RESOLVED (A) That the Director of Leisure and Environment be given delegated authority to formally accept the offer of a of up to £982,000, to be used in the Tawd Valley Park Project, and to take all necessary steps to comply with the terms of the Grant. (B) That call-in is not appropriate for this report as the matter is one requiring urgent action. After consideration of this item business was suspended due to disturbance by the public.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To seek delegated authority to accept an offer of external funding from the Water Environment Grant scheme operated by The Environment Agency and Natural England, to be used for the development of Sustainable Urban Drainage Systems (SUDS) in Tawd Valley Park ("the Grant").
Recommendations
2.1That the Director of Leisure and Environment be given delegated authority to formally accept the offer of a Water Environment Grant of up to £982,000, to be used in the Tawd Valley Park Project, and to take all necessary steps to comply with the terms of the Grant.
2.2That call-in is not appropriate for this report as the matter is one requiring urgent action.
Background
3.1In 2017 Council approved a Masterplan looking at environmental and recreational improvements in Tawd Valley Park, Skelmersdale.(Cabinet Report:Tawd Valley Park Masterplan – 7th Nov 2017). The Masterplan looked at various ways in which we can provide new and improved recreational facilities, but also looked at ways of improving the local environment, including the water quality of the River Tawd. 3.2 The River Tawd suffers from diffuse urban pollution the source of which is difficult to access due to tributaries being culverted, therefore we concentrated on investigating end-of pipe solutions. With the support of the Environment Agency who provided funding of £15,000 to engage consultants to look at this issue, a study was undertaken. (Water Quality Options for Tawd Valley Park – May 2017)
3.3The remit of this study was to improve the overall water quality of the River Tawd with particular emphasis on Tawd Valley Park, in order to create a family friendly public park providing a healthy environment with enhanced environmental habitats and increased amenity value
3.4The first part of this study looked at the hydrology of the valley, assessed pollution sources, identified Sustainable Urban Drainage System (SUDS) opportunities, prioritised options, and shortlisted 5 priority locations. This number was subsequently reduced to 4 with the withdrawal of a site due to its proximity to the proposed Skelmersdale Town Centre development, and its high proposed costs. (see Appendix 1 – Proposed SUDS Locations in Tawd Valley Park).
3.5The SUDS would be in the form of wetlands or ponds and would work by slowing the flow of water providing natural water treatment and flood management before the water is discharged into the river Tawd.
3.6A further study was then undertaken to look at the prioritised SUDS and produce more detailed designs for each one, and full costings for their construction. Overall the cost of the construction of the 4 SUDS, including project management fees, totalled £982,000. (Tawd Valley Park Masterplan - High Level Design Report – July 2017).
3.7The 4 prioritised SUDS were incorporated within the Tawd Valley Masterplan which was approved by Council in November 2017.
4.0CURRENT POSITION
4.1The Water Environment Grant (WEG) scheme provides funding to improve the water environment in rural England. It is managed by the Environment Agency and Natural England and is part of the Rural Development Programme for England, on behalf of the Department of the Environment, Farming, and Rural Affairs ( DEFRA).
4.2In May 2017 the Council made a bid to the WEG for £982,000 to enable it to implement the SUDS scheme as part of the Tawd Valley Park masterplan.
4.3In September 2018 it is hoped that an offer will be made to the Council from the WEG to implement this scheme. One of the conditions of any offer is that the funders would require a formal acceptance within 30 days of the offer being made. 5.0 ISSUES
5.1In accepting the Grant the Council must comply and be able to comply with the terms and conditions of the Grant. The terms and conditions include the following:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.