West Lancashire Borough Council
Cabinet, Wednesday 16 October 2019 at 6.30pm

Installation of a commercial photovoltaic (PV) system at West Lancashire Investment Centre

Decided Executive 1 paper

Cabinet decided this item on Wednesday 16 October 2019. Below is the council's own wording, with the papers it was decided on.

Item48

Resolved

RESOLVED A. That a commercial photovoltaic (PV) system be installed at the West Lancashire Investment Centre. B. That call-in is not appropriate for this item as the matter is one where timely action is required in order that installation can take place before the worst of the winter weather and panels can be energy producing so serving to help reduce operating costs as soon as possible. Furthermore the current availability of an experienced management resource/project lead is time limited.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1To seek consent for the installation of a commercial photovoltaic (PV) system at West Lancashire Investment Centre serving to harness a green energy source to reduce operating costs.

Recommendations

2.1That, a commercial photovoltaic (PV) system be installed at the West Lancashire Investment Centre.

2.2That Call-in is not appropriate for this item as the matter is one where timely action is required in order that installation can take place before the worst of the winter weather and panels can be energy producing so serving to help reduce operating costs as soon as possible. Furthermore the current availability of an experienced management resource/project lead is time limited.

Background

4.1West Lancashire Investment Centre was completed in December 2004 and provides accommodation for 31 small and medium sized businesses in a two storey office building across c.47,000 sq ft. 4.2 The Centre was developed with £5 million North West Development Agency and European Regional Development Funding and currently generates rental income of £320,000 per annum.

4.3As at 6 June 2019 the Centre’s reserve fund stood at £269,000 plus £33,000 in the sinking fund, the latter funded from the service charge levied on the tenants.

4.4Consideration has previously been given to the installation of a PV system at the Centre but this was never progressed due to a number of factors including resource availability.

5.0CURRENT POSITION

5.1During the financial year 2018 – 2019 electricity costs for the Investment Centre amounted to £100,679.08.

5.2Studies most recently undertaken show the following benefits are to be gained from the installation of a PV system at the Centre:

• Utility bill savings. • Move towards grid independence. • Affords protection against rising electricity prices. • Improves the Centre’s Energy Performance Certificate (EPC) rating. • Reduces carbon footprint. • Positively demonstrates the Council’s green environmental approach to the public, particularly tenants of the Investment Centre and their visitors. • Offers reliable, low maintenance technology.

5.3An analysis by a specialist company, Procure Plus, has estimated that if there was a simulated energy price increase of 5% per annum then there would be a payback period for the proposed system of 7.7 years.

In summary:

Generation Output (kWh) 62,811kWh/year Year 1 Electricity Savings £8,402.39 based on a day-rate electricity cost of 13.03p/kWh Return on Investment £279,462.17 Over 25 years

5.4From the outset the Investment Centre has sought to be a “leading edge“ facility, championing sustainable development and adopting an environmentally friendly approach. PV installation would support this stance.

6.0SUSTAINABILITY IMPLICATIONS

6.1Implementation of the proposal will result in reduced dependency on the national electricity grid for the Investment Centre, reducing its carbon footprint and improving efficiencies while further positively demonstrating the Council’s green environmental approach and supporting its aspiration to be carbon neutral by 2030.

6.2There is no significant impact on crime and disorder.

7.0FINANCIAL AND RESOURCE IMPLICATIONS

7.1According to the conditions attached to the funding secured for the development of the Investment Centre, any operational surplus generated must be ring fenced and held in a reserve account to be used for economic regeneration in the area. The expected financial cost of this project of £79,000 will therefore be met using existing resources from this ring fenced account.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Installation of a commercial photovoltaic (PV) system at West Lancashire Investment CentreReport 549 KB DownloadRead as text

At this meeting

Whole meeting
45PUBLIC SPEAKINGOn the agenda
48Installation of a commercial photovoltaic (PV) system at West Lancashire Investment CentreThis decision
49EXCLUSION OF PRESS AND PUBLICDecided 51Skelmersdale Town Centre RedevelopmentPrivate

Who was there

7 of 27 attended
IM
Councillor Ian MoranLeader of the Council, present
YG
Councillor Yvonne GagenDeputy Leader of the Council, present
DE
Councillor David EvansCommittee Member, present
JW
Councillor Jenny WilkieCommittee Member, present
KW
Councillor Kevin WilkieCommittee Member, present
KW
Councillor Kevin WrightCommittee Member, present
AY
Councillor Adam YatesCommittee Member, present
KW
Kim WebberOfficer, in attendance
JH
John HarrisonOfficer, in attendance
JS
Jacqui Sinnott-LaceyOfficer, in attendance
HM
Heidi McDougallOfficer, in attendance
TB
Terry BroderickOfficer, in attendance

All 27 on the meeting page

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies