RESOLVED A. That a commercial photovoltaic (PV) system be installed at the West Lancashire Investment Centre. B. That call-in is not appropriate for this item as the matter is one where timely action is required in order that installation can take place before the worst of the winter weather and panels can be energy producing so serving to help reduce operating costs as soon as possible. Furthermore the current availability of an experienced management resource/project lead is time limited.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To seek consent for the installation of a commercial photovoltaic (PV) system at West Lancashire Investment Centre serving to harness a green energy source to reduce operating costs.
Recommendations
2.1That, a commercial photovoltaic (PV) system be installed at the West Lancashire Investment Centre.
2.2That Call-in is not appropriate for this item as the matter is one where timely action is required in order that installation can take place before the worst of the winter weather and panels can be energy producing so serving to help reduce operating costs as soon as possible. Furthermore the current availability of an experienced management resource/project lead is time limited.
Background
4.1West Lancashire Investment Centre was completed in December 2004 and provides accommodation for 31 small and medium sized businesses in a two storey office building across c.47,000 sq ft. 4.2 The Centre was developed with £5 million North West Development Agency and European Regional Development Funding and currently generates rental income of £320,000 per annum.
4.3As at 6 June 2019 the Centre’s reserve fund stood at £269,000 plus £33,000 in the sinking fund, the latter funded from the service charge levied on the tenants.
4.4Consideration has previously been given to the installation of a PV system at the Centre but this was never progressed due to a number of factors including resource availability.
5.0CURRENT POSITION
5.1During the financial year 2018 – 2019 electricity costs for the Investment Centre amounted to £100,679.08.
5.2Studies most recently undertaken show the following benefits are to be gained from the installation of a PV system at the Centre:
• Utility bill savings. • Move towards grid independence. • Affords protection against rising electricity prices. • Improves the Centre’s Energy Performance Certificate (EPC) rating. • Reduces carbon footprint. • Positively demonstrates the Council’s green environmental approach to the public, particularly tenants of the Investment Centre and their visitors. • Offers reliable, low maintenance technology.
5.3An analysis by a specialist company, Procure Plus, has estimated that if there was a simulated energy price increase of 5% per annum then there would be a payback period for the proposed system of 7.7 years.
In summary:
Generation Output (kWh) 62,811kWh/year Year 1 Electricity Savings £8,402.39 based on a day-rate electricity cost of 13.03p/kWh Return on Investment £279,462.17 Over 25 years
5.4From the outset the Investment Centre has sought to be a “leading edge“ facility, championing sustainable development and adopting an environmentally friendly approach. PV installation would support this stance.
6.0SUSTAINABILITY IMPLICATIONS
6.1Implementation of the proposal will result in reduced dependency on the national electricity grid for the Investment Centre, reducing its carbon footprint and improving efficiencies while further positively demonstrating the Council’s green environmental approach and supporting its aspiration to be carbon neutral by 2030.
6.2There is no significant impact on crime and disorder.
7.0FINANCIAL AND RESOURCE IMPLICATIONS
7.1According to the conditions attached to the funding secured for the development of the Investment Centre, any operational surplus generated must be ring fenced and held in a reserve account to be used for economic regeneration in the area. The expected financial cost of this project of £79,000 will therefore be met using existing resources from this ring fenced account.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.