AI summaryWelwyn Hatfield Council launched a Community Governance Review focused on Welwyn Garden City, with the first consultation set to open on 19 May 2026. The 12-month process, costing up to £140k, will examine whether to create a new parish council.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTerms of Reference, consultation and Cross-Party Panel agreed
MoneyUp to £140kFunded from Strategic Initiatives Earmarked Reserve
What happens next19 May 2026Process commences with first consultation
Who it affectsWelwyn Garden City residentsUnparished area of Welwyn Garden City, plus wider stakeholders

What was decided

Full Council approved the Terms of Reference, notice for publication, and consultation questions for the Community Governance Review, focusing on Welwyn Garden City. Report 2.2

A Community Governance Review Cross-Party Panel was established, with councillor membership to be set by Group Leaders. Report P12, 2.4

Authority was delegated to the Chief Executive, in consultation with the Cross-Party Panel, to make minor changes to documents and decisions needed to keep the process on track. Report 2.4, 2.5

Why

A motion passed at Full Council on 12 March 2025 instructed officers to explore a Community Governance Review, particularly to safeguard local representation in Welwyn Garden City.

A December 2025 residents' consultation in Welwyn Garden City indicated support for a new Parish Council, considered by Cabinet on 3 March 2026, which then recommended this approach to Full Council. Report 1.2, 1.3

What happens next

The review formally commences on 19 May 2026, when the Terms of Reference, consultation questions and related documents are published. Report 1.5, 2.6

Two consultation stages will run with all residents and stakeholders within the council's boundary, with the Cross-Party Panel evaluating responses and recommending an outcome to Full Council. Report 1.6, 12.2

The review is expected to finish within 12 months, with any new parish council elections planned to coincide with the May 2027 local elections, or for the shadow Unitary Authority to decide if not completed by then. Report 1.6, 4.3

The money

  • up to £140k Estimated total cost of the Community Governance Review, covering external resources such as Counsel and postage Report 5.2, 5.3

Options considered

  • Rejected: Take no further action. One of three options to be put to public consultation under the Terms of Reference Report 3.3
  • Rejected: Establish a Neighbourhood Area Committee or other non-parish community engagement arrangement. One of three options to be put to public consultation under the Terms of Reference Report 3.3
  • Rejected: Establish a new Parish Council for Welwyn Garden City. One of three options to be put to public consultation under the Terms of Reference; residents' consultation in December 2025 indicated support for this option Report 1.2, 3.3

Implications

  • Legal: A Community Governance Review is a Full Council function under the Local Government (Functions and Responsibilities) Regulations 2000, with the process set out in sections 79 to 102 of the Local Government and Public Involvement in Health Act 2007 and 2010 Statutory Guidance. Report 4.1, 4.2
  • Legal: If the review is not completed before the shadow Unitary Council is established in May 2027, that body will have the power of decision-making on outstanding milestones, possibly via a Joint Committee. Report 4.3
  • Financial: The review is estimated to cost up to £140k, funded from the Strategic Initiatives Earmarked Reserve, with exact costs dependent on officer capacity and any unforeseen events. Report 5.2, 5.3, 5.4
  • Risk: Risks include the Government issuing further guidance, limited officer capacity, the pre-election period around May 2027, and difficulty securing external consultancy support. Report 6.2, 6.3, 6.4
  • Equalities: No Equality Impact Assessment was carried out as no differential impacts are anticipated. Report P42
  • Other: The review links to the Corporate Priority 'Together, create opportunities for our communities', although not directly associated with this report. Report P41

Who and where

  • Residents of the unparished area of Welwyn Garden City, including a small part of the Welwyn East ward Report 3.3
  • All residents and stakeholders within the Welwyn Hatfield borough boundary, who will be consulted Report 1.6
  • Existing Town and Parish Councils, whose May 2027 elections may coincide with any new parish arrangements Report 1.6
  • The shadow Unitary Authority due to be established in May 2027, which may inherit any unfinished decisions Report 4.3

Timeline

  • 12 March 2025: Full Council resolved to examine the merits of a Community Governance Review
  • December 2025: Consultation with Welwyn Garden City residents completed Report 1.2
  • 23 February 2026: Officer report dated and signed by the Assistant Director (Legal & Governance, Monitoring Officer) Report P43
  • 3 March 2026: Cabinet considered consultation responses and recommended the Terms of Reference and questions to Full Council Report 1.2, 1.3
  • 11 March 2026: Full Council approved the recommendations and established the Cross-Party Panel Report 2.2, P12
  • 19 May 2026: Community Governance Review formally commences; first consultation opens and Terms of Reference published Report 1.5, 2.6
  • May 2027: Scheduled elections for existing Town and Parish Councils; shadow Unitary Council expected to be established Report 1.6

Plain English for the jargon

  • Community Governance Review (CGR): A review of parish-level electoral arrangements that a principal council may carry out under the Local Government and Public Involvement in Health Act 2007.
  • Cross-Party Panel: A politically proportionate group of councillors set up to oversee the Community Governance Review and make recommendations to Full Council.
  • Shadow Unitary Council: A successor body expected to be established in May 2027 with decision-making powers ahead of local government reorganisation.
  • Terms of Reference: The key document setting out the scope, options and timetable for the Community Governance Review.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item94b

Resolved

Full Council approved: 1. The Terms of Reference; notice for publication; and consultation questions, as contained in Appendices 1, 2 and 3 respectively; 2. The Cross-Party Panel be established on the basis of the Terms of Reference as contained in Appendix 4 with Councillor membership to be determined by Group Leaders; 3. Authority was delegated to the Chief Executive, in consultation with the Cross-Party Panel, to make changes to the Terms of Reference, questions and related documents thereto prior to publication. 4. Authority was delegated to the Chief Executive to make decisions, in consultation with the Cross-Party Panel, on behalf of Council which are necessary to ... view the full minutes text for item 94b
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Council

Part I Main author: Gavin Ramtohal Not Ward Specific

WELWYN HATFIELD BOROUGH COUNCIL COUNCIL – 11 MARCH 2026 REPORT OF THE EXECUTIVE DIRECTOR FINANCE AND TRANSFORMATION

COMMUNITY GOVERNANCE REVIEW

1 Executive Summary 1.1 In light of Local Government Reorganisation, on 12 March 2025, in response to a motion to Council, Full Council resolved to instruct officers to examine and explore the merits of a Community Governance Review (CGR) with a particular focus on ensuring the continuation of local and effective representation for residents of Welwyn Garden City. Full Council also resolved that a Cross-Party Panel should be established to oversee and progress a CGR should Members agree that a CGR should commence.

1.2A consultation with residents of Welwyn Garden City completed in December 2025 and an explanation of the responses was considered at the 3 March 2026 Cabinet meeting.

1.3In summary, the residents of Welwyn Garden City indicated support for a new Parish Council. On 3 March 2026, Cabinet resolved to recommend to Full Council that the Terms of Reference and notice for publication as set out in Appendices 1 and 2 respectively should be agreed for the purposes of commencing the CGR. Cabinet also resolved to recommend to Full Council that the consultation questions, as set out in Appendix 3, should also be agreed; these questions correspond with the Terms of Reference and would be published with the same.

1.4The papers for the Cabinet recommendations can be found at Agenda Item 7f (Community Governance Review) of the Cabinet Agenda for the 3 March 2026 Cabinet meeting. Agenda for Cabinet on Tuesday 3rd March 2026, 6.30 pm – Welwyn Hatfield Borough Council

1.5In order to commence the CGR, the Council must agree the Terms of Reference. An indicative timetable is contained in the Terms of Reference which envisages completion of the process within 12 months. The timetable envisages that the process would commence on 19 May this year.

1.6The outcome of the CGR would be informed by public consultation with all residents and stakeholders within the Council’s boundary. It would be for Full Council to decide the outcome of the CGR with the benefit of recommendations from the Cross-Party Panel. Any resulting changes to the structure and/or number of Parish Councils within the Council’s administrative area may be reflected in the May 2027 scheduled elections for existing Town and Parish Councils.

2 Recommendation 2.1 That Council resolves to agree as follows:

2.2The Terms of Reference; notice for publication; and consultation questions, as contained in Appendices 1, 2 and 3 respectively, are approved.

-1- 2.3 The Community Governance Review Cross-Party Panel is established on the basis of the Terms of Reference as contained in Appendix 4 with Councillor membership to be determined by Group Leaders.

2.4Authority is delegated to the Chief Executive, in consultation with the Community Governance Review Cross-Party Panel, to make minor changes to the Terms of Reference and related documents thereto prior to publication.

2.5Authority is delegated to the Chief Executive to make decisions, in consultation with the Community Governance Review Cross-Party Panel, on behalf of Council which are necessary to ensure the process completes within the approved timetable.

2.6The process shall commence on 19 May 2026 and the Terms of Reference, first consultation questions and related documents thereto shall be published on this date.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Consultation questions 25.2.26Appendix 3 61 KB Download
PDF
Draft Terms of Reference CGR Cross-Party Panel 25.2.26Appendix 4 76 KB Download
PDF
Statutory Guidance Community Governance ReviewAppendix 5 329 KB Download
PDF
Community Governance ReviewReport 207 KB DownloadRead as text
PDF
draft terms of reference cgr 25.2.26Appendix 1 487 KB Download
PDF
draft notice of a community governance review whbc 17.2.26Appendix 2 103 KB Download

At this meeting

Whole meeting

Who was there

41 of 55 attended
EW
Emma WalkerCouncil Staff, expected
MH
Councillor Matthew HobbsCommittee Member, present
TS
Councillor Tony SkottoweCommittee Member, present
IW
Councillor Ian WalshCommittee Member, present
SA
Councillor Shirley AsareCommittee Member, present
KB
Councillor Karthik BonkurCommittee Member, apologies
KG
Councillor Katherine GardnerCommittee Member, present
SK
Councillor Salman KhanCommittee Member, apologies
LG
Councillor Leo GilbertCommittee Member, present
AB
Councillor Alex BardettCommittee Member, present
JO
Councillor Jane OtumunyeCommittee Member, present
MS
Councillor Mark ShortCommittee Member, apologies

All 55 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. Community Governance ReviewThis decision
  2. Community governance review for welwyn garden cityApproved
  3. FP2242 Community Governance ReviewAgreed

More from Welwyn Hatfield Council

All decisions
MeetingDecisionOutcome
16 Sep 2026 Community governance review for welwyn garden cityRESOLVED (Unanimously) Council resolved to approve: a) The second consultation document, frequently asked questions a... Approved Open
16 Sep 2026 Planning committees and the national scheme of delegation: constitutional updatesRESOLVED (FOR: 29, AGAINST: 0, ABSTAIN: 15) It was resolved that: a) Council notes and endorses the recommendations o... Approved Open
16 Sep 2026 Notices of motions under procedure rule 16(FOR: 29, AGAINST: 15, ABSTENTIONS:0) The amendment to the motion was approved. The motions as amended is set out bel... Approved Open
15 Jul 2026 Matters arising from the cabinetRESOLVED The Council agreed the Annual Report 2025/26 Agreed Open
21 May 2026 Election of MayorThat Councillor Michal Siewniak elected as Mayor of the Borough of Welwyn Hatfield for the municipal year 2026/27. Decided Open