsistent contractor performance, long-standing structural voids, and uneven application of recharges; the recommendations are designed to mitigate these. Report P15
  • Equalities: No Equality Impact Assessment was carried out, as the recommendations do not require a policy or service change. Report P18
  • Climate: No new climate change implications arise from the report. Report P16

Who and where

  • Council tenants ending their tenancy, who will be asked to give four weeks' notice and may face recharges for poor-condition homes Report P5
  • Housing applicants waiting for re-let properties, who may see shorter turnaround times and earlier advertising
  • Council housing staff in pre-inspection and surveying roles, facing recruitment and training changes
  • Void works contractors, particularly Morgan Sindall (under improvement notice) and McConnells (newly appointed)

Timeline

  • 10 December 2025: First task and finish group meeting; officers outlined the voids process and performance data Report P5
  • early February 2026: Group visited two contrasting void properties and viewed a video of a third requiring rewiring Report P6
  • 11 February 2026: Second task and finish group meeting discussed benchmarking, contractor capacity, decision-making and workforce issues Report P5
  • 16 February 2026: Report dated and signed off by the Assistant Director (Homes and Neighbourhoods) Report P19
  • 4 March 2026: Overview and Scrutiny Committee noted the report and agreed the recommendations Report P2
  • 31 March 2026: Target date for contractors to complete long-standing voids
  • Summer 2026 / Q2 2026/27: Officers to provide a progress report to the Overview and Scrutiny Committee

Plain English for the jargon

  • Void: A council home that is empty between tenancies and being prepared for re-letting.
  • Pre-void inspection: A check carried out before a tenant leaves to identify repairs, recharges and works needed.
  • Recharge: A charge to a former tenant for repair or cleaning costs when a property is left in poor condition.
  • KPI: Key Performance Indicator, a measure used to track how well a service is performing.
  • Major-plus void: Voids needing the most complex structural or major works, currently excluded from standard void performance figures.
  • HRA: Housing Revenue Account, the ring-fenced account that funds council housing.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item31a

Resolved

The Overview and Scrutiny Committee noted the report, and agreed the recommendations as set out in the report.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Part I Main author: Janice White Executive Member: Cllr Gemma Moore All Wards

WELWYN HATFIELD BOROUGH COUNCIL OVERVIEW AND SCRUTINY COMMITTEE – 4 MARCH 2026 REPORT OF THE EXECUTIVE DIRECTOR (RESIDENT SERVICES AND CLIMATE CHANGE)

HOUSING VOIDS TASK & FINISH GROUP REPORT 1 Executive Summary 1.1 The Housing Voids Task & Finish Group was established to examine the Council’s voids management processes and assess opportunities to: • Reduce void turnaround times. • Strengthen contractor performance management; and • Ensure current void targets remain appropriate in light of recent changes to void standards.

1.2This report provides the Overview and Scrutiny Committee with the work of the Housing Voids Task & Finish Group and to seek endorsement of the recommendations to support improvements in void turnaround. 1.3 The key findings were: • The void process is clearly defined but has been affected by staffing shortages, especially in pre-inspections. Recruitment is underway but remains challenging. • Contractor performance has been mixed. Morgan Sindall has missed targets and received a formal improvement notice, and some work reallocated to the recently appointed contractor McConnells. • Performance currently averages around 13 voids returned per week, and long-standing voids remain, but the contractors are working to a target date of 31 March 2026 to complete these. • Recharge policies for properties left in poor condition by outgoing tenants are inconsistently applied; work is ongoing to strengthen enforcement • Voids turnaround targets are similar to neighbouring hertfordshire councils • Current KPIs do not cover all key elements (e.g. time to key handover or re-let) and require review. • A range of operational improvements in addition to contractor performance, such as digital inspection tools, earlier advertising, and strengthened pre-void processes, has the potential to reduce turnaround times. 2 Recommendation 2.1 That Overview and Scrutiny Committee note the contents of the report. 2.2 That Overview and Scrutiny Committee agree the following recommendations: 2.2.1 That the pre-void process is improved requiring tenants to give the contractual four weeks’ notice when terminating a tenancy. 2.2.2 The introduction of a standardised pre-termination visit form. 2.2.3 That recharges are consistently applied and recorded on tenancy accounts. 2.2.4 To strengthen contractor oversight and apply financial recovery mechanisms where timescales are not met. 2.2.5 Officers implement a revised list of KPIs for voids and lettings 2.2.6 Officers to provide a progress report in Quarter 2 of 2026/27. 2.3 That Overview and Scrutiny Committee note the following operational improvements being made: 2.3.1 Implement a digital inspection checklist supported by photographic evidence. 2.3.2 Advertise properties earlier in the void cycle where feasible (“pre-let”). 2.3.3 Reduce refusal rates through initiatives such as open days for hard-to-let homes. 2.3.4 Ongoing recruitment of staff to ensure pre-inspections are undertaken. 2.3.5 Staff training to be undertaken on the digital inspection tools and the recharge policy.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Final Report of the Housing Voids Task & Finish GroupReport 200 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
BC
Bernice ComptonSecretary, expected
ZA
Zayd Al-JawadOfficer, expected
RM
Roxanne MisirSecretary, expected
TR
Councillor Tim RowseCommittee Member, present
KN
Ka NgOfficer, expected
HO
Helen O'KeeffeOfficer, expected
TM
Councillor Terry MitchinsonCommittee Member, expected
AN
Councillor Adrienne NixCommittee Member, apologies, sent representative
BS
Councillor Bernard SarsonCommittee Member, present
CC
Clare CadeOfficer, expected
LC
Councillor Lynn Chesterman OBEVice-Chairman, present
SA
Councillor Shirley AsareCommittee Member, present

All 17 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. Final Report of the Housing Voids Task & Finish GroupThis decision
  2. Final Report of the Housing Voids Task and Finish GroupApproved

More from Welwyn Hatfield Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 Actions status reportResolved To note the report. Noted Open
22 Jul 2026 Committee work programme 2026/27To note the Overview and Scrutiny Work Programme 2026/27 Noted Open
4 Mar 2026 Final report of the Customer Communication & Case Management Task and Finish GroupThe Overview and Scrutiny Committee noted the report, and the recommendations in the report be referred to Cabinet. Noted Open
4 Mar 2026 Presentations on Crime and DisorderRecommendations from report/what was agreed. Agreed Open