Welwyn Hatfield Borough Council
Cabinet, Tuesday 9 June 2026 at 6.30pm

FP2249 Capital Financial Outturn 2025/26

Noted Executive 2 papers

AI summaryWelwyn Hatfield Cabinet notes £68.602m capital outturn for 2025/26 and approves £30.090m of budgets being rephased into 2026/27, mostly housing schemes.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBudget moved to next financial year
Money£30.090m rephased to 2026/27Of £68.602m total outturn against £101.376m budget
What happens nextSchemes continue into 2026/27Detailed breakdown in Appendix A
Who it affectsHRA and General Fund projectsHousing, leisure and infrastructure schemes

What was decided

Cabinet noted the overall capital outturn and financing for 2025/26, with £68.602m spent against a budget of £101.376m. Report 1.2, P5

Cabinet approved rephasing £30.090m of capital budgets into 2026/27, including £27.556m from the Housing Revenue Account and £2.534m from the General Fund. Report 2.3, P27

Cabinet approved the reallocation of the £5.720m Burfield budget to the Affordable Housing Programme garage sites redevelopment and new schemes. Report P38

Why

Re-phasing was needed because many projects were not finished in 2025/26, including the Howard House redevelopment (£9.212m), Burfield (£5.720m), and Howlands House (£2.481m). Report 2.6, 2.7, P36, P37, P38, P50

There was a £6.789m adverse variance on Major Repairs because of historic uncharged works, a backlog of void works, and higher than expected inflation. Report 2.7, P41

Spending on Door Entry Systems was significantly lower than budgeted due to contractor delays, producing a £1.710m favourable variance. Report P46, P47

What happens next

Officers will look for schemes able to use the £0.200m of Section 106 funding earmarked for rugby improvements. Report P32

A procurement process will begin in 2026/27 for Howlands House before works can start on site. Report P37

Resident engagement for Kingsdale House works will start once the pre-election period is over. Report P45

The money

  • £101.376m Current approved capital budget for 2025/26 Report 1.2, P14
  • £68.602m Capital outturn position for 2025/26 Report 1.2, P25
  • £30.090m Total net re-phasing into 2026/27 Report 2.3, P27
  • £27.556m HRA re-phasing into 2026/27 Report 2.3, P27
  • £2.534m General Fund re-phasing into 2026/27 Report 2.3, P27
  • £9.212m Rephasing for Howard House redevelopment Report P50
  • £6.789m Adverse variance on Major Repairs Report P41
  • £5.720m Rephasing of AHP Burfield budget Report P38
  • £3.922m Rephasing for Insulation Improvements Report P43

Options considered

  • Chosen: Note the capital outturn position and financing for 2025/26 Report P5
  • Chosen: Approve re-phasing of budgets into 2026/27 as detailed in Appendix A Report P6

Implications

  • Financial: Capital reserves balance for the General Fund at year end is £3.854m, £2.491m lower than budgeted. Report P56
  • Equalities: No Equality Impact Assessment was carried out as the recommendations do not directly affect services. Report P73
  • Climate: Less decarbonisation work was completed than planned due to reduced grant available, with £1.800m rephased into 2026/27. Report P52
  • Legal: No direct legal implications arise from the report, though individual projects will need legal input into procurement and contracts. Report P71
  • Risk: No risk management implications arise directly from the report. Report P70

Who and where

  • Housing Revenue Account tenants and residents, through delays to the Howard House redevelopment, Major Repairs, Insulation Improvements and Decarbonisation works Report P41, P43, P50, P52
  • Hatfield Town Council, as lead on football development at Birchwood Leisure Centre using rephased Section 106 funding Report P32
  • Affordable housing delivery partners, with the Burfield budget reallocated to the garage sites redevelopment and new schemes Report P38
  • Council tax and rent payers, as the cumulative borrowing position changes from the original plan Report P55, P57

Timeline

  • 2025/26: Demolition and disconnection works completed at Howlands House, with redesign submitted for planning Report P37
  • 2025/26: Contract signed for Howard House redevelopment, project now in pre-construction stage Report P51
  • 2025/26: Work on Corners completed under Major Repairs (Other Contractors) Report P45
  • 2025/26: Chilton Green and The Green sheltered refurbishment schemes completed Report P49
  • 2026/27: Procurement process for Howlands House before works can begin on site Report P37
  • 2026/27: Most of the Howard House redevelopment works scheduled to take place Report P51
  • 2026/27: Kingsdale House works to go through planning and consultation after pre-election period Report P45

Plain English for the jargon

  • Capital outturn: The actual amount spent on capital projects at the end of the financial year, compared to the budget
  • Re-phasing: Moving budget from one financial year to the next because a project will not be completed in time
  • HRA: Housing Revenue Account, the ring-fenced account that records income and spending on council housing
  • Section 106 funding: Money paid by developers to a council for local infrastructure or services, tied to planning permission
  • Minimum Revenue Provision (MRP): The minimum amount a council must set aside each year from revenue to repay past capital borrowing
  • Decarbonisation HRA: Works to reduce carbon emissions from council housing, partly funded by government grants
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23

Resolved

RESOLVED Cabinet resolved to: a) Note the overall capital outturn position and financing for 2025/26 b) Approve the re-phasing of budgets into 2026/27 as detailed in Appendix A of the report.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report presents the capital expenditure and associated capital funding as at the end of March 2026. The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery.

1.2The current approved capital budget is £101.376m (which includes the approved re- phasing of budgets from 2024/25) and the outturn position (including proposed re-phasing of budgets into 2026/27) is £68.602m. A summary of variances to budget and re-phasing is shown in Table 1 and detailed explanations for key variances in Section 2.4.

1.3The capital financing outturn table showing how the capital programme has been funded is set out in Section 3 of this report.

Recommendations

It is recommended that Cabinet:

a. Note the overall capital outturn position and financing for 2025/26.

b. Approve the re-phasing of budgets into 2026/27 as detailed in Appendix A.

2. Capital Programme – Outturn Position Capital Budgets

2.1The following table tracks approved changes to the original budget during the year (excluding fully funded virements). 09 June 2026 Agenda Item No. 7c £

Original Budget £55.990m

Re-phasing from 2024/25 £29.199m

Additional budget for Gatehouse purchase £15.700m

Additional budget for Outdoor Energy Gym £0.020m

Additional budget for Food Waste Recycling Project £0.793m

Removal of incorrect roll-forwards from 24/25 (Hatfield Town Centre (£0.326m) Public Realm, Play Area Replacement Scheme and Hatfield Town Centre Market Place) Current Budget £101.376m

2.2The capital outturn position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies.

Table 1: Capital Outturn 2025/26 By Fund and Directorate

Re- Outturn phasing (Under)/ Budget Outturn Variance of Over 2025/26 2025/26 to Capital Budget Budget Schemes

£'000 £'000 £'000 £'000 £'000

General Fund Executive Director (Finance and Transformation) 229 165 (64) 0 (64)

Executive Director (Place) 18,652 16,999 (1,654) 1,716 62

Executive Director (Resident Services and Climate Change) 2,820 1,237 (1,583) 818 (765)

General Fund Total 21,701 18,401 (3,300) 2,534 (766) Housing Revenue Account

Executive Director (Place) 17,690 5,265 (12,425) 10,995 (1,430)

Executive Director (Resident Services and Climate Change) 61,985 44,937 (17,048) 16,561 (487) 09 June 2026 Agenda Item No. 7c Housing Revenue Account Total 79,675 50,202 (29,473) 27,556 (1,917)

Grand TOTAL 101,376 68,602 (32,773) 30,090 (2,683)

2.3There is re-phasing of £30.090m into 2026/27, split between funds as follows:

HRA £27.556m – re-phase budget into 2026/27 General Fund £2.534m – re-phase budget into 2026/27 Total net re-phasing - £30.090m

2.4Key outturn variances (over £1m) are outlined below:

GENERAL FUND REPHASING £2.534m

Executive Director (Place) rephasing £1.716m

2.5£1.000m rephasing – Angerland Football and Rugby Schemes (App A ref. nos 10 & 11)

This is Section 106 funding earmarked for football and rugby improvement schemes. £0.800m of this funding is earmarked for football improvement schemes and it has been agreed that this funding will be used to fund football development at Birchwood Leisure Centre via Hatfield Town Council. Hatfield Town Council are in the process of appointing a project manager to lead the scheme and applying for planning permission and it is therefore proposed that the entire budget of £0.800m is rephased into 2026/27. £0.200m of this funding is earmarked for rugby improvement schemes. As there are no schemes currently planned, it is proposed that the entire budget of £0.200m is rephased into 2026/27. Schemes which can use this funding will continue to be looked for.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2526 Outturn Capital MonitorAppendix A 170 KB Download
PDF
FP2249 Capital Financial Outturn 2025/26Report 233 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
AS
Councillor Astrid ScottCommittee Member, present
SB
Councillor Sandreni BonfanteVice-Chairman, present
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, expected
RB
Richard BakerOfficer, expected
HO
Helen O'KeeffeOfficer, expected
JH
Jenny HowellOfficer, expected
MS
Michael SherryCouncil Staff, expected
CC
Clare CadeSecretary, expected
RG
Councillor Rose GrewalChair, present
GM
Councillor Gemma MooreCommittee Member, present

All 15 on the meeting page

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open