A That the Council's performance against the indicator set for the quarter period ended 31 March be noted. B That the call-in procedure is not appropriate for this item as the report will be submitted to the meeting of the Corporate and Environmental Overview and Scrutiny Committee on 11 June 2020.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To present performance monitoring data for the quarter ended 31 March 2020.
2.0RECOMMENDATIONS TO CABINET
2.1That the Council’s performance against the indicator set for the quarter ended 31 March 2020 be noted.
2.2That the call-in procedure is not appropriate for this item as the report will be submitted to the meeting of the Corporate & Environmental Overview & Scrutiny Committee on 11 June 2020.
3.0RECOMMENDATIONS TO CORPORATE & ENVIRONMENTAL OVERVIEW & SCRUTINY COMMITTEE
3.1That the Council’s performance against the indicator set for the quarter ended 31 March 2020 be noted.
4.0CURRENT POSITION
4.1Members are referred to Appendix A of this report detailing the quarterly performance data for key performance indicators. The performance information aims to help demonstrate performance against the corporate priorities as well as providing some service-specific information.
4.2The suite of indicators for 2019/20 includes the quarterly indicators provided in Appendix A.
4.3There are 47 items reported. Seven of these are data only. Of the 40 PIs with targets reported: • 26 indicators met or exceeded target • 5 indicators narrowly missed target • 9 were 5% or more off target.
A direct comparison with the same quarter of the previous year is not possible due to changes in indicators and targets, however performance in Q4 2018/19 gave 22 (from 33) performance indicators on or above target at that time.
4.4Within Environmental Services, data agreed for reporting in 2019/20 has had to be revised in line with access to collection mechanisms available. The proposed PIs were based on the understanding at the time of what would be reported through new external benchmarking reports and Service Now. The revisions are close to the original expectations as explained for the Q2 report.
4.5Performance plans prepared by service managers are already in place for those indicators where performance falls short of the target by 5% or more for this quarter. These plans provide the narrative behind the outturn. Progress on actions from previous Performance Plans where indicators are no longer red are provided in Appendix C.
4.6Although the purpose of this report is to comment on quarterly information, where available, a brief reference on draft annual performance is also given in Appendix A.
4.7This quarterly suite of indicators and targets was agreed as part of a suite of indicators by Cabinet in March 2019. Targets for 2019/20 were finalised through Cabinet following consideration of comments from the Executive Overview and Scrutiny Committee. Performance against the full corporate suite of indicators 2019/20 will be reported within the Council Plan Annual Report.
5.0FUTURE PERFORMANCE REPORTING
5.1As referred to in Item 6f Council Plan and Corporate Performance Review in March's Cabinet papers, corporate performance information is being reviewed. This has previously been agreed as an Annual Suite with key indicators reported quarterly to Members following the same format and process that was in place for the now discontinued national reporting requirements. Members receive largely operational information on particular outputs from a service. A revised reporting suite will provide Members with key information more relevant to the delivery of the Council Plan. It was agreed that to ensure there is no gap in performance information for Members the existing Annual Suite of performance indicators and key quarterly indicators will be retained and reported on following current practice until at least October 2020.
6.0SUSTAINABILITY IMPACTS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.