RESOLVED A. That the newly developed Asset Management Strategy included at appendix A to the report be approved. B. That in order to deliver the Asset Management Strategy and realise economies of scale and continuity, the procurement of the housing capital investment programme starting from April 2021 for a term of 5 years to maximise value for money and flexibility be approved.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To seek approval from Cabinet/Council of the newly developed Housing and Inclusion Asset Management Strategy (AMS) including an ability to enter into a 5 year contract(s) to deliver the capital investment programme commencing April 2021.
2.0RECOMMENDATIONS TO CABINET
2.1That the newly developed Asset Management Strategy included as appendix A be approved.
2.2That in order to deliver the Asset Management Strategy and realise economies of scale and continuity, the procurement of the housing capital investment programme starting from April 2021 for a term of 5 years to maximise value for money and flexibility be approved.
3.0RECOMMENDATION TO EXECUTIVE OVERVIEW & SCRUTINY COMMITTEE
3.1That following consideration of the report any agreed comments be submitted to Council.
4.0RECOMMENDATIONS TO COUNCIL
4.1That the Housing Asset Management Strategy be approved and implemented.
4.2That the procurement of a 5 year contract to deliver the Housing and Inclusion Capital Investment Programme be approved.
4.3That further approval will be sought from Cabinet / Council should officers wish to utilise the contract extension options included within the contract.
Background
5.1In order to ensure the long term sustainability of the Councils housing stock/ business plan, Officers have developed a new AMS which provides a framework to ensure the Council make good investment decisions for the housing stock. The AMS will deliver individual 5 year area investment plans which will be shaped by robust intelligence along with the invaluable knowledge from the various teams within the Housing and Inclusion service. The AMS for consideration is included as appendix A.
5.2Procurement for the capital investment programme has been on a year by year basis since 2017/18. This was an interim arrangement while stock condition data was being analysed and the asset management strategy developed. In order deliver the 5 year investment plans officers now plan to procure longer term contract(s) which will realise economies of scale and continuity which will also facilitate increasing the social value of our contracts such as, increased training opportunities through the development of a social enterprise models which could potentially benefit the whole borough, developing/utilising local supply chains and utilising local educational institutions. This duration of contract will also have the added benefit of removing the need to procure on an annual basis freeing up officer time to enable greater focus on contract management and quality assurance.
6.0CURRENT POSITION
6.1Officers are procuring the 2019/2020 capital programme using a mixture of open tender and frameworks and a similar procurement route is proposed for the 2020/21 capital programme. From April 2021 it is proposed a 5(+3,+2) year contract(s) will commence to deliver the asset management strategy. It is anticipated that these contracts will be broader in scope to ensure specifications and quality standards are aligned with those contained within the new Responsive Maintenance and Void contracts, ensuring standardisation of components across the housing stock is achieved.
6.2In addition to standardising components and quality standards, contracts will be structured in a way that allows flexibility for change which will allow option appraisal recommendations to be implemented without contractual penalties.
7.0SUSTAINABILITY IMPLICATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.