Welwyn Hatfield Borough Council
Cabinet, Tuesday 24 March 2026 at 5.30pm

FP2243 Howlands House Update and Pre Construction Agreement

Agreed Executive 1 paper

AI summaryCabinet noted progress on the Howlands House affordable housing scheme and gave the Executive Director (Place) delegated authority to enter a pre-construction services agreement, with the contract value in a part II report.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedfor pre-construction services agreement
Money£10,000 estimated procurementfunded from AHP budgets
What happens nextContractor evaluation by 1 May 2026then planning submission in Q2 26/7
Who it affectsAffordable housing delivery44 dwellings planned at Howlands

What was decided

Cabinet noted the update on the progress of the Howlands House scheme. Report 2.1

Cabinet granted delegated authority to the Executive Director (Place), in consultation with the Executive Member for Housing, to enter a pre-construction services agreement for the Howlands redevelopment, to the maximum contract value set out in Part II of the report. Report 2.2

Why

Direct delivery of affordable housing across the borough remains a key strategic objective of the council's Affordable Housing Programme. Report 1.1, 1.2

The scheme is in design stage with a planning submission anticipated in Q2 26/7, and a contractor is needed to keep it moving. Report 1.3, 3.9

The procurement via the Pretium framework runs from February to early May 2026, so it is not viable to bring the appointment back to Cabinet before the elections, making delegated authority the practical option. Report 3.11, 3.13

What happens next

Preferred contractor to be determined between 23rd March 2026 and 1st May 2026 following evaluation of tender returns. Report 3.13, P33

Planning submission anticipated in Q2 26/7, subject to design and viability work. Report 3.9

A business case and viability report will be produced to assess overall financial savings from using the site for temporary accommodation instead of nightly lets. Report 6.2

The money

  • £243k Brownfield Land Release grant funding secured in March 2025 to fund demolition Report 3.7
  • £10,000 Estimated costs of procurement and obtaining costs of development, funded from the AHP budgets Report 5.1
  • £20,000 Estimated writeback of capital costs to revenue if tenders are deemed non-viable and construction does not proceed Report 6.4

Options considered

  • Chosen: Grant delegated authority to the Executive Director (Place) to appoint the contractor. To avoid unnecessary delay because the preferred contractor is determined after the Cabinet cycle and before any elections Report 3.13

Implications

  • Financial: Procurement and development cost work of around £10,000 is funded from the Affordable Housing Programme budgets. Report 5.1
  • Financial: If tenders are non-viable, up to £20,000 of capital costs would be written back to revenue. Report 6.4
  • Risk: Main project risk is scheme viability, though the Pretium Framework is PCR 2015 compliant and used nationally, which limits procurement risk. Report 6.2, 6.3
  • Legal: Cabinet has the appropriate authority to agree the recommendations under the council's constitution and Contract Procedure Rules. Report 4.1
  • Other: A comprehensive communication and engagement strategy will be created for the life of the project. Report 12.1
  • Other: No EqIA was completed at this stage; one will be prepared if the project progresses. Report 14.1

Who and where

  • Households on the council's housing waiting list and in need of temporary accommodation in the borough Report 1.1, 3.2, 3.4
  • Future residents of the Howlands redevelopment, with 44 dwellings planned (18 two-bed and 26 three-bed, with some wheelchair compliant units) Report 3.9

Timeline

  • 6th February: Cabinet received an update on the Affordable Housing Programme and approved a new 3-5 year development pipeline Report 1.2
  • March 2025: Howlands redevelopment secured £243k of Brownfield Land Release grant funding for demolition Report 3.7
  • 09th February 2026: Competition issue date for pre-construction services Report P33
  • 16th February 2026: Deadline for intend-to-submit-a-bid responses Report P33
  • 13th March 2026: Questions end date Report P33
  • 20th March 2026: Competition submission date Report P33
  • 23rd March 2026, 01st May 2026: Evaluation period for tender returns Report P33
  • Q2 26/7: Anticipated planning submission for the Howlands redevelopment Report 3.9

Plain English for the jargon

  • AHP: Affordable Housing Programme, the council's programme for direct delivery of affordable homes.
  • Pre-construction services agreement: An early-stage contract with a contractor to carry out design, costing and planning work before a main construction contract is awarded.
  • Pretium framework: A PCR 2015 compliant procurement framework used nationally by the public sector.
  • M4(3): Building regulations category for wheelchair accessible dwellings.
  • EqIA: Equality Impact Assessment, a written assessment of how a proposal affects protected groups.
  • Part II report: A confidential section of the agenda that sets out information such as contract values that is not for publication.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Resolved a) That Cabinet notes the update on the progress of Howlands House scheme. b) That Cabinet grants delegated authority to Executive Director (Place) in consultation with the Executive Member for Housing to enter a pre-construction services agreement for the Howlands redevelopment, to the maximum contract value set out in Part II of the report.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The Affordable Housing Programme continues to aspire to deliver modern high- quality homes within the Borough. The direct delivery of affordable housing across the borough remains a key strategic objective.

1.2At Cabinet on 6th February, an update was provided for the Affordable Housing Programme, and a new pipeline for development for the next 3-5 years was approved.

1.3This report provides an update on one of the sites, Howlands redevelopment, and seeks delegated authority for the appointment of contractors to ensure this scheme can progress to the next stage.

2 Recommendation(s)

2.1That Cabinet notes the update on the progress of Howlands House scheme.

2.2That Cabinet grants delegated authority to Executive Director (Place) in consultation with the Executive Member for Housing to enter a pre-construction services agreement for the Howlands redevelopment, to the maximum contract value set out in Part II of the report.

Background

3.1The Council’s five priorities as agreed by Full Council in November 2023 are set out as follows:

• Homes to be proud of

• Enable an economy that delivers for everyone

• Action on climate change

• Run an effective council

• Together, create opportunities for our communities

3.2WHBC completed 159 homes in 23/4, 139 of which were added to the Council’s stock of socially rented properties, with the remaining 20 being used by the Council as temporary accommodation for families in urgent need.

-1- 3.3 With this phase of construction completed, the attention has turned to the next phase of direct delivery for the Affordable Housing Programme and catalysing the delivery of more homes.

3.4The challenges facing the borough in relation to housing affordability, remains evident, and the council remains committed to the direct delivery of affordable housing as part of the Corporate Business Plan.

Affordable Housing Programme: next stage of delivery

3.5Whilst the delivery of the Affordable Housing Programme has been positive, the last remaining schemes in the programme are now underway, with three sites in procurement stages for a contractor and Howlands House demolished.

3.6These first tranches coupled with in the schemes that are currently progressing- Ludwick Green, Peartree, Phase 3 garage sites (Haseldine Meadows and Lockley Cresent) and Howlands house- will complete a minimum of 136 homes within the next 5 years.

Scheme name Number of Units Development stage

Ludwick Green 14 In construction

Phase 3 garage sites 11 In procurement

Peartree 42 In procurement

Howlands house 44 In design stage

Burfield 20-40 Early feasibility

3 Additional sites 25-30 (range) Early feasibility

5 year potential Total 136-147

Howland redevelopment progress:

3.7In March 2025, Howlands redevelopment secured £243k of Brownfield Land Release grant funding. This was improve the viability of the scheme, by funding a significant amount of the total required for the demolition of the site.

3.8Working with Employer’s Agent Press and Starkey, the scheme is currently in design stage with a submission for planning decision next financial year. This development will provide a purpose-built temporary accommodation facility that will assist in easing pressure on the use of short term nightly let’s.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FP2243 Howlands House Update and Pre Construction AgreementReport 212 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
AS
Councillor Astrid ScottCommittee Member, present
SB
Councillor Sandreni BonfanteVice-Chairman, present
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, in attendance
HO
Helen O'KeeffeOfficer, expected
JH
Jenny HowellOfficer, expected
MS
Michael SherryCouncil Staff, expected
CC
Clare CadeSecretary, expected
RG
Councillor Rose GrewalChair, present
GM
Councillor Gemma MooreCommittee Member, present

All 15 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. FP2243 Howlands House Update and Pre Construction AgreementThis decision
  2. Howlands House and Burfield Close Redevelopment (Forward Plan Reference FP1079)Decided
  3. Proposals for the Demolition and Reprovision of Enhanced and Increased Temporary Accommodation at Howlands House, Welwyn Garden City (Forward Plan Reference FP822)Approved

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open