Resolved

RESOLVED A. That the progress made in relation to the management of the risks shown in the Key Risks Register (Appendix A to the revised report) be noted and endorsed. B. That the updated Risk Management Policy (Appendix B to the revised report) be approved.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Risk Management Policy

1 1.0 Introduction

Risk is a part of everyday life. The Authority recognises that there are risks involved in everything it does and that it has a duty to manage these risks. This duty is to employees, residents and people working in the Borough, service users, partners and other stakeholders.

The Authority defines risk as the possibility that an action or event will adversely or beneficially affect its ability to achieve its planned objectives. The effective identification, assessment, control, monitoring, management and reporting of risk will help to ensure that:

 Planned objectives are more likely to be achieved

 Opportunities are recognised

 Adverse risks are less likely to happen

 The impact of adverse risks which are realised is reduced

Effective risk management is therefore regarded as a critically important part of the work of the Authority.

This policy aims to ensure that we have a planned and systematic approach to identify, evaluate, control and manage the whole range of risks and opportunities facing the Authority. This policy also informs the approach to the Risk Management framework which is the established process by which the Authority identifies, assesses and manages risk in order that it should succeed in its planned objectives.

2.0Aims of the Risk Management Policy

The Risk Management Policy has the following aims and objectives:

 To integrate Risk Management into the culture of the Authority

 To raise awareness of the need for Risk Management with all those connected with the delivery of services

 To enable the Authority to anticipate and respond to changing social, environmental and legislative conditions

 Minimisation of injury, damage, loss and inconvenience to residents, employees, service users, assets etc. arising from or connected with the delivery of Council services

 To maximise the rewards that can be gained through risk management

2  To maintain and develop a robust framework and procedures for the identification, analysis, assessment, control and management of risk

 To assist in the achievement of the Council's vision to be a Council which is ambitious for West Lancashire

 To aid the achievement of the Council's priorities

3.0Risk Assessment

Risk arises naturally and directly from the implementation of corporate and service aims and objectives. Therefore risk assessment is an integral part of all Council activity. It is the Authority’s policy that all substantive activities should be subject to risk assessment. This includes all significant projects, for example, financial developments, legislative developments, human resource initiatives, health and safety, communication upgrades, partnerships and IT developments. Risks must be regularly monitored and actively managed until the objectives have been achieved (or the risk realised).

Risks should be assessed using the standard approach set out at the end of this policy. This requires the impact and likelihood of a risk to be evaluated and then scored on a risk matrix. This score then determines the level of concern associated with that risk and the action that is required to be taken. The Authority’s risk appetite is determined by Cabinet and can be defined as the level of risk that the Authority is willing to take in pursuit of its objectives and values.

4.0Service Risk Registers

Heads of Service are responsible for ensuring that all significant risks are included in Service Risk Registers using the Pentana Risk system. This risk register should describe the risk event, identify who the risk has been assigned to and who is responsible for managing the risk, planned and completed actions, potential effects, internal controls and a current and target risk assessment. Risk events should be deactivated when the objective has been reached (or the risk realised) and new risk events added as soon as they are identified.

Advice on completing service risk registers is available to officers via the Council's Intranet Risk Management Page.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Key Risk RegisterAppendix A 176 KB Download
PDF
Key Risk Register 2Appendix A 178 KB Download
PDF
Risk Management Policy: March 2020Appendix B 286 KB Download
PDF
RM Policy: March 2020: Tracked changes 2Report 286 KB DownloadRead as text
PDF
Risk Management Report: Cabinet March 2020 2Report 138 KB Download
PDF
Risk Management ReportReport 138 KB Download

At this meeting

Whole meeting

Who was there

7 of 27 attended
PW
Pat WrightCouncil Staff, expected
IM
Councillor Ian MoranLeader of the Council, present
YG
Councillor Yvonne GagenDeputy Leader of the Council, present
DE
Councillor David EvansCommittee Member, present
JW
Councillor Jenny WilkieCommittee Member, present
KW
Councillor Kevin WilkieCommittee Member, present
KW
Councillor Kevin WrightCommittee Member, present
AY
Councillor Adam YatesCommittee Member, present
JS
Jacqui Sinnott-LaceyOfficer, in attendance
HM
Heidi McDougallOfficer, in attendance
CT
Chris TwomeyOfficer, absent
MT
Marc TaylorOfficer, absent

All 27 on the meeting page

On this subject at West Lancashire

Search all
  1. Risk Management ReportThis decision
  2. Risk Management - Annual Report 2024/25Approved
  3. Risk management framework & key risk reportDecided
  4. Risk management framework & key risk reportNoted
  5. Risk Management Framework Update & Key Risk RegisterNoted
  6. Risk Management Framework Update & Key Risk RegisterNoted

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open