Approved Planning 4 papers

Planning Committee approved this item on Tuesday 21 June 2016. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

RESOLVED A. That the under-mentioned planning applications be approved subject to the conditions in the report:- 2015/1224/FUL; 0563/FUL B. That in respect of planning application 2014/1361/FUL relating to Hangar C2 to C4 Tollgate Road, Burscough:- (i) That the decision to grant planning permission be delegated to the Director of Development and Regeneration in consultation with the Chairman or Vice-Chairman of the Planning Committee subject to a planning obligation being entered into under Section 106 of the Town and Country Planning Act requiring:- An agreement to relinquish the use of Barton Farm, Moss Lane, Burscough as a knacker yard in perpetuity in line with an agreed timetable. (ii) That any planning permission granted by the Director of Development and Regeneration pursuant to recommendation (i) above be subject to the conditions as set down on pages 114 to 119 of the Book of Reports and with the additional conditions as set out below:- Condition No. 22 Externally mounted ancillary plant, equipment and servicing shall be selected and/or acoustically treated in accordance with a scheme designed so as to achieve a rating level of 5dB (LA eq ) below the typical background (LA 90 ) level at the boundary of Boundary House, Pippin Street, Burscough. All measurements and assessment shall be done in accordance with BS4142:2014. Reason To safeguard the amenity of adjacent properties and the area generally and so comply with the provisions of Policy GN3 in the adopted West Lancashire Local Plan 2012-2027 Development PIan Document. Condition No.23 Prior to the knackers yard being brought into use, the existing Pippin Street access shall be permanently closed in accordance with a scheme that has been submitted to and approved in writing by the Local Planning Authority. Reason In the interests of highway safety and in compliance with Policy GN3 of the West Lancashire Local Plan 2012-27. C. That in respect of planning application 2015/0733/FUL relating to Grove Farm, High Lane, Ormskirk:- (i) That the decision to grant planning permission be delegated to the Director of Planning and Regeneration in consultation with the Chairman or Vice-Chairman of the Planning Committee subject to the applicant entering into an obligation under S.106 of the Town and Country Planning Act 1990 to secure the provision of: Affordable housing at 20% intermediate tenure but subject to re-appraisal. The provision and maintenance of the public open space. Appropriate sustainable travel measures. Funding for Pine Grove link. (ii) That any permission granted by the Director of Development and Regeneration pursuant to recommendation (i) above be subject to the conditions as set down on pages 175 to 184 of the Book of Reports but subject to the amendments to the conditions as set out on pages 202 to 203 of the late Information and the additional conditions on pages ... view the full minutes text for item 15.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Planning Committee

AGENDA ITEM:

PLANNING COMMITTEE: 21ST JUNE 2016

Report of: Director of Development and Regeneration

Contact: [name removed] (Extn.5134) Email: [email protected]

SUBJECT: ADDITIONAL LATE INFORMATION

1.0INTRODUCTION

The information below has been received since compilation of your Agenda. The following also includes suggested adjustments to the recommendations further to the receipt of late plans and/or information.

2.0ITEM 7 – PLANNING APPLICATIONS

REPORT NO. 3 - LAND NORTH OF JUNCTION WITH PIPPIN STREET, LIVERPOOL ROAD SOUTH, BURSCOUGH

Condition 4 should be amended to read:

The development shall be implemented in strict accordance with the details of levels, including the finished floor levels of all buildings, as indicated by the approved plans.

REPORT NO. 6 – GROVE FARM, HIGH LANE, ORMSKIRK

Consultation Response

LCC Highways have provided further comments on the need for the proposed roundabout at the Burscough Road/County Road/High Lane junction. They advise that:

The A59 High Lane/B5319 Burscough Road/A59 County Road junction operates well at the current time and does have some spare capacity to deal with additional development traffic. However, there is a large volume of additional

1 traffic that is expected to be using this junction as a result of committed but not yet constructed/occupied developments, as well as the traffic generated by the proposed Grove Farm development. These committed developments include: - 2012/1224/OUT – 86 Dwellings off Liverpool Road South, Abbey Lane, Burscough - 2012/0080/FUL – Proposed Mixed use development comprising Class A1 foodstore, 4 non-food retail units, offices, vehicle showroom and workshop, restaurant, ambulance station and security lodge, Pippin Street, Burscough (when traffic flow data was collected, for junction capacity assessment, this site had not yet been occupied) - 2015/0171/OUT – 580 dwellings, Extra Care or Care Accommodation, a Local Centre (500m2); 4.6 hectares of Employment Development (up to 13,800m2 of B1, B2 and B8 floorspace), Yew Tree Farm, Liverpool Road South, Burscough

When junction analysis is carried out for a scenario in 2027 where all the above developments have been constructed and occupied the maximum queue for drivers turning right from B5319 Burscough Road to A59 High Lane, in the PM peak period, increases to 29 vehicles and a delay of 344 seconds (5 minutes and 44 seconds) from the present situation where queues do not form. When traffic from the proposed Grove Farm development is added on to this the maximum queue increases to 61 vehicles and the delay increases to 706 seconds (11 minutes and 46 seconds).

As the above analysis assumes that there is no queue already present the start of the PM peak period, it does not reflect a worst case scenario. It should also be noted that the above future scenarios do not include any traffic that would be generated by developments within the safeguarded land of the Yew Tree Farm Masterplan, such as the already submitted Meadowbrook application (2016/0516/FUL).

LCC accident data indicates that over the last 6 years there have been 5 road traffic collisions at the A59 High Lane/B5319 Burscough Road/A59 County Road priority junction. These collisions involved a total of 7 vehicles and resulted in 8 injuries to adults, 1 of which was classed as serious.

As well as the obvious issues of increased journey times, this additional delay also raises a significant safety concern. Drivers subjected to large delays in trying to exit B5319 Burscough Road on to the A59 will be frustrated. This often leads to drivers becoming impatient and making higher risk turning manoeuvres into smaller gaps in passing traffic, thereby increasing the risk of a collision.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ADDITIONALLATEINFORMATIONJUNE2016Report 233 KB DownloadRead as text
PDF
Cttee Report Plans 21-06-16Plan 1.6 MB Download
PDF
LATEINFORMATIONJUNE2016Report 238 KB Download
PDF
Planning ApplicationsReport 718 KB Download

At this meeting

Whole meeting

Who was there

15 of 15 attended
GO
Councillor Gaynar OwenVice-Chairperson, present
IA
Councillor Iain AshcroftCommittee Member, present
MP
Councillor Mrs Pam BaybuttCommittee Member, present
DM
Councillor David McKayCommittee Member, present
CM
Councillor Charles MarshallCommittee Member, present
MN
Councillor Maureen NixonCommittee Member, present
DO
Councillor David O'TooleCommittee Member, present
RP
Councillor Robert PendletonCommittee Member, present
EP
Councillor Edward PopeCommittee Member, present
MM
Councillor Mrs Marilyn WestleyCommittee Member, present
GD
Councillor Gareth DowlingChairperson, present
CC
Councillor Claire CooperCommittee Member, present

All 15 on the meeting page

On this subject at West Lancashire

Search all
  1. Planning ApplicationsThis decision
  2. Procedure for the Public and Applicants who wish to speak at the Planning Committee on Planning Applications that might affect themDecided
  3. Planning ApplicationsApproved
  4. Planning ApplicationsDeferred
  5. Planning ApplicationsApproved
  6. Planning ApplicationsApproved

More from West Lancashire Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 MINUTESThat the minutes of the meeting held on the 30 th July 2026 be approved as a correct record and signed by the Chairpe... Approved Open
3 Sep 2026 2025/0548/FUL - Burscough Methodist Church, Orrell Lane, Burscough, L40 0SGAGREED: That planning application 2025/0548/FUL be deferred until a sufficient number of eligible Members are present... Agreed Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 18 th June 2026 be approved as a correct record and signed by the Chairman. Approved Open
30 Jul 2026 2025/1054/COU - Former Forest View NurseriesThat planning permission is granted subject to conditions set out on pages 65 - 66 of the Public Reports Pack for the... Decided Open
30 Jul 2026 2026/0229/FUL - Land West of Red Cat LaneThat planning application 2026/0229/FUL be granted subject to a deed of variation to the original Section 106 Agreeme... Agreed Open